CON-2300MP Control System Manual
CON-2300MP Control System Manual
A Sheet: 1 of 29
INDEX Page.
1. INTRODUCTION ......................................................................................................2
2. INSTALLATION AND SAFETY REGULATIONS.........................................................3
3. DESCRIPTION OF THE AUTOMATIC SYSTEM.......................................................4
3.1 Description of the control elements of the group module...........5
3.2 Description of the signaling and measurement system of the group module… 7
3.3 Description of the control elements of the network module...............9
3.4 Description of the signaling and measurement system of the network module….. 11
3.5 Description of the system alarms.....................................................13
3.6 Description of the auxiliary elements of the equipment ..................................23
3.7 Description of the special equipment elements ................................24
4. MODES OF OPERATION...........................................................................25
4.1 Out of service system..............................................................25
4.2 Switching between networks ……………………………………………………..26
4.3 Manual operation with group............................................................27
4.4 Automatic operation due to network failure with group.............................30
4.5 Automatic operation by remote signal or time control................33
5. MAINTENANCE AND FAULT LOCATION ...........................................34
5.1 Maintenance ...........................................................................................34
5.2 Fault localization .............................................................................34
6. PLANS AND SCHEMES
Situation plan of elements in the CON-2300MP equipment.
Electrical diagram of the switching panel.
1. INTRODUCTION
The CON-2300MP switching control system is comprised of three modules.
of control, is designed to automatically control a switching system
power electrical between two network supplies and a generator supply
automatic startup. It performs load transfers between networks or between the network and
group through a interlocked switching system to avoid the maneuver
simultaneous between the group and either of the two networks.
The CON-2300MP system detects the failure of the power supply from any of the
Networks or receive a commissioning order of the group (from the programmer of
operation of the optional equipment, or of a remote control system); then it gives
a start signal to the automatic switchboard of the group and controls the load transfer
group networks through signals given to the power circuit breakers of the panel
switching.
Modes of operation:
Before the equipment assembly, the following checks must be carried out:
• Check the nominal supply voltage of the equipment. See indication on the equipment itself.
Equipment. Standard power supply: Three-phase 400 V AC with neutral (other upon request)
Tensions). Frequency: 50/60 Hz.
• Check that the rated current of the circuit breakers is suitable for the installation.
• Check that the connections have been made according to the 'Electrical Diagram of
switchboard
• Check that the panel has its ground terminal connected to a grounding point.
effective.
• Check that the insulation of the electrical installation is correct according to the
Low Voltage Regulation.
• Check that the alternator neutral complies with the 'grounding' regulation.
in one of the following three systems: TT (neutral to earth and masses to earth with grounds
independents); TN (neutral to ground and masses to neutral); IT (isolated neutral and masses to
Earth). The system commonly used in Spain is the TT.
Safety precautions:
• Do not touch the electrically live parts of the panel or the cables or conductors of
interconnection with no part of the body or with any conductive object of the
electricity that is not properly insulated.
• In fires caused by the electrical system, only fire extinguishers may be used.
of class BC or ABC. Never use water or foam extinguishers if the group or
The team is under pressure.
• In case of an electrocution accident, do not touch the victim with your hands.
naked until the power supply has been disconnected. If
this last one is not possible, the separation of the injured person will have to be carried out at
through intermediate elements that are electrical insulators, or by being situated
about an electrical insulator and dragging the injured person away from the electrical contact.
The entire automatic system consists of three modules, each of which controls the three
switching circuit breakers, the position of the elements that make up each one
the three CON-2300MP can be seen in the plan 'Dimensions and situation of elements in'
the CON-5300MP team
S30 'Out of service' button. When this button is pressed, it locks the
operation of the entire automatic system of the CON-2300MP and it locks
all the functions performed by this module. This state is indicated with a
LED type indicator light.
S5 Manual 'Start and Stop' Button. When this button is pressed, while the
system programmed in 'Manual service', the group will be ordered to start.
