Pmo Case Study
Pmo Case Study
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 1
PMO Implementation - Modern Building Case Study
Submitted to:
Name LinkedIn Profile
Participants
The following participants contributed to this case study.
Name LinkedIn Profile
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 2
PMO Implementation - Modern Building Case Study
Table of Contents
a. PMO Value Ring Methodology Overview ....................................................................................................... 4
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 3
PMO Implementation - Modern Building Case Study
The PMO Value Ring methodology is a comprehensive framework designed to maximize the value a PMO
delivers to its organization. This methodology consists of eight key steps:
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 4
PMO Implementation - Modern Building Case Study
1. Company Profile
Company Name Modern Building
Industry Construction Solutions
Company Size Mid Company
2. Portfolio Value
Year Portfolio Value
2021 SAR 35,000,000
2022 SAR 32,000,000
2023 SAR 37,800,000
2024 SAR 31,250,000
Average SAR 34,012,500
3. Mission
We aim to provide our clients with the highest-quality structure projects that exceed their expectations and
perfectly meet their demands, fitting their usage and routine.
4. Mission
We aim to provide our clients with the highest-quality structure projects that exceed their expectations and
perfectly meet their demands, fitting their usage and routine.
5. Strategic Objectives:
Strategic Objectives
1 Improve Governance
2 Effective Engagement
3 Decision-Making Enabler
4 Enhance Collaboration
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 5
PMO Implementation - Modern Building Case Study
6. Organizational Structure
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 6
PMO Implementation - Modern Building Case Study
Benefits
Functions
# Strategic Objective Benefits PMO Function Realization
Categories
Time Frame
Manage Resource
Better control over
1 Improve Governance
project teams
Allocation Between Tactical Short-Term
Projects
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 7
Manage Provide Provide Provide Advice Promote Manage Manage
Lessons Project Project to Upper Project People in Resource
Learned Management Management Management Management Projects Allocation
Meetings Methodology Tools and in Decision- within the Between
PMO Function
Information Making Organization Projects
Systems
No formal There is no Essential, Minimal advice There is little to Minimal people Ad hoc resource
lessons learned standardized disconnected provided. no promotion of management. allocation. No
process. methodology. tools. Manual Reactive PM practices. Roles unclear. formal process.
Initial (1)
processes. approach.
Occasional Basic PM Some integrated Basic reporting Some PM Basic role Basic resource
lessons learned methodology PM tools. Partial for awareness definitions and allocation
sessions— defined but automation. management. initiatives. assignments. process in place.
limited follow- inconsistently Some proactive Limited Limited Limited visibility
up. applied. advice. organizational performance across projects.
Developing (2)
buy-in. tracking.
PMO Implementation - Modern Building Case Study
Regular lessons Comprehensive Comprehensive Regular, Regular PM Clear roles and Structured
learned in PM PM toolset. structured promotion responsibilities. resource
meetings. methodology Good advice to activities. Good Regular allocation
Systematic consistently integration and management. organizational performance process. Good
knowledge applied across automation. Data-driven support. reviews. visibility across
Established (3)
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology
application. organizational capabilities. analytics for and innovation and career balance across
Optimized (4)
4
3
2
2
1
1
3
Maturity Level
Maturity %
75%
60%
50%
25%
25%
75%
100%
8
58.57142857 F. Weight
PMO Implementation - Modern Building Case Study
This report evaluates the organization's Project Management Office (PMO) functions. The
assessment covers seven critical areas of PMO functionality, examining their current maturity
levels, benefits, and strategic importance. Our analysis reveals a mixed landscape of PMO
maturity, with some functions performing at an optimized level while others require significant
development.
Key findings:
1. Introduction
The Project Management Office (PMO) ensures effective project execution, governance, and strategic
alignment within an organization. This report evaluates the current state of our PMO across seven essential
functions, providing insights into areas of strength and opportunities for improvement.
2. Methodology
1. Initial
2. Developing
3. Established
4. Optimized
Each PMO function is evaluated against this scale, with consideration given to its strategic objective,
benefits, and realization timeframe.
