Chapter 2 Project Management
Chapter 2 Project Management
MANAGEMENT
Prepared by:
YAU’MEE HAYATI HJ MHD YUSOF
NUR HAZWANI MOHAMAD ROSELI
UiTM TERENGGANU
Course Description
▪ a temporary endeavor,
▪ having a defined beginning and
end
▪ undertaken to meet particular
goals and objectives
▪ usually to bring about beneficial
change or added value.
Project Management Terminology
CLICK ON SUBJECT
Project Management Terminology
CLICK ON SUBJECT
Dependency
CLICK ON SUBJECT
Gant Chart
• Defining
• Organizing
• Tracking
• Communicating info about a
project
Note :
This tutorial will use Microsoft Project
2010. However you may use any version
as your wish because the function is still
the same
Tutorial 1
(Create New Project)
INSTRUCTION
Step 1 : Create a file
1. Click on File
2. Click on New Command
3. Choose Blank Project
INSTRUCTION
Step 1 : Setup Calendar
1. Click on Project.
2. Choose Project Information.
3. Choose Standard Calendar
from Calendar drop down
menu.
Step 2 : Make new Calendar
1. Click on Tools.
2. Choose Change Working Time.
3. Create New Calendar
4. Tick on make a copy of
Standard Calendar
5. Rename your new calendar
6. Go back to Project Information, ;
change Standard calendar to
your new rename calendar..
Tutorial 3
(Task & Recurring Task)
INSTRUCTION
Step 1 : Task Entry
1. Click on Task Entry.
2. Enter subtasks.
3. For summary task, highlight the
task and choose 🡪 and 🡪 on
your menu to change it.
Step 2 : Recurring Task
1. Click on Insert
2. Choose Recurring Tasks.
3. Key in your recurring tasks
4. Tick on Recurrence Patern,range
Of Recurrence and Calendar for
the task.
5. Click ok.You will see a symbol
representing recurring task in
information column.
Tutorial 4
(Notes & Milestone)
INSTRUCTION
Step 1 : Notes Entry
1. Double Click on task.
2. Choose Notes on Summary Task
Information.
3. Choose tasks, write your notes.
4. Then , click ok.
Step 2 : Milestones
1. Double click on task given.
2. At General, tick on Mark
task as milestone.
3. Or you may go to any tasks,
choose duration , change
duration to 0 or Zero
4. Milestone will marks as
diamond.
Tutorial 5
(Resources)
INSTRUCTION
Step 1 : Resource List
1. Click on View.
2. Choose Resource Sheet
3. Type your Resource Name ,
Material or Activity used in the
project.
Step 2 : Assigning Resources
1. Go back to Task Entry
2. Double click any tasks.
3. In Task Information, choose
Resources.
4. Choose task to be assigned to
dedicated resources.
5. Click ok.
6. You will see the name of
resources appear in the Gant
Chart and Resources column.
Tutorial 6
(Dependency)
INSTRUCTION
Step 1 : Identify Dependency
1. Identify which task to SS,FF,FS
or SF..
2. Identify Successor and
Predecessor.
Step 2 : Assign Dependency
1. Double click on any Tasks
2. On Task Information ,choose
Predecessor.
3. Choose Task Name as
Successor or Predecessor, and
Type of Dependency.
4. Click ok.
5. You will see a symbol
representing dependency of
your choice appear in Gant
Chart bar.
Tutorial 7
(Timescale)
INSTRUCTION
Step 1 : Identify Time Scale
1. Double click on Gant Chart Timeline.
2. Timescale dialog appears with Four
tabs Top tier, Middle Tier, Bottom Tier
and Non Working To.
3. Choose your time scale based on
your project timeline.
Step 2 : Formatting Time Scale
1. Click on Middle Tier
2. Choose Middle Tier Formatting.
3. Choose Time Scale Option.
(Note: Two layer time scale is
the most appropriate)
4. Change your non working time
based on your project.
Tutorial 8
(Produce Report)
INSTRUCTION
Step 1 : Notes Entry
1. Go to menu File
2. Choose Print 🡪 Page Setup.
3. Choose Margin , write Header
and Footer to format your report.
4. Print Preview the report.
Step 2 : Overview Report
1. Click on Report
2. Choose template of your report.
3. Close the Report dialog if you
have produce desired report.
TUTORIAL 9
(Project View)
INSTRUCTION
Step 1 : Changing View
1. Click on View
2. Choose any type of view.
3. If you choose many view, you can see all
view by using splitting window.
4. To do that you can click on Window
menu, select Split.
TUTORIAL 10
(Print Report)
INSTRUCTION
Step 1 : Print file
1. Click on File menu.
2. Choose Print.
3. Choose Printer you want to print
from.
4. Select ALL print range area.
5. Select Dates in Timescale section.
6. Then ok.
Benefit of Project Management
• Better understanding of overall project goals
• Better understanding of project tasks,
durations, schedule dates, and costs
• More organized and streamlined way to
manage the many details of a project
• More accurate and reliable project status
information
• More efficient use of project resources
• Better communication between
management, the project manager, and
others
• Faster response to conflicting project
goals
• Greater awareness of project progress
• Faster project completion
• Lower project costs
• Fewer project failures
My First Exercise in Microsoft
Project 2013
WBS:
Task Duration
Order kit and schedule delivery (week one) 1 day
Preparation (summary task)
Site preparation – clear and level the landscape (week one) 2 days