Pressing the button again will result in an immediate stop. The maneuver of
The start is indicated with a light pilot.
S51 Button for 'Lock measurements display'. The digital screen (display) can
present various pieces of information that follow one after another in a manner
cyclical. By pressing the 'Fix measurement display' button, the screen is fixed
Measurements present at that moment on the display. The measurements that it performs
the team consists of: tensions, intensities, frequencies, powers and values of
timers in seconds with a countdown to zero. Once
fixed on the electric measurements screen, these update every second.
Upon pressing the button again, the following screens will be displayed.
measurements or messages from the display or if the button is not activated, after
Intellectual property document of Electra Molins S.A. manual CON2300MP edition 1
Copying or reproduction without authorization is prohibited. D0057
Electra Molins S.A Sheet: 5 of 29
The automatic control team of the group module includes the following
signaling and measurement elements:
H6 'Network available'. Indicator light that the network is available for service.
When the network is in the stabilization period, the pilot makes intermittent signals.
H8 "Network in service". Indicator pilot that the network circuit breaker is connected.
SYSTEM OFF
FOR SERVICE
BATTERY
25.4V
TENSION GROUP
402V 403V 401V
The measurement of group tension is carried out with three digits and the measurement of
the intensities with four digits, in both cases in whole numbers. The
the maximum error of the readings in sinusoidal waves is± 1%± a digit.
The frequency measurement is carried out with four digits and a precision of 0.01.
Hz with a maximum reading error of± 1%± a digit.
The battery voltage measurement is performed with three digits and appreciation.
from 0.1 V with a maximum reading error of the± 1%± a digit. If the group is in
marching, or stopped with the electronic maintenance charger functioning, the
the voltage marked by the voltmeter will be higher than the nominal voltage of the battery. In the
Groups with 12V batteries will be between 12 and 14V. In the groups with
24V batteries will be positioned between 24 and 28V.
S30.1 'Out of service' button. When this button is pressed, it locks the
operation of the entire automatic system of the CON-2300MP and it gets blocked
all the functions performed by this module while disconnected
network circuit breaker. This state is indicated by a luminous indicator of the 'LED' type.
S5.1 Button for 'Manual closing and opening of the circuit breaker'. When activating this
button, with the system programmed in 'Manual service', an order will be given
for the closure or opening of the network circuit breaker. The closing maneuver is left
indicated with a light indicator.
S18.1 Button 'Network 1 in priority service over network 2'. When this is activated
the button gives priority to network service 1 over 2. When both networks
They cannot work in parallel; this programming can only be activated in one.
only of the modules, putting into service the network that has this programming.
If the networks can be connected in parallel, the priority switch can be placed on both.
network control modules will cause it to operate in parallel.
Reactivating the button cancels the priority for the service of this network
disconnecting it from the parallel operation. If the two networks do not
Can the suppression of the service priority of a network not work in parallel?
it will not cause any changes in the switching between networks. The programming of
priority is indicated with a light pilot
S51.1 Button to 'Lock measurement display'. The digital screen (display) can
present various pieces of information that follow one after another in a way
cyclical. When pressing the button "Fix measurement display", the screen of
measurements present at that moment on the display. The measurements that it performs
the team consists of: tensions, intensities, frequencies, powers, and values of
timers in seconds with a decreasing counter to zero. Once
the electrical measurements screen is fixed, and these are updated every second.
When the button is pressed again, it will proceed to the following screens of
measurements or messages from the display or if the button is not activated, after a period of time
In a few seconds, the measurement screen will change automatically.
The measurement fixing maneuver is indicated by a light indicator.
S6.1 "Reset alarms" button. Pressing this button will clear the
memorization of all alarms that are activated on the equipment. When
in the system there is one or more alarms activated, the alarm reset pilot
it causes intermissions.
The network control module 2 has the same control elements as the other one.
the network 1 changing exclusively the subscripts.
S2 "Switching selector with cut off." The selector has two positions 0 and 1.