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 9
PMO Implementation - Modern Building Case Study
3.3.1 Strengths
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 10
PMO Implementation - Modern Building Case Study
4. Impact Analysis
The PMO functions are categorized into strategic, tactical, and operational levels:
The current maturity levels indicate a more robust performance in operational and some tactical areas, with
strategic functions requiring significant development.
The organization is better positioned to realize short-term benefits, particularly resource allocation. However,
long-term strategic benefits are at risk due to the low maturity of PM promotion and management advice
functions.
5. Recommendations
Based on the assessment, we recommend the following actions to enhance PMO maturity and
effectiveness:
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 11
PMO Implementation - Modern Building Case Study
6. Implementation Roadmap
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 12
PMO Implementation - Modern Building Case Study
This table shows the diversity of opinions among stakeholders and the weight of stakeholders’ opinions
related to the recommended benefits (this evaluation can help calculate how much each function would
contribute to achieving stakeholders' expectations).
portfolio
and other
director
weight projects weight relevant weight
# group of benefits relevance
(7-1) managers (7-1) departments (7-1)
(45%)
relevance (25%)
(30%)
B1 Better control over project teams B1 7 B4 7 B1 7
Better definition of roles and
B6 6 B5 6 B2 6
B2 responsibilities
Better communication among areas
B4 5 B1 5 B6 5
B3 of the organization
Greater integration among areas of
B3 4 B3 4 B5 4
B4 the organization
Improved availability of information
B2 3 B2 3 B4 3
B5 for better decision-making
Greater agility in project
B7 2 B7 2 B3 2
B6 management decision-making
Effective transfer of knowledge in
B5 1 B6 1 B7 1
B7 project management
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 13
PMO Implementation - Modern Building Case Study
Recommended Functions
Manage Resource Allocation
Top 4 Benefits
Provide Advice to Upper
Between Projects
[Link]
Methodology
Meetings
Making
BAI
0.75 0.5 0.25 0.25 0.25 0.25 0.25 69%
23.5
23.5
75%
B1
B1
18.2
50%
B4
B2
14.7
50%
B6
B3
13.8
75%
B2
B4
50%
B5
75%
B6
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 14
PMO Implementation - Modern Building Case Study
%Relevance %Accumulated
Potential Functions (EAI) relevance
#
1 Manage Resource Allocation Between Projects 19.78 19.78
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 15
PMO Implementation - Modern Building Case Study
satisfaction value
of stakeholders'
The top four
stakeholders'
short - term
% achieving
long-term
Mid-term
functions
needs by
Top four benefits that can be functions
needs
# achieved based on the mix participate in
manager matrix achieving
potential benefits
Manage Resource
Better control over
1 Allocation 60 25 15
project teams Between Projects
Better definition of
Manage Lessons
4 roles and Learned Meetings
45 25 30
responsibilities
AVG 30.75 36.75 32.5
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 16
PMO Implementation - Modern Building Case Study
1. Focus on Resource Management: Prioritize the "Manage Resource Allocation Between Projects" function,
which is the most relevant (23.5%) and contributes significantly to better control over project teams.
2. Enhance Decision-Making Support: Strengthen the "Provide Advice to Upper Management in Decision-
Making" function to improve integration among organizational areas and support long-term benefits.
3. Standard Methodology: Invest in the "Provide Project Management Methodology" function to enhance agility
in project management decision-making and support mid-term benefits.
4. Knowledge Management: Implement a robust "Manage Lessons Learned Meetings" process to improve the
definition of roles and responsibilities and balance short-term and long-term benefits.
5. Balanced Approach: Maintain an even focus distribution across short-term, mid-term, and long-term
functions to ensure comprehensive PMO effectiveness.
6. Stakeholder Alignment: Continue to monitor and improve stakeholder satisfaction, aiming to increase the
current 69-70% achievement rate of stakeholder needs.
7. Continuous Improvement: Regularly review and adjust the mix of PMO functions to ensure ongoing
alignment with organizational needs and stakeholder expectations.
