0% found this document useful (0 votes)
194 views

CDC UP Project Scheduling Practices Guide

The document provides guidance on project scheduling practices for developing an effective project schedule. It discusses decomposing work packages into schedule activities, sequencing activities based on dependencies, estimating resources and durations, developing the initial schedule, and baselining the schedule. The goal is to create a master plan that shows what work will be accomplished, how, when, and by whom, to track progress and meet deadlines. Input from stakeholders is important for developing an accurate schedule.

Uploaded by

junlab0807
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
194 views

CDC UP Project Scheduling Practices Guide

The document provides guidance on project scheduling practices for developing an effective project schedule. It discusses decomposing work packages into schedule activities, sequencing activities based on dependencies, estimating resources and durations, developing the initial schedule, and baselining the schedule. The goal is to create a master plan that shows what work will be accomplished, how, when, and by whom, to track progress and meet deadlines. Input from stakeholders is important for developing an accurate schedule.

Uploaded by

junlab0807
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 0

CDC UNIFIED PROCESS

PRACTICES GUIDE

PROJECT SCHEDULING

UP Version: 06/30/07 Page 1 of 4
Document Purpose
The purpose of this document is to provide guidance on the practice of Project Scheduling and to
describe the practice overview, requirements, best practices, activities, and key terms related to this
requirement. In addition, templates relevant to this practice are provided at the end of this guide.
Practice Overview
A successful project schedule requires proper estimation of the effort, definition of staffing needs and
resource requirements, and the identification of work durations.

In order to build a project schedule the project work defined in the Work Breakdown Structure (WBS) work
packages must be further decomposed into smaller, more manageable components referred to as
schedule activities. These schedule activities are then sequenced in order to build a project schedule.
The ultimate goal of this effort is to build an effective project schedule that answers questions such as:
What will be accomplished?
How it will be accomplished?
When it will be accomplished?
Who will accomplish it?

The Project Management Institutes Project Management Body of Knowledge defines a project schedule
as the planned dates for performing schedule activities and the planned dates for meeting schedule
milestones. A schedule milestone is defined as a significant event in the project schedule, such as an
event restraining future work or marking the completion of a major deliverable. A project schedule is
developed by further decomposing WBS work packages and analyzing activity sequences, durations,
resource requirements, and project constraints to create a formal list of project activities and an outline of
which order they should be performed. The processes for accomplishing this include the following project
scheduling practices:
Activity definition focuses on identifying and documenting the planned work.
Activity sequencing focuses on identifying and documenting relationships among scheduled
activities.
Resource and duration estimating focuses on determining what resources are required, in
what quantities, and for how long, to complete the project work as planned.
Schedule development focuses on determining schedule activity start and finish dates.
Schedule control focuses on influencing factors that create project schedule change.

In some instances, projects are so tightly structured that the steps of creating a project schedule can be
performed by a single individual. However, in most cases, representatives from across the organization,
and most certainly the project team, will be involved in different aspects of the schedule development
process.

Activity Definition
For scheduling purposes, WBS work packages are decomposed into even smaller components known as
schedule activities. This process is referred to as activity definition. Schedule activities are work defined to
a level that can be easily estimated, scheduled, executed, and monitored and controlled. Good project
planning practice is to define these activities to a level no smaller than one full work day (~8hrs) and no
larger than ten full work days (~2wks). Anything more than ten working days most likely can be better
managed if further decomposed. Anything less than one working day is usually too detailed to be
managed affectively.

To facilitate this effort a project manager may seek out examples of similar projects, review project
templates, reuse all or some part of schedules from past projects, solicit feedback from subject matter


CDC UNIFIED PROCESS
PRACTICES GUIDE

PROJECT SCHEDULING

UP Version: 06/30/07 Page 2 of 4
experts, the project team, etc. The ultimate goal is to develop a list of schedule activities and to identify
any dependencies or conflicts that may exist between them. If prospective conflicts do exist, work on
resolving them as early in the project life cycle as possible utilizing the projects defined schedule control
process.

Activity Sequencing
Many times schedule activities have inherent interdependencies, resource limitations, date constraints,
etc. that all need to be considered when outlining how project work aligns in the form of a defined project
schedule. The project schedule links schedule activities together in a manner that creates a timeline of
work throughout the projects life. Schedule activities that need to be conducted early in the project, or are
depended upon by other tasks later in the project need to be performed in the projects life cycle to
accommodate these types of dependencies.