At position 0, all the switching will be done without interruption between networks and
Position 1 will be carried out with a cut.
H6.1 "Network available". Indicator pilot that the network is available for service,
When the network is in the stabilization period, the pilot makes intermittent signals.
If the available network is the one that controls the other module, it will carry out
constantly interruptions.
H7.1 "Available group". Indicator pilot that the group is available for
service, when the group is in the stabilization period the pilot performs
intermittencies.
H8.1 "Network in service." Indicator pilot that the network circuit breaker is connected.
If the network that is in service is the one that controls the other module, it will carry out
constant intermissions.
H9.1 "Group in service". Pilot indicator that the group circuit breaker is
connected.
SYSTEM OUT
OF SERVICE
BATTERY
25.4V
TENSION RED 1
402V 403V 401V
The measurement of group tension is carried out with three digits and the measurement of
the intensities with four digits, in both cases in whole numbers. The
the maximum error of the readings in sinusoidal waves is± 1%± a digit.
The frequency measurement is done with four digits and an appreciation of 0.01.
Hz with a maximum reading error of± 1%± a digit.
The battery voltage measurement is carried out with three digits and appreciation.
from 0.1 V with a maximum reading error of the± 1%± a digit. If the group is in
running, or stopped with the maintenance electronic charger functioning, the
the voltage indicated by the voltmeter will be higher than the nominal voltage of the battery. In the
groups with 12V batteries will be between 12 and 14V. In the groups with
24V batteries will be between 24 and 28V.
The CON-5300MP team includes the necessary alarms to achieve the maximum
safety and reliability of operation.
The alarms of the CON-5300MP equipment are divided into four groups according to their action:
a) Preventive alarms
b) Switch system alarms
c) Parallel operation alarms
d) Communication alarms
When any alarm appears, the display will show the alarm that has occurred and the
The LED of the S6 button for 'Reset alarms' will flash until the issue is resolved.
the problem and reset the alarm with the 'Reset alarms' button.
When a stop alarm is triggered while the equipment is in 'Automatic Service', it changes
the programming to 'Manual Service'. Once the anomaly is resolved, it must be reassembled.
the alarm and, if applicable, return to 'Automatic Service' with the S11 button of 'Service'
automatic / Manual service.
The complete list of alarms can be displayed on the screen while the equipment is on.
programmed in automatic or manual service, activating for 3 seconds the
S6 button for 'Reset alarms'.
a) PREVENTIVE ALARMS. They are the alarms that are only indicated:
Low and high battery voltage. This alarm is activated when voltage is detected.
the battery that powers the equipment is below or above normal values
predefined. It will appear on the screen:
ALARM
BATTERY VOLTAGE
Blocked group. If the programming of the service is changed in the generator set
automatic by maneuver or by alarm, the display screen will show:
GROUP SERVICE
NO AUTOMATIC
The CON-5300MP team controls the maneuvering of the power circuit breakers located in
the switching panel allowing load transfer maneuvers to be carried out without
cut it with a cut.
The 4 alarms that each of the two modules controls related to the
the network circuit breakers are as follows:
The 4 alarms that the module controls related to the group circuit breaker are
next:
Network circuit breaker connection failure. When the closing order is given
network circuit breaker, if it is not connected, the following message will appear on the display:
ALARM CONNECTION
RED DISCONNECTOR
If the network circuit breaker does not connect during the switching operation, it will be blocked.
maneuver and the group circuit breaker will be reconnected.
Press the S6 button 'Reset alarms'. The system will attempt to switch.
from group to network. If the switching is not performed, the "Failure of" alarm will reappear.
the network circuit breaker connection" and the group will remain in service.
Failure in the network circuit breaker disconnection. When the opening command is given
network circuit breaker, if this opening is not carried out within the preset time, on the display
the following alarm will appear:
DISCONNECT ALARM.
RED DISCONNECTOR
When this alarm occurs, the system will not allow the group circuit breaker to connect.
the system will be blocked.