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 17
PMO Implementation - Modern Building Case Study
Resource Allocation
To efficiently allocate resources across multiple Agile Project management software (e.g., Jira, Version
Objectiv
Responsibilities
projects in an agile environment, ensuring One) Resource management tools (e.g., Resource Guru,
e
- Resource management tools (e.g., Resource Use visual boards for transparent resource
Guru, Forecast allocation.
- Capacity planning spreadsheets Conduct regular capacity planning meetings.
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 18
PMO Implementation - Modern Building Case Study
Executive Advisory
To provide timely, data-driven insights and APMO: Collect and analyze data and prepare reports and
Responsibili
Objective
ties
enabling informed decision-making aligned
reports, make decisions, provide feedback
with agile principles and organizational
goals.
- Agile metrics and KPIs from all projects Decision turnaround time
- Strategic organizational objectives Percentage of recommendations implemented.
Matrix
Inputs
communications
Power BI)
Use data visualization to present complex
Tools
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 19
PMO Implementation - Modern Building Case Study
Responsibilitie
methodology, provide training, and
Objective
s
organizational agility and project success rates development and provide training and
mentoring. Upper Management: Approve
and support the methodology adoption
Methodology adoption rate across
- Current project management practices
projects
Impact on project success rates
- Industry best practices in agile methodologies (time, budget, quality, customer
Matrix
Inputs
satisfaction)
- Feedback from project teams and stakeholders Training completion rates
Continuous improvement
suggestions received and
- Organizational goals and constraints implemented.
Methodology updates are released
- Customized agile methodology documentation
Service Levels
quarterly
Training programs available
Outputs
continuous improvement.
Develop a scalable methodology
- Agile project management tools configured to support
that can adapt to different project
the methodology
sizes and types.
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 20
PMO Implementation - Modern Building Case Study
Responsibilitie
To facilitate the continuous capture, sessions and maintain the knowledge base. Project
Objective
s
across all projects, fostering a culture of constant Organize and categorize lessons for easy retrieval
improvement and knowledge sharing.
Matrix
Inputs
projects
Improvement in project performance
- Stakeholder feedback
metrics
Participation rate in lessons learned
- Incident reports and resolution details
sessions
Lessons learned sessions conducted at the
- Lessons learned database
Service
Levels
sessions application.
- Agile retrospective tools (e.g., FunRetro, Integrate lessons learned reviews into
Retrium) regular project rituals.
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 21
PMO Implementation - Modern Building Case Study
Responsibilitie
on project initiation, continuation, or
Objective
To manage the organization's project portfolio using agile termination. Project Managers: Provide
principles, ensuring strategic alignment, optimal resource project status updates and forecasts.
s
utilization, and maximized value delivery. Upper Management: Set strategic
priorities and review portfolio
performance
- Organizational strategic objectives Portfolio ROI
- Project proposals and business cases Strategic alignment score
Matrix
Inputs
Service Levels
adjustment
Monthly portfolio performance
- Resource allocation recommendations
Outputs
reports
Weekly updates on portfolio
- Portfolio performance reports
Kanban board
- Agile portfolio management software (e.g., Clarity PPM, shortest job first)
Planview)
Implement rolling wave planning
Tools
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 22
PMO Implementation - Modern Building Case Study
PMO Objectives
Main Strategic
# Function Strategic Objective Objective
Optimize Resource Utilization: Resources Effective Engagement
Manage Resource
Between Projects
Decision-Making
Management in
2
management
Align Projects with Business Objectives: Improve Governance
Ensure project outcomes contribute to
overall business strategy and goals.
Methodology
Management
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 23
PMO Implementation - Modern Building Case Study
58.8%
Project Priority
35% 4.5 1.5 33.3% 11.7%
Alignment Score
Resource Bottleneck 20%/quar
25% 14% 70.0% 17.5%
Reduction ter
65.7%
Business Objective
35% 4.5 2 44.4% 15.6%
Alignment Score
Data-Driven Insight
25% 90% 60% 66.7% 16.7%
Utilization
58.7%
Project Success Rate 35% 85% 66% 77.6% 27.2%
Methodology
25% 4.5 60% 13.3% 3.3%
Effectiveness Score
Knowledge Base
35% per project 14 70.0% 24.5%
Utilization per month
Continuous
Improvement 25% 4.5 3.5 77.8% 19.4%
Impact Score
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 24
PMO Implementation - Modern Building Case Study
Classifi
# # KPI Description equation limits Data source
cation
Measures the Project
Utilization
Resource
lagging
Manage Resource Allocation
60%
70%
85%
95%
Rate
1
Project priority
Alignmen
leading
Assesses how well
Priority
Project
t Score
matrix, resource
2.7
3.5
4.5
resource allocation aligns score * Resource allocation
2
5
with project priorities allocation
%)) / Total projects
reports
(Number of bottlenecks in
the previous period - Number Project delay
Bottleneck
Reduction
leading
of bottlenecks in the current reports,
0.06
0.1
0.2
0.3
bottlenecks caused by
3
ion Rate
lagging
0.5
0.6
0.8
0.9
decisions that are decisions / Total Number of implementation
4
Decision
Alignment Score
leading
advised decisions align assessments,
3.8
4.5
4.5
ratings (1-5 scale) for each
5
5
with overall business business
decision
objectives strategy
documents
Tracks the percentage (Number of advice items with Advice
Data-Driven
Utilization
leading
Insight
100%
of advice that data-driven insights / Total documentation,
65%
75%
90%
6
leading
100%
standardized methodology /
75%
80%
95%
(Number of successful
lagging
Project
70%
85%
95%
effectiveness of the
Score
3.5
4.5
4.5
5
y
project management
surveys (1-5 scale) stakeholder
methodology
feedback forms
Measures the
Lessons Learned
Lessons learned
Implementation
Manage Lessons Learned Meetings
percentage of
(Number of lessons database,
lagging
50%
75%
90%
Rate
10
logs, user
Utilization
accesses
accesses
10
20
30
assessments
Improvement
Impact Score
Continuous
impact of lessons
surveys,
leading
3.5
3.5
12
learned on project
5
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 25
PMO Implementation - Modern Building Case Study
Resource Utilization Rate Decision Implementation Rate Methodology Adoption Rate Lessons Learned Implementation Rate
Total hours utilized Total available hours Previous cuurent rate Targeted Number of implemented decisions Total number of advised decisions Previous cuurent rate Targeted Number of projects using standardized methodology Total number of projects Previous cuurent rate Targeted Number of lessons implemented Total number of lessons identified Previous cuurent rate Targeted
352 500 63 70.4 80 35.2 20 35 67 57.1 80 28.57143 20 35 67 57.1 95 24.06015 63 88 69 71.6 75 38.18182
17 10 13 23 28 38 6 3
Previous current Previous current Previous current Previous current
12% 8% 5%
21% 16%
29% 29%
40%
60%
71% 71%
79% 84%
88% 92% 95%
Project Priority Alignment Score Business Objective Alignment Score Project Success Rate Knowledge Base Utilization
(Sum of (Project priority
Total number of completed
score * Resource Total projects Previous cuurent rate Targeted Average score of alignment ratings Previous cuurent rate Targeted Number of successful projects Previous cuurent rate Targeted Average number of knowledge base accesses per project per month Previous cuurent rate Targeted
projects
allocation %))
25 7 2 3.57 4.5 27.77778 2.70 2.00 2.70 4.50 21 17.00 25.00 66.00 68.00 85.00 28 17.00 14.00 17.00 20.00 29.75
3 1 3 2 19 17 6 3
20% 15%
21% 22%
30%
40%
44% 44%
56% 56%
60%
70%
78% 80%
79% 85%
Resource Bottleneck Reduction Data-Driven Insight Utilization Methodology Effectiveness Score Continuous Improvement Impact Score
(Number of bottlenecks
in previous period - Number of bottlenecks in Number of advice items with data-
Previous cuurent rate Targeted Total number of advice items Previous cuurent rate Targeted Average score from project manager and stakeholder surveys (1-5 scale) Previous cuurent rate Targeted Average score from project team surveys (1-5 scale Previous cuurent rate Targeted
Number of bottlenecks in previous period driven insights
current period)
12 80 14 15.00 20 18.75 45 60 60 75.0 90 20.83333 3 2.7 3.0 4.5 16.66667 3.9 3.5 3.9 4.5 21.66667
6 5 30 15 2 2 1 1
Previous current Previous current Previous current Previous current
17% 13%
25% 22%
30% 33% 33%
40%
60%
70% 67% 67%
75% 78%
83% 87%
Manage Resource Allocation Between Projects performance Provide Advice to Upper Management in Decision-Making Provide Project Management Methodology Manage Lessons Learned Meetings
previous 1 2 3 current previous 1 2 3 current previous 1 2 3 current previous 1 2 3 current
58.80 70.30 60.20 79.40 81.73 65.70 67.50 68.90 70.00 70.40 58.70 55.00 62.80 66.40 68.73 80.07 77.50 72.00 84.00 89.60
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 26
PMO Implementation - Modern Building Case Study
Roles Analysis
# Function Required Roles Role Main objective
Oversees resource prioritization and allocation across projects to align with
Portfolio Manager
Manage Resource strategic goals
1 Allocation Between Coordinates and manages the distribution and utilization of resources to
Projects Resource Manager meet project needs effectively.
Lessons Learned Organizes and facilitates lessons learned meetings, ensuring best practices
Coordinator and insights are captured and shared
Manage Lessons
4
Learned Meetings Collects data and analyzes lessons learned to provide actionable insights for
PMO Analyst future project improvement
Headcount
Headcount
Required
Frequency
Function
# Function Evaluation
Manage Resource
Allocation Resource allocation is a continuous and critical PMO function, as multiple projects often
Between Projects compete for limited resources. The Portfolio Manager and Resource Manager will be needed
High
1 2
frequently to ensure optimal resource use, especially during project planning, execution, and
reallocation phases.
Provide Advice to The PMO Director and Project Management Consultant will regularly engage during crucial
Moderate to High
Upper decision-making moments, such as project prioritization, strategic shifts, and issue escalations.
2 Management in 2 While not required as continuously as resource allocation, this function will be frequently
Decision-Making: requested during executive reviews, strategy meetings, or when significant project
adjustments are necessary.
Provide Project The Project Management Methodology Specialist and PMO Analyst ensure consistent
Management methodology application across projects. This function may be periodically reviewed, updated,
Moderate
3 Methodology 2 or enforced, particularly at the start of new projects or when processes or standards change.
As methodologies tend to be stable once set, this function may not be required as often but is
essential for maintaining project consistency.
Manage Lessons
Low to Moderate
Learned Meetings Lessons Learned meetings usually occur at the end of a project or phase. This function will be
required less frequently than ongoing activities like resource allocation or decision-making
4 2
advice, but it remains critical for continuous improvement. The Lessons Learned Coordinator
and PMO Analyst will be engaged primarily during project closures or post-mortem reviews.
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 27
PMO Implementation - Modern Building Case Study
Competencies Analysis
M R M R M R M R
PMO Member
0.35 0.25 0.20 0.20
Amjad Alghamdi 4 1.40 4 1.00 3 0.60 3 0.60 90.0%
Usama 2 0.70 3 0.75 1 0.20 2 0.40 51.3%
Amin Mohammed 3 1.05 4 1 3 0.6 4 0.8 86.3%
88.13%
Ibrahim Alhaj 3 1.05 3 0.75 2 0.40 2 0.40 65.0%
Reem Al-Qarni 2 0.70 1 0.25 2 0.40 1 0.20 38.8%
Abeer Al-Khaled 1 0.35 1 0.25 1 0.20 3 0.60 35.0%
Ahmad Al-Hafi 2 0.70 3 0.75 2 0.40 4 0.80 66.3%
Mohammed Al-Amri 1 0.35 1 0.25 1 0.20 1 0.20 25.0%
F2-C Strategic
Planning
Decision
Making and Resource Project
and Problem Optimization Management CAIPp CAIPf
Execution Solving
M R M R M R M R
PMO Member
0.20 0.15 0.40 0.25
Amjad Alghamdi 2 0.40 4 0.60 2 0.80 2 0.50 57.5%
Usama 3 0.60 2 0.30 4 1.60 4 1.00 87.5%
Amin Mohammed 2 0.4 3 0.45 2 0.8 2 0.5 53.8%
Ibrahim Alhaj 3 0.60 4 0.60 2 0.80 4 1.00 75.0% 81.25
Reem Al-Qarni 2 0.40 1 0.15 2 0.80 1 0.25 40.0% %
Abeer Al-Khaled 1 0.20 1 0.15 1 0.40 3 0.75 37.5%
