MS Project
Table of contents
Introduction Define Resource
Design of MS Project Resource scheduling
3 steps to project Resource overallocation
management Tracking project
Customization Printing reports
Steps in Planning Working with multiple
projects
Editing tasks Importing/exporting of
Task scheduling data
Critical path method Formatting views
Pert analysis Customizing tables,views
and forms
Introduction to Project management
What is a project?
Features of project
What is project management?
Project management software(PMS)
What is a Project?
Project can be defined as a
set of tasks or activities
with a defined start and end date
designed to achieve a unique short term goal
and constrained by time, cost and scope and
quality
Co
e
Tim
Resource st
Scope and Quality
Features of Project
Projects are temporary
Project objectives are specific and measurable
Projects are constrained by time, cost and scope
and quality.
Project management
is a process of
planning
tracking
and controlling project
MS Project helps you to
Develop a better plan
Makes calculated projections easy and more
reliable
Detect inconsistencies and problems in the plan
Communicate the plan to others
Track progress and detect potential difficulties
Design of MS Project
Views in MS Project
Gantt chart view
Calendar view
Network diagram view
Task Usage view
Resource sheet view
Resource usage view
Resource graph view
Tracking Gantt
MS Project Window Project
Guide
Title Bar
Menu Bar
Standard
Toolbar
Task
pane
Status
bar
Gantt chart view
Gantt chart
Timescale
Gantt chart
table
Calendar view
Non working
day
Normal Tasks
Milestone
Network diagram view Non Critical
Normal task
Critical
Summary Critical
task milestone
Critical
Normal
task
Task Usage view
Timescale
Resource
Assigned
Task
Resource sheet view
Overallocated
resource
Resource Usage view
Resource Timescale
Assigned
Task
Resource graph view
Percent
Overallocation
Resource
3 steps to project management
Planning project
Tracking project
Closing project
Customizing MS Project
Customizing toolbars and menu
Changing the date format
Changing the currency format
Adjusting the Gantt chart view
Formatting the timescale
Customizing Project environment
Click on Tools menu
Click on Options button
Select View tab button
Select the date time format
from date format dropdown
list
Change $ symbol to Rs. in
Symbol text field
Select the Show outline
number check box
Steps in Planning
Enter Project information
Define a calendar for your project
Create a list of major tasks, sub tasks and
milestones (Using WBS)
Edit tasks, indent tasks, link tasks, add constraints
to tasks
Create resource list and assign resources to tasks
Remove resource overallocation
Optimize duration, cost and quality
Distribute the plan to other members in the project
for review.
Create a final plan
Project information
There are 2 types of Project:
Forward scheduled projects
This projects have a fixed start date
Backward scheduled Projects
This projects have a fixed finish date
Entering project information includes:
Define start date/end date of project
Set Priority of a Project
Steps to enter Project Information
Click on Project menu
Select schedule from start
date from schedule from
dropdown list
Enter Start date of the
project in Start date field
Set the priority for the
project
Note: Priority range is 0-1000
Creating calendar
Project creates the schedule based on the
calendar defined in the project
Types of calendar
Standard
24 hours
Night shift
Objective: Creating a calendar for the project:
To create a calendar you need to:
Set the calendar working time
Add holidays to the calendar
Change hours/day, hours/week, default start time,
default end time etc
Creating a calendar
Click on Tools menu
Click on Change working time
button
Select Standard calendar from
the drop down list
Select the working days in the
week from the calendar box.
Select the nondefault working
option
Enter the working time in the
From and To fields
Select the day which is an
holiday from calendar box
Select non working time option
Click on Options button
Setting Calendar options
Set the week start day.
Set the fiscal year start
Set the default start time
Se the default end time
Set the hours/day
Set the hours/week
Set the days/month
Editing tasks
What is WBS?
Introduction to fields in task table view
Types of task
Summary tasks, Subtasks and milestones
Inserting, copying, moving, deleting tasks
Inserting notes and hyperlinks to tasks
Indenting tasks
Work Breakdown Structure (WBS)
Design Of Car
Design of Brakes Design of Engine Design of body
Chemical design Mechanical design
Fields in Gantt chart table
Fields Description
Task ID Unique Task number
Task Indicator Indicates additional information of task
Task Name Describes information about the task or
action
Duration Total duration of the task in minutes,
hours, days, weeks, months,
Start date Start date of the task
Finish date End date of the task
Predecessor Task which determines start or finish of
successor task
Resource Name The resource/s assigned to the task
Types Of tasks
Summary Task: The major phase of the project
or a group name to collection of similar tasks is
known as summary task
Sub Task (Normal): Task to which resource is
assigned is a sub task
Milestone: Milestone is a decision point, check
point or a major phase completion indicator in
project. Milestone is a task which do not have
resource assigned and has a 0 day duration.
Editing Tasks
Select a cell in the task name field of Gantt chart
table to enter task.
Press tab key to move to the next field
Duration is entered in months, weeks, days, hours
or minutes.
E.g. 1 mo, 2 w, 3 d, 4 h, 45 m
Note: Let project enter the start date and end date
for your project
Insert task: Click on Insert menu Click on insert
task
Delete task: Select the entire row/s to delete
Press delete key
Indenting and linking tasks
Indenting (Outlining) tasks:
Select the sub tasks you want to indent. Click on demote
button on the Standard toolbar.
After performing this operation you can observe that the task
above the indented tasks appears to be bold.
