Deciding the work to
be Performed
(Work Breakdown
Structure)
Goals of the Unit
Understanding the transition from project goals to the
project schedule
Introducing the Work Breakdown Structure notation
spm - 2014 adolfo villafiorita - introduction to software project management
!2
Plan
Assess
Feasibility
Formalize
Goals
Execute &
Monitor
Monitor Goals, Cost and
Schedule
Initiate
Define
Schedule
Close
Collect
Outputs
Close
Develop
Release
Kick Off
Activities
Define Costs
[Obtain
Approval]
Change Control & Configuration Management
Quality Management
Risk Management
Human Resource Management
What is a WBS?
A Work Breakdown Structure (WBS
for short) is a (deliverable-oriented)
hierarchical decomposition of the work
to be executed by the project team to
accomplish projects objectives and
create the required deliverable
spm - 2014 adolfo villafiorita - introduction to software project management
!4
WBS Example
1
Software
System
1.1
1.2
Configuration
Management
1.3
Main
Requirements
1.3.1
Detailed
Requirements
1.4
1.5
Mobile Client
Development
Appstore
Deployment
1.3.3
1.3.4
1.3.2
Architecture
Code
[Link]
Dev. Tools
Procurement
User Manual
Tests
[Link]
Unit
Tests
1.6
System
Tests
[Link]
Integration
Tests
spm - 2014 adolfo villafiorita - introduction to software project management
!5
WBS: Remarks
Two formats
Graphical tree (Vision, Graffle, LibreOffice, ...)
Textual outline (MS Word, Text Editor, Outliner, ...)
Uses a decimal numbering system to identify
elements (Ex: 3.1.5)
Shows is contained in relationships
Does not show dependencies nor durations
spm - 2014 adolfo villafiorita - introduction to software project management
!6
Why is it useful?
A WBS establishes the basis for:
Defining the work to be performed in a
project
Showing how various activities are related
to the project objectives
Establishing a framework for defining,
assigning, and monitoring work and costs
Identifying the organizational elements
responsible for accomplishing the work
spm - 2014 adolfo villafiorita - introduction to software project management
!7
WBS Rules of the Thumb
Everything (and nothing else) is in place:
The 100% rule: make sure all work items are there (product oriented WBS are
better suited for this kind of rule)
The ME rule (Mutually Exclusive rule): make sure there are no overlaps in the
definition of the elements (see coupling, below)
No need to make it balanced: all paths do not have to go to the same level
Quality of the WBS is high (*)
Coherence: tasks within a work package should have the same goal;
Coupling: work package dependencies should be minimised, so that
team members can work independently;
Continuity: production work packages should be full-time to maximise
efficiency;
Cost: bottom level work packages should require between one man- week and
one man-month of effort.
taken from
ESA standards
software development
spm - 2014 adolfo villafiorita(*)-Criteria
introduction
to the
software
projectformanagement
!8
When do you stop?
Simple answer: at the work-package level (which,
btw, could be composed of more elementary activities,
which, however, you do not want to trace)
However: how big is a work-package?
According to DOD and NASA Guide to PERT COST: leaves
of the WBS should be no more than 3 months of work or
$100.000 of expenditure
According to other standards: 1-2 weeks for 1-2 people
Mind you though, the level of details depends on the
size of the project...
spm - 2014 adolfo villafiorita - introduction to software project management
!9
WBS Types (1/3)
Product WBS
It develops according to the structure of the outputs that need to
be produced
It can start from a Product Breakdown Structure, when defined
Process WBS
It develops according to the phases in which a project is
organized
For instance: Requirements, Analysis, Design, Testing
Hybrid WBS: both of the above
It mixes process and product
For instance: life-cycle phases at higher levels; component at
lower levels
spm - 2014 adolfo villafiorita - introduction to software project management
!10
WBS Types (2/3)
Organizational WBS and Geographical WBS
Higher levels are organizational units
Lower levels collect the work which is under the responsibility
of a Unit.
Can be useful for highly cross-functional projects
Geographical WBS
Higher levels are geographically distributed teams (e.g. NY
team, Trento Team)
Lower levels collect the work under the responsibility of a team
Remarks: according to the PMBOK, these are not
WBSs. In any case, they are less commonly used.
spm - 2014 adolfo villafiorita - introduction to software project management
!11
WBS Type (3/3)
PWBS: Program
(project) WBS, used
to coordinate all
projects (systems)
CWBS: Contract
WBS, basis for
subcontracting
system development
PWBS Program WBS
System A
CWBS Contract WBS
Program
Project A
Project B
System B
System C
Project C
Contract X
(Used by NASA)
Subsystem 1
Subsystem 2
Subsystem 3
spm - 2014 adolfo villafiorita - introduction to software project management
!12
Product WBS Example
Software
System
Requirements
Document
Architecture
Document
Front End
Middleware
Back End
Site
Templates
Web Pages
SQL
Schema
DB Data
Dynamic
Pages
Admin Intf
Static
Pages
spm - 2014 adolfo villafiorita - introduction to software project management
!13
Process WBS Example
System
Development
Requirements
Analysis
Analysis and
Design
Cycle 1
Scenarios
Analysis
Security
Reqs.
Analysis
Supportability
Requirements
Analysis
Coding
Cycle 2
Testing
Integration
System Test
spm - 2014 adolfo villafiorita - introduction to software project management
Acceptance
Test
!14
WBS Example (MIL-HDBK-881)
WBS Dictionary
A WBS dictionary helps further specify the entries of a
WBS
It might contain title, number, detailed description of the
element, quantities, associated work, contractual items
Rules of the thumb:
it can be done for each entry in the tree.
follow the definition: increase the details as you move down
the tree
a good practice is doing it for the leaves (work-packages)
spm - 2014 adolfo villafiorita - introduction to software project management
!16
WBS Dictionary
Month 1
Work
package
number
Work
package title
Case Study Requirements and Experimentation Site Assessment
Activity type
RTD
Participant
number
Participant
short name
P1
P2
P3
P3
P4
P5
P6
P7
Personmonths per
participant
Objectives
Description
of work
Task 1.
Task 2.
...
Deliverables
D1.1.
D1.2.
Milestones
M1.1.
M1.2.
Start date or starting event: