Project Schedule Management Plan Template

This document provides a template for a project schedule management plan. It outlines how the project schedule will be created, monitored, and updated. The schedule will be created in MS Project with milestones and will be reviewed bi-weekly. Any changes exceeding 10% of duration must be approved through a request. The project manager is responsible for schedule development and control, with the team providing input and updates.

Uploaded by

APP Compañia 7R
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
104 views7 pages

Project Schedule Management Plan Template

This document provides a template for a project schedule management plan. It outlines how the project schedule will be created, monitored, and updated. The schedule will be created in MS Project with milestones and will be reviewed bi-weekly. Any changes exceeding 10% of duration must be approved through a request. The project manager is responsible for schedule development and control, with the team providing input and updates.

Uploaded by

APP Compañia 7R
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

ProjectManagementDocs.

com

PROJECT SCHEDULE MANAGEMENT PLAN TEMPLATE


This Project Schedule Management Plan Template is free for you to copy and use on your
project and within your organization. We hope that you find this template useful and
welcome your comments. Public distribution of this document is only permitted
from the Project Management Docs official website at:
[Link]

SCHEDULE MANAGEMENT PLAN


<PROJECT NAME>

COMPANY NAME
STREET ADDRESS
CITY, STATE ZIP CODE

DATE

1
[Link]

TABLE OF CONTENTS
INTRODUCTION .................................................................................................................................... 3
SCHEDULE MANAGEMENT APPROACH ...................................................................................................... 3
SCHEDULE CONTROL ............................................................................................................................. 4
SCHEDULE CHANGES AND THRESHOLDS .................................................................................................... 5
SCOPE CHANGE ................................................................................................................................... 6

2
[Link]

INTRODUCTION

This section highlights the purpose and importance of the schedule management plan. It
provides a general description of what should be included in the schedule management plan.
These items will be described in more detail later in the plan under each corresponding section.

The project schedule is the roadmap for how the project will be executed. Schedules are an
important part of any project as they provide the project team, sponsor, and stakeholders a
picture of the project’s status at any given time. The purpose of the schedule management
plan is to define the approach the project team will use in creating the project schedule. This
plan also includes how the team will monitor the project schedule and manage changes after
the baseline schedule has been approved. This includes identifying, analyzing, documenting,
prioritizing, approving or rejecting, and publishing all schedule-related changes.

SCHEDULE MANAGEMENT APPROACH

This section provides a general framework for the approach which will be taken to create the
project schedule. This includes the scheduling tool/format, schedule milestones, and schedule
development roles and responsibilities.

Project schedules will be created using MS Project 2007 starting with the deliverables identified
in the project’s Work Breakdown Structure (WBS). Activity definition will identify the specific
work packages which must be performed to complete each deliverable. Activity sequencing
will be used to determine the order of work packages and assign relationships between project
activities. Activity duration estimating will be used to calculate the number of work periods
required to complete work packages. Resource estimating will be used to assign resources to
work packages in order to complete schedule development.

Once a preliminary schedule has been developed, it will be reviewed by the project team and
any resources tentatively assigned to project tasks. The project team and resources must agree
to the proposed work package assignments, durations, and schedule. Once this is achieved the
project sponsor will review and approve the schedule and it will then be baselined.

The following will be designates as milestones for the project schedule:


 Completion of scope statement and WBS/WBS Dictionary
 Baselined project schedule
 Approval of final project budget

3
[Link]

 Project kick-off
 Approval of roles and responsibilities
 Requirements definition approval
 Completion of data mapping/inventory
 Project implementation
 Acceptance of final deliverables

Roles and responsibilities for schedule development are as follows:

The project manager will be responsible for facilitating work package definition, sequencing,
and estimating duration and resources with the project team. The project manager will also
create the project schedule using MS Project 2007 and validate the schedule with the project
team, stakeholders, and the project sponsor. The project manager will obtain schedule
approval from the project sponsor and baseline the schedule.

The project team is responsible for participating in work package definition, sequencing, and
duration and resource estimating. The project team will also review and validate the proposed
schedule and perform assigned activities once the schedule is approved.

The project sponsor will participate in reviews of the proposed schedule and approve the final
schedule before it is baselined.

The project stakeholders will participate in reviews of the proposed schedule and assist in its
validation.

SCHEDULE CONTROL

This section defines how the project’s schedule will be controlled throughout the life of the
project. This includes the frequency of updates and schedule reviews as well as communicating
the schedule and progress. This section also defines roles and responsibilities as they relate
specifically to project schedule control.

The project schedule will be reviewed and updated as necessary on a bi-weekly basis with
actual start, actual finish, and completion percentages which will be provided by task owners.

The project manager is responsible for holding bi-weekly schedule updates/reviews;


determining impacts of schedule variances; submitting schedule change requests; and reporting
schedule status in accordance with the project’s communications plan.

4
[Link]

The project team is responsible for participating in bi-weekly schedule updates/reviews;


communicating any changes to actual start/finish dates to the project manager; and
participating in schedule variance resolution activities as needed.

The project sponsor will maintain awareness of the project schedule status and review/approve
any schedule change requests submitted by the project manager.

SCHEDULE CHANGES AND THRESHOLDS

As the project schedule is created it is important that boundary conditions are set by the
project sponsor to establish the schedule parameters within which the project is expected to
operate. Any event which may potentially cause a schedule change which exceeds these
boundary conditions must have a schedule change request submitted and approved by the
sponsor before the schedule change is made. For this example we will use a change threshold
of 10%.

If any member of the project team determines that a change to the schedule is necessary, the
project manager and team will meet to review and evaluate the change. The project manager
and project team must determine which tasks will be impacted, variance as a result of the
potential change, and any alternatives or variance resolution activities they may employ to see
how they would affect the scope, schedule, and resources. If, after this evaluation is complete,
the project manager determines that any change will exceed the established boundary
conditions, then a schedule change request must be submitted.

Submittal of a schedule change request to the project sponsor for approval is required if either
of the two following conditions is true:
 The proposed change is estimated to reduce the duration of an individual work package
by 10% or more, or increase the duration of an individual work package by 10% or more.
 The change is estimated to reduce the duration of the overall baseline schedule by 10%
or more, or increase the duration of the overall baseline schedule by 10% or more.
Any change requests that do not meet these thresholds may be submitted to the project
manager for approval.

Once the change request has been reviewed and approved the project manager is responsible
for adjusting the schedule and communicating all changes and impacts to the project team,
project sponsor, and stakeholders. The project manager must also ensure that all change
requests are archived in the project records repository.

5
[Link]

SCOPE CHANGE

Occasionally, approved changes to the project’s scope may result in the schedule needing to be
re-baselined. These scope changes may include new deliverables or requirements that were
not previously considered as part of the original schedule’s development. In these situations
the project manager and team must consider the current status of the project schedule and
how the scope change will affect the schedule and its resources as the project moves forward.

Any changes in the project scope, which have been approved by the project sponsor, will
require the project team to evaluate the effect of the scope change on the current schedule. If
the project manager determines that the scope change will significantly affect the current
project schedule, he/she may request that the schedule be re-baselined in consideration of any
changes which need to be made as part of the new project scope. The project sponsor must
review and approve this request before the schedule can be re-baselined.

6
[Link]

SPONSOR ACCEPTANCE

Approved by the Project Sponsor:

__________________________________________ Date: ___________________


<Project Sponsor>
<Project Sponsor Title>

This free Project Schedule Management Plan Template is brought to you by


[Link]

Common questions

Powered by AI

Defining roles and responsibilities is crucial in the schedule management plan as it clarifies expectations, reduces ambiguity, and ensures accountability for each aspect of schedule development and control. This alignment facilitates effective collaboration among team members and stakeholders, streamlines communication, and enhances the efficiency and reliability of project execution .

Project stakeholders participate in reviews of the proposed schedule and assist in its validation. They provide feedback and ensure that the schedule aligns with their expectations and the project requirements. Their involvement helps in identifying potential issues early and ensures broader acceptance and support for the schedule, facilitating smoother project execution .

Activity sequencing contributes to the development of a project schedule by determining the order of work packages and assigning relationships between project activities. This process helps in organizing the activities logically so that each step is performed at the right time, ensuring that dependencies are respected. Correct sequencing is essential for estimating the duration and resources accurately, which ultimately aides in developing a realistic schedule .

Obtaining schedule approval from the project sponsor before baselining is significant because it provides a formal endorsement that the schedule has been thoroughly reviewed and aligns with the project's objectives and constraints. This approval signifies stakeholder buy-in and enhances commitment to the schedule, reducing the likelihood of disputes and changes later in the project lifecycle .

The key components involved in creating a project's schedule management plan include defining the approach for creating the project schedule, monitoring the schedule, and managing changes after the baseline schedule has been approved. This involves outlining roles and responsibilities for schedule development, utilizing scheduling tools/format like MS Project 2007, establishing milestones, and ensuring that the project sponsor reviews and approves the schedule before it is baselined .

It is essential for the project manager to participate in bi-weekly schedule updates and reviews to monitor progress, ensure the project remains on track, identify and resolve variances, and manage any necessary adjustments. These regular check-ins allow the manager to communicate the schedule status to stakeholders and maintain control over the schedule, which is vital in mitigating risks and ensuring successful project completion .

Not addressing schedule variances can have significant negative impacts including project delays, cost overruns, and failure to meet stakeholder expectations. Ignoring variances undermines the schedule’s reliability, reduces the team’s ability to meet project milestones, and can lead to negative stakeholder perceptions. Proactively managing variances is essential for maintaining project control, enabling timely corrective actions, and ensuring project success .

A project schedule may need to be re-baselined when there are approved changes to the project’s scope that significantly affect the current schedule. Such changes might include new deliverables or requirements not considered in the original schedule. The project sponsor plays a crucial role by reviewing and approving the request for re-baselining, thereby ensuring that any scope changes are formally considered and integrated into the project plan .

Establishing change thresholds is critical in schedule management as it sets the boundary conditions under which the project is expected to operate. It ensures that any proposed change which exceeds these thresholds, such as a 10% variation in individual work package duration or overall baseline schedule duration, undergoes a formal change request process. This helps maintain control over the project's scope and time objectives, facilitates better resource and stakeholder management, and safeguards against project drift .

Resource estimating contributes to project schedule development by determining the amount and type of resources required to complete work packages. It ensures that each activity has the necessary human, equipment, and financial resources assigned, influencing the activity duration and thus the overall project timeline. Accurate resource estimating is pivotal for creating a feasible and balanced schedule that aligns with the project’s objectives and constraints .