Linking Tasks:
Select the tasks you want to link. E.g. task1 and task2 are to
be linked. Select the 2 tasks.
Click on link button on the Standard toolbar
Unlinking tasks:
Select the tasks you want to unlink.
Click on unlink button on the Standard toolbar.
Note: Always indent the tasks before linking. Do not link
summary task to subtask or another summary task.
Task scheduling
Predecessors and successors
Predecessor is a task whose completion (wholly or
partly) determines the start of the successor
Successor is a task which is dependent on the
completion (wholly or partly) of the predecessor.
There are 4 types of relationship (links) or dependencies
between Predecessor an successor. They are as
follows:
Task Dependencies
Finish to start
Finish to finish
Start to start
Start to finish
Task dependencies
Task Description Relationship
Dependency Diagram
Finish to Start The finish of the predecessor A
determines the start of the B
successor
Finish to Finish The finish of the predecessor A
determines the finish of the B
successor
Start to Start The Start of the predecessor A
determines the Start of the B
successor
Start to Finish The Start of the predecessor A
determines the Finish of the
B
successor
Task Constraints
Flexible constraints
As soon as possible (ASAP)
As late as possible (ALAP)
Start no earlier then (SNET)
Finish no earlier then (FNET)
Inflexible constraints
Start no later then (SNLT)
Finish no later then (FNLT)
Must start on (MSO)
Must finish on (MFO)
Task Constraints
There are 2 types of constraints: 1) Flexible 2) Inflexible
Flexible constraints are date constraints on tasks which allows to increase
the end date of the project
Inflexible constraints are date constraints which does not allow to
increase the end date of the project.
Flexible constraints Inflexible constraints
As soon as possible (ASAP) Start no later then (SNLT)
As late as possible (ALAP) Finish no later then (FNLT)
Start no earlier then (SNET) Must start on (MSO)
Finish no earlier then (FNET) Must finish on (MFO)
Critical Path Method (CPM)
What are critical tasks?
The tasks on the longest sequence in a project whose
delay expands the project schedule are called critical
tasks
What are non-critical task?
The tasks whose delay does not delay the project end date
are called non-critical tasks.
What is a Critical Path?
The series of tasks that must be completed on time for the
project to be satisfactorily completed
What is a CPM?
Critical Path Method is a technique of scheduling tasks in
a project
PERT Analysis
What is PERT?
Project Evaluation and Review Technique; a variant of CPM
where the task duration time is assigned a probability of
completion
Optimistic duration
Pessimistic duration
Expected duration
Resources
What is a Resource?
Types of resources
Work and Material Resource
Difference between Work resource and Material
resource
Creating a resource sheet
Resources
Definition: A resource is an entity which performs effort or
work on the task.
There are 2 types of resources
Work Resource e.g. Man, Equipments and facilities
Material Resource e.g. Cement, Petrol, Diesel, paper etc
Work Resource (WR) Material Resource (MR)
WR is reusable. It can be MR is non reusable. Once
assigned to several tasks. consumed it cannot be used
in other tasks.
It requires a calendar It does not require a
calendar
Resource Cost = (Cost of Resource cost = (Cost/ unit
resource/hr) * (work hours) of the Material resource) *
(no. of units consumed.)
Fields in Resource Sheet Table
Fields Description
Resource Id Unique Id assigned to a resource.
Resource Indicator Symbols indicates Resource overallocation or notes indicator.
Type Describes the type of Resource i.e. Work /Material.
Material Label A label given to the material resource e.g. Petrol is a material resource and its label is
liters.
Initials Abbreviation of resource name e.g. Engineers, Initial -Eng
Group Group name or department name of the resource e.g Resource A, B are belonging to
Finance dept.
Max. Units Describes max no. of units that a task can be assigned
Std. Rate The cost of work/material Resource
Overtime cost The cost of the Work resource if he works more than the max. hrs/day scheduled for the
resource
Cost/use One time Cost of the resource. E.g Deposit on renting a Vehicle
Accrued At Prorated – Cost calculated with work
Start- Cost calculated as soon as the work starts
End –Cost is calculated at the end
Resource scheduling
Work formula
Work= Duration * Units
Assigning resources to tasks
Task types
Fixed units effort driven
Fixed units without effort driven
Fixed duration effort driven
Fixed duration without effort driven
Fixed work
Task types and work formula calculations
Initial Change Fixed Units Fixed Work Fixed Duration
Result Result Result
+Duration +Work -Units -Units
+Units -Duration -Duration +Work
+Work +Duration +Duration +Units
Formulas: D*U=W D*U=W D*U=W
Resource Overallocation
What is resource overallocation?
Example of resource overallocation
Identifying resource overallocation
Viewing and filtering overallocation
Strategies to remove resource overallocation
Resource Overallocation
A resource is overallocated when it is assigned to
work more hours during a given time period than it
has available for work on the project.
Identifying Resource overallocation
The resource sheet, Resource Usage, and Resource
allocation views all highlight overallocated resource names
by using red text.
Strategies for eliminating Resource overallocations
Increase the availability of the resource during the time
period in question.
Reduce the total work assigned to the resource in that time
period.
Tracking
Save a baseline
Select a tracking method and prepare a custom view for
tracking
Incorporate actual progress information into the project
Check the status of tasks
Modify the project in light of tracking information
Track issues related to the project
Request periodic text-based assessments of general
status from key resources
Publish new and changed assignments to Project Server
Tracking View % Duration
Complete
Act. Start
date
Act. Finish
date