Ahmad Al-Hafi 2 0.40 3 0.45 2 0.80 4 1.00 66.3%
Mohammed Al-Amri 1 0.20 1 0.15 1 0.40 1 0.25 25.0%
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 28
PMO Implementation - Modern Building Case Study
F3-C Methodolog
y
Developmen
Training and
Developmen
t
Data Analysis
and
Interpretation
Reporting
and
Visualization
CAIPp CAIPf
t
M R M R M R M R
PMO Member
0.35 0.20 0.30 0.15
Amjad Alghamdi 3 1.05 2 0.40 2 0.60 1 0.15 55.0%
Usama 2 0.70 2 0.40 4 1.20 2 0.30 65.0%
Amin Mohammed 3 1.05 3 0.6 3 0.9 1 0.15 67.5%
Ibrahim Alhaj 2 0.70 2 0.40 3 0.90 1 0.15 53.8%
78.75
Reem Al-Qarni 1 0.35 3 0.60 4 1.20 3 0.45 65.0%
%
Abeer Al-Khaled 2 0.70 2 0.40 1 0.30 3 0.45 46.3%
Ahmad Al-Hafi 2 0.70 2 0.40 4 1.20 4 0.60 72.5%
Mohammed Al-
4 1.40 4 0.80 3 0.90 2 0.30 85.0%
Amri
F4-C Facilitation
Skills
Knowledge
Managemen
t
Communicatio
n Skills
Continuous
Improvemen
t Mindset
CAIPp CAIPf
M R M R M R M R
PMO Member
0.30 0.25 0.25 0.20
68.8
Amjad Alghamdi 3 0.90 2 0.50 3 0.75 3 0.60
%
65.0
Usama 3 0.90 3 0.75 3 0.75 1 0.20
%
68.8
Amin Mohammed 2 0.6 3 0.75 4 1 2 0.4
%
75.0
Ibrahim Alhaj 2 0.60 4 1.00 4 1.00 2 0.40 80.00
%
77.5 %
Reem Al-Qarni 4 1.20 2 0.50 4 1.00 2 0.40
%
82.5
Abeer Al-Khaled 4 1.20 2 0.50 4 1.00 3 0.60
%
Ahmad Al-Hafi 2 0.60 2 0.50 4 1.00 4 0.80 72.5%
Mohammed Al-
2 0.60 3 0.75 3 0.75 3 0.60 67.5%
Amri
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 29
PMO Implementation - Modern Building Case Study
Roles Cards
Field Details
Job Title sn
Department [Insert Department]
Reports To [Insert Reporting Manager]
• Eight key roles were identified: Portfolio Manager, Resource Manager, PMO Director, Project Management Consultant,
Project Management Methodology Specialist, PMO Analyst, and Lessons Learned Coordinator.
• Each role has a specific objective aligned with the four essential functions.
2. Function Frequency and Required Headcount
• Resource Allocation: High frequency, 2 headcounts (Portfolio Manager and Resource Manager)
• Advice to Upper Management: Moderate to High frequency, 2 headcounts (PMO Director and Project Management
Consultant)
• Project Management Methodology: Moderate frequency, 2 headcounts (Methodology Specialist and PMO Analyst)
• Lessons Learned Meetings: Low to Moderate frequency, 2 headcounts (Lessons Learned Coordinator and PMO
Analyst)
3. Competency Assessment
The assessment was conducted using a Competency Assessment Index (CAI) for each function, evaluating team
members on various skills:
• F1-C (Resource Allocation): Strategic Planning, Decision Making, Resource Optimization, Project Management
• F2-C (Advice to Upper Management): Strategic Leadership, Organizational Awareness, Change Management,
Performance Management
• F3-C (Project Management Methodology): Methodology Development, Training and Development, Data Analysis,
Reporting and Visualization
• F4-C (Lessons Learned Meetings): Facilitation Skills, Knowledge Management, Communication Skills, Continuous
Improvement
4. Team Performance
• The team showed varying levels of competency across the four functions.