Press the S6 button 'Reset alarms'. The system will attempt to disconnect again.
the network circuit breaker. If it does not disconnect, this alarm will appear again.
Network circuit breaker current relays. When the network circuit breaker carries
incorporated intensity relays with signaling contact, if a
overcurrent, which causes its disconnection, will appear on the display the
alarm
ALARM INTENSITY.
RED BREAKER
Since this alarm is triggered upon detecting an overcurrent, the equipment does not provide
starting order for the generator group to prevent overcurrent from occurring
also about the group itself. The switching is therefore blocked and the system
out of service with the group stopped. The S30 LED of 'Out of service' will perform
intermittencies.
The rearming of this alarm and the commissioning of the network will be carried out as follows.
manner
Activate the "Reset alarms" button S6, which will also turn on the "Out of service" LED.
S30 will stop blinking and will stay on.
To reconnect the network circuit breaker, activate the S11 "Automatic service" button.
/ Manual service" changing to "Automatic service".
If the network circuit breaker has a contact for trip signaling by relays
of intensity (in addition to the signaling contacts of the closed/open state); it
it will be considered that the unexpected disconnection of the circuit breaker was due to a cause
different from an overintensity. In this case, when this alarm is detected, the equipment will give
Start order for the generator set to put it into service and maintain it.
the power supply. It will appear on the screen:
ALARM SHOT
RED DISCONNECTOR
In this case, the rearming of the alarm and the commissioning of the network will be carried out from
the following way:
Press the S6 button 'Reset alarms'. The equipment will give the orders to
disconnect the group circuit breaker and to connect the network circuit breaker. If the
the network circuit breaker does not connect, the group breaker will reconnect, and
this alarm will appear again.
If the network circuit breaker does not have a relay tripping signal contact
of intensity and only has contacts for the signaling of the status
(closed/open), the disconnection of the circuit breaker will be considered to have been due to the
triggering of said relays for which the same treatment is applied as for the alarm
from 'Network circuit breaker current relays'. The equipment does not give a start command to the
generator set to prevent overcurrent from occurring also on the
group. The switching is therefore blocked and the system is out of service with the
group stopped. The S30 LED of "Out of service" will flash. It will appear in
the screen
ALARM INTENSITY.
RED DISCONNECTOR
In this case, the rearming of the alarm and the commissioning of the network will be carried out from
the following way:
Activate the "Reset alarms" button S6, which will also activate the "Out of" LED.
The 'S30 service' will stop flashing and will remain on.
To reconnect the network circuit breaker, press the S11 'Service' button
automatic / Manual service" switching the programming to "Service
automatic.
Failure of the group circuit breaker connection. When the closing order is given for the
group circuit breaker, if it is not connected, the following message will appear on the display:
ALARM CONNECTION
GROUP BREAKER
If the group circuit breaker does not connect during the switching maneuver with the network, it
it will block the group circuit breaker maneuver and will automatically reconnect the
network circuit breaker, keeping the network in service, the programming of 'Group in service'
"priority" will be blocked.
Press the S6 button 'Reset alarms'. The equipment will attempt to carry out the
network switching to group. If the switching still does not occur, it will return to
the alarm 'Group circuit breaker connection failure' and the network appear
will remain in service.
Failure in the group circuit breaker disconnection. When the opening command is given.
of the circuit breaker, if this opening is not performed within the established time,
the following alarm will appear:
DISCONNECTED ALARM.
GROUP DISCONNECTOR
When this alarm is detected, the system will not allow the network circuit breaker to connect.
blocking the switching, leaving the group in service.
Press the S6 button 'Reset alarms'. The equipment will try again.
disconnect the group circuit breaker. If it does not disconnect, it will return to
this alarm appears.
Intensity relays of the group circuit breaker. When the group circuit breaker has
incorporated intensity relays with signaling contact, if a occurs
overcurrent, which causes its disconnection, will appear on the display the
alarm:
ALARM INTENSITY.