During the practice of activity sequencing the project manager aligns the sequence of schedule activities
in a way to best avoid any factors that may limit how quickly project work can be completed. To facilitate
this effort a project manager may use project scheduling tools such as Microsoft Project or advanced
sequencing techniques using various diagramming methods and/or applying scheduling leads or lags to
individual tasks. The ultimate goal is to often structure the sequence of schedule activities in a way that
completes the project as quickly as possible.

Contained within all schedules is a critical path. The critical path is the series of tasks that determines the
duration of the project. The tasks on the critical path are often scheduled tightly; upon finishing one, the
next one immediately starts. In other words, there is no slack between critical tasks, if one task slips, the
entire schedule slips. Understanding and effectively managing the schedules critical path is vital to
completing a project as planned.

Resource and Duration Estimating
The practice of estimating involves determining what quantity of a resource is required to complete the
project work that it is assigned to. Resources could include people, equipment, material, etc. Estimates
are usually provided by the person or group on the project team who is most familiar with the nature of
the work to be estimated. Details regarding the actual practice of developing estimates for schedule
activities are detailed in the CDC UP Estimating Practices Guide.

Once work effort estimates have been developed, determining the time duration of how that effort will be
distributed through out the projects life is known as duration estimating. The Project Management
Institutes Project Management Body of Knowledge defines duration as the total number of work periods
required to complete a schedule activity or WBS component, usually expressed as work days or work
weeks. Duration estimates are determined by identifying when the required project resource is needed
and then adjusting the project schedule to accommodate for its actual availability. Most project
management software for scheduling can handle this automatically.

Schedule Development
Developing a project schedule is most often the responsibility of the project manager. Project
Management Institutes Project Management Body of Knowledge defines a project schedule as the
planned dates for performing schedule activities and the planned dates for meeting schedule milestones.
The practice of schedule development leverages knowledge gained from activity definition, sequencing,
and estimating to create a formal sequence of project activities, the project schedule, that outlines when
required work should start, when it is expected to be completed, and who will do the work.

The project schedule serves as a master plan which the project team, management, customers, and
other stakeholders look to for an up-to-date picture of how project work is progressing. The project
schedule should clearly define:
A direct relationship to the WBS


CDC UNIFIED PROCESS
PRACTICES GUIDE

PROJECT SCHEDULING

UP Version: 06/30/07 Page 3 of 4
Major events and dates
Sequence of work
Interrelationships between tasks
Task constraints
Resources required to complete each schedule activity

To effectively develop a reasonably accurate project schedule the project manager cannot rely on their
input alone. Input from functional manager, knowledge experts, consultants, and project team members
from across the organization must be leveraged throughout the schedule development process.

One approach to schedule development is known as rolling wave planning. Rolling wave planning is a
form of progressive elaboration planning where the work to be accomplished in the near term is planned
in detail at a low level of the WBS, while the work far in the future is planned at a relatively high level of
the WBS, but the detailed planning of the work to be performed within another one or two periods in the
near future is done as work is being completed during the current period.

Once complete, the initial project schedule is baselined and is used to track project progress. A baselined
project schedule is the original approved project plan used to track progress on a project. The baselined
schedule is a snapshot of the schedule, at the time that the baseline was saved, and includes baselined
information about tasks, resources, and assignments.

The result of defining a detailed project schedule also produces updates to other project areas and/or
documents such as resource requirements, project calendars, performance measurements and reports,
change control, organizational processes, PMP, etc. These updates should be reflected in these areas by
utilizing any defined update procedures.

Each activity is now clearly defined and scheduled, and responsibility for completion assigned and
communicated. As project work progresses the project schedule should be adjusted to reflect actual work
completed and planned work remaining.

Schedule Control
Schedule control is primarily concerned with influencing and/or managing the factors that create schedule
change. This is done by monitoring such things as project variances, external factors, project progress,
etc. The activities that control changes to the project schedule are often outlined as part of the Project
Management Plan (PMP).

One important activity required for controlling project schedules is resource leveling. Resource leveling
involves leveling out the workload of resources assigned in the schedule by bringing the workload