• Top performers for each function:
o F1-C: Amjad Alghamdi (90.0%) and Amin Mohammed (86.3%)
o F2-C: Usama (87.5%) and Ibrahim Alhaj (75.0%)
o F3-C: Mohammed Al-Amri (85.0%) and Ahmad Al-Hafi (72.5%)
o F4-C: Abeer Al-Khaled (82.5%) and Reem Al-Qarni (77.5%)
Important Details
1. The assessment used weighted scoring for each competency within the functions.
2. Overall team performance varied across functions, with the highest average F2-C (Advice to Upper Management)
score at 88.13%.
3. Some team members consistently performed across functions, while others had strengths in specific areas.
4. The process identifies both individual and team competency gaps, allowing for targeted development and resource
allocation.
Implications
1. The results can guide training and development initiatives to address competency gaps.
2. Project resource allocation can be optimized based on individual strengths identified in the assessment.
3. The PMO can leverage high-performing individuals in each function to mentor others and improve overall team
performance.
4. Regular reassessment using this methodology can track progress and evolving competency needs within the PMO.
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 31
PMO Implementation - Modern Building Case Study
Maturity Score
100.00% 83.00%
80.00% 64.00%
53.00% 48.00%
60.00%
40.00%
20.00%
0.00%
MANAGE RESOURCE PROVIDE ADVICE TO PROVIDE PROJECT MANAGE LESSONS
ALLOCATION BETWEEN UPPER MANAGEMENT MANAGEMENT LEARNED MEETINGS
PROJECTS IN DECISION-MAKING METHODOLOGY
Detailed Analysis
1. Managing Resource Allocation Between Projects (64% - Established)
Current State:
• Formal resource allocation process implemented.
• Regular resource forecasting was conducted.
• Proactive resource management practices in place
• Minimal resource conflicts observed.
• Good visibility of resource availability
Target: Maintain Optimized level
Improvement Actions:
• Optimize the resource allocation process.
• Implement advanced resource forecasting and modeling.
• Develop strategic resource management practices.
• Implement systems to prevent resource conflicts.
• Achieve complete visibility and optimization of resource utilization.
2. Providing Advice to Upper Management in Decision-Making (48% - Developing)
Current State:
• Some regular interaction with upper management has been established.
• Basic reporting structure in place
• Mix of proactive and reactive advisory services
• Some data-driven insights were provided.
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 32
PMO Implementation - Modern Building Case Study
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 33
PMO Implementation - Modern Building Case Study
Part-
7 Ahmad Al-Hafi Lebanese PMO Analyst 8000 900 1200 2100 110100
time
Project
Mohammed Al- Management Full-
8 Saudi 12360 1112.4 1200 1100 163968.8
Amri Methodology time
Specialist
SAR 1,102,592.80
SAR 119,640.00
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 34
PMO Implementation - Modern Building Case Study
Low-quality projects
Lack of Sponsorship
Lack of leadership
unmanaged risks
Function Contribute to the solution
median probabilities of each function to solve the problem
# of the problem
Manage Resource Allocation
1 10 40 10 10 15 25 15 5 10 15 15 15 35 10
Between Projects
Provide Advice to Upper
2 40 25 15 15 15 15 25 40 35 15 15 15 15 35
Management in Decision-Making
Provide Project Management
3 10 15 40 15 35 30 30 15 15 35 30 35 25 25
Methodology
4 Manage Lessons Learned Meetings 15 10 25 25 25 20 20 15 15 20 15 25 15 20
ROI calculations
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 35
PMO Implementation - Modern Building Case Study
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 36
PMO Implementation - Modern Building Case Study
Project Management Office - Certified Practitioner (PMO-CP™) - PMO Value Ring Methodology 37