GROUP BREAKER
Since this alarm is triggered by detecting an overcurrent, the equipment does not
It will give the order to put the network into service to prevent overcurrent from occurring.
also about the network. The switching is therefore blocked and the system out of
service with the group stopped, until the problem is resolved and the alarm is rearmed. The
The S30 LED of 'Out of service' will flash intermittently.
The rearming of this alarm and the commissioning of the group will be carried out as follows
way
Activate the 'Reset alarms' button S6, which will also turn on the 'Out of'
service" S30 will stop blinking and will remain on.
-To restart the group and connect the group circuit breaker, activate the
button S11 "Automatic service / Manual service" entering programming
Automatic service.
Unexpected disconnection of the group circuit breaker. This alarm is triggered if while
the group circuit breaker is connected, it disconnects for an unknown reason. The action of
this alarm is triggered by the signaling contacts of the state (closed/open)
circuit breaker and it is different depending on whether the group circuit breaker includes or does not include a contact
additional exterior signaling for firing by the operation of the intensity relays
characteristics of the group circuit breaker:
If the group circuit breaker has a contact for signaling tripping for
intensity relays (in addition to the signaling contacts of the state
closed/open); it will be considered that the unforeseen disconnection of the circuit breaker has been
for a reason other than an overintensity. It will appear on the screen:
Intellectual property document of Electra Molins S.A. manuals\ CON2300MP edition1
Copying or reproduction without authorization is prohibited. D0057
Electra Molins S.A Sheet: 17 out of 29
ALARM SHOT
GROUP BREAKER
The system will act differently depending on the state of the network at the time of
to produce the anomaly:
If the anomaly has occurred while there is network voltage, it will be given
immediate order to connect to the network circuit breaker.
If the anomaly has occurred without network voltage, upon returning to the
the same, it will be put into service with a minimum stabilization time.
In this case, the rearming of the alarm and the commissioning of the group will be carried out.
in the following way:
Press the S6 button 'Reset alarms'. If at that moment the network is not
In service, the team will give the connection order to the group circuit breaker. If the network
it is in service, the button S18 "Group in service" must be activated
"priority" to bring the group back into service. If the group circuit breaker
If it disconnects again, this alarm will reappear.
If the group circuit breaker does not have an independent signaling contact
circuit breaker trip by current relays and only has contacts for the
status signaling (closed/open), the disconnection of the circuit breaker will be considered
which has been due to the triggering of said relays for which the same is carried out
treatment for the alarm of 'Group circuit breaker intensity relays'. The
the team will not issue the order to put the network into service to prevent that
overvoltage also occurs on the network. The switching remains therefore
blocked and the system out of service with the group stopped, until it is resolved
problem and the alarm will reset. The S30 LED of "Out of service" will perform
intermittencies. It will appear on the screen:
ALARM INTENSITY.
GROUP DISCONNECTOR
The rearming of this alarm and the commissioning of the group will be carried out from the
next way:
Activate the "Reset alarms" button S6, which also turns on the "Out of
service" S30 will stop flashing and will remain on.
To restart the group and connect the group circuit breaker, activate the
Button S11 "Automatic Service / Manual Service" switching to programming
"Automatic service".
The alarm related to the parallel operation between the networks can work.
in parallel:
Timing failure.
When synchronization occurs between the networks, if it is not carried out on time
5 minutes, the display screen will show:
RED ALARM
SYNCHRONISM
The indication of this anomaly only appears in the module corresponding to the circuit breaker.
that has to be synchronized with use.
By resetting this alarm using the S6 button 'Reset alarms', it will be repeated again.
the 'automatic synchronization cycle'. In case the alarm repeats, it must be sought
cause of the anomaly. Provisionally, and until the cause of the 'failure' is found
"synchronization", the S2 switch located at the back of the CON modules will be passed.
2300MP that control the breakers of the networks, to the position "1".
In this way, the team is programmed to perform the switchovers with cut.
c) COMMUNICATION ALARMS:
The three modules that control the circuit breakers are interconnected with an RS bus.
485, if this interconnection is interrupted, the alarm will appear on the display screen:
ALARM
COMMUNICATION
This alarm only blocks the module that doesn't respond to its communication but I don't know.
they interrupt the other modules.
The CON-2300MP device has two contacts with a common terminal without voltage that
they allow to signal at a distance the firing of the alarms of the equipment. One of the contacts
signals the preventive alarms, the other the alarms in the switching system.
Through an external contact connected to the equipment, the group can be started or
put it into service according to the programming carried out on the device itself.
Optionally, a module can be installed for the communication of the equipment with a
PC computer, through an RS 485 serial communication. Allows for control
remote completion of the switching team. To know the details of
operation and programming, see the manual 'Protocol Description of
communication from the team CON-2300MP
Operating programmer.
Section normally without content except for equipment built under project
special.
4. MODES OF OPERATION.
SYSTEM OFF
OF SERVICE
BATTERY
25.4V
Although the switching control team is in the 'System out of' position.
service, it is possible that the group is underway, either because it has been set in motion
manual from the group itself, or because it has received a start order from another
switching (in case there is more than one switching).
In the event that the two networks cannot be connected in parallel, the selection of the network
service priority can be selected to be automatic or manual, in the
automatic selection, the network that is in service is always the priority and in the system
manual, it is the user who selects it.
In the event that the two networks can be connected in parallel, two can be presented.
work systems, which have redundant networks for the service (a single network
can provide service for the use), or that have been essential for the service, (the two
networks must work in parallel inevitably due to the power of
utilization
In the first case, the group will start when both networks fail and in the
second, when a single network fails.
Manual programming
When the system is in manual programming, and the networks are available the LEDs
H6 will be lit, activating the buttons for 'Manual close and open of'
circuit breaker" closing the respective circuit breaker If you want to switch to the other circuit breaker of the
Another network with a cut, the buttons S18.1 of 'Network 1' will be activated respectively.
priority service over network 2" or the equivalent of network 2 and then the button
S5.1 or S5.2 of "Manual closing and opening of circuit breaker" which will open the
circuit breaker that was connected and the new circuit breaker will close.
When the two networks cannot work in parallel, by program they will not be able to.
connect the buttons of 'Network 1 in priority service over network 2' at the same time or the
equivalent of the network 2.
If the two networks can work in parallel, to carry out the maneuver of having both
if the circuit breakers are connected, the previous process will be repeated but with the difference of
Both buttons S18.1 of 'Network 1 in priority service' must be activated.
about network 2" and the equivalent of network 2.
If the maneuver to be performed was a hot-switching operation, once the two circuit breakers are
The parallel service priority button that is to be disconnected will be deactivated.
Automatic Programming
If the two networks have to work in parallel in automatic mode, in both networks
The network button will be programmed in priority service.
Acting on the button S11 of each module "Automatic service / Manual service"
the programming will be changed from "Out of service" to "Manual service", appearing
the pilot light of 'Manual Service' is illuminated. If the network voltage is correct, it
It will intermittently illuminate the H6 pilot light available on all modules.
After the first stabilization time has elapsed, the H6 pilot light will remain on.
Then acting on the button 'Manual closing and opening of the circuit breaker' of
module that controls the network circuit breaker, the equipment will give the order to close the circuit breaker
red for its commissioning, the H8 indicator lights up. At the moment of connecting the
red, a screen will appear with the network voltage readings in each phase.
TENSION RED
402V 403V 401V
If the maneuver described above is repeated in the other circuit breaker control module
of the network, this second network will not connect unless it has previously not been
the button that gives priority of service to this second network has been activated, upon being activated the
the closing button of this second network would disconnect the first to connect the second
second
Once the group is started and available (the H7 status pilot of the group lights up in the
If the network is operational, the group will remain functioning and available.
If the network is down, the group will be put into service immediately
the H9 group pilot light is turning on in service.
To put the generator in service even though the networks are in service, it
S18 will pulse 'Group in priority service'. The service priority of the generator group.
it will be signaled with a luminous indicator.
In this position, the load will be disconnected from the network and connected to the group.
a cut in the supply is occurring.
By pressing S18 "Group in priority service" again, the priority service will be canceled.
of the group and the group's load will be switched.
The manual shutdown of the generator set will be carried out by pressing S5 'Start and manual stop'.
removing the march signal that had been given to the control panel of the group, if this one
It was scheduled in 'Automatic Service' the group will start the shutdown cycle.
Note: All timing settings of the CON-2300MP equipment are adjustable by the service.
ELECTRA MOLINS, S.A. technician to the values desired by the customer within a range
valid through the programming console.
To program the equipment for automatic operation in case of network failure, you must
press the button S11 "Automatic service/Manual service" switching to "Service
automatic" in the three modules, signaling the maneuver by the lighting of
the corresponding pilots.
When a 'network failure' occurs, the CON-2300MP equipment will perform a brief
timing, usually 1 second to give the order to be put into service
the other network, to avoid giving a "start order" in a first cut of shorter duration
to a second. With this type of operation, the group will not start until
that both networks crash.
If the normal operating system of the equipment requires both networks to work
permanently in parallel, the group's start will occur when a single one fails.
of the networks
After this confirmation timing of the 'network failure' has elapsed in any of the
Two systems, the CON-2300MP equipment sends the signal to the automatic panel of the group for the
start of this. Once the CON-2300MP group module receives the group signal
available, coming from the group's automatic panel, the H7 group indicator lights up
available for service, then the team will give the order for the closure and startup
group circuit breaker service appearing illuminated then the group H9 pilot light
service.
The generator set will remain in service for as long as the "network failure" lasts.
Upon returning, the network stabilization timing begins. This timing
its purpose is to avoid frequent switching in unstable networks. The
timing on the screen with indication of the countdown to zero:
AVAILABLE NETWORK
EN 300 SEG.
During this stabilization time, the H6 pilot will perform intermissions. Once finished
the network stabilization the H6 pilot light will remain on indicating that the network is
available for immediate service.
From this moment, the load will be switched to the network, and once
Once completed, the team CON-2300MP will suppress the start signal to the panel.
automatic of the group to produce its stoppage.
Control of voltage cuts shorter than 1 second. The equipment incorporates a control of
number of cuts in the supply during a period of time. The number of cuts and the
time is programmable. When exceeding the number of cuts to the programmed value, it
the start of the group will be carried out.
When the group is available, the first cut that occurs will be carried out.
network switching to group. If the network stabilization time has passed and it has not
no new cuts have been made, the service will return to the network.
This mode of operation is performed by placing the selector S11 in the position of
"Automatic service" and keeping the S5 button "Group in priority service" activated.
the group's module.
When the network fails, the group automatically enters service. But when it returns the
red, when the button S5 "Group in priority service" is activated, the action is not performed
automatic group to network switching. This switching will be done manually
when the button S5 is deactivated.
This mode of operation is useful when you want the group to network switching.
it should be done at an opportune moment.
REMOTE START
GROUP
Once the group has been started by the external signal, the team will put the group into service or
no, according to the position of the selector S1 located at the back of the CON module.
2300MP that controls the group circuit breaker.
With the S1 selector in position 0, the group will start but will not be put into service.
With selector S1 in position 1, the group will be put into service. Performing the
network switching to group.
The external start signal can be provided with an external timer to the equipment.
CON-2300MP and which can be optionally mounted on the switching frame.
It allows starting the group on the days and hours set in the programmer by carrying out
the transfer of load without network interruption to group and from group to network.
For the maintenance of the electrical equipment, it will only be necessary once or twice a...
year, a test of all the automations is carried out through its system
automatic, and a review is carried out and if necessary a retightening of all its
embeddings, both of maneuver and power, as well as a cleaning of the
same with dry compressed air or with a vacuum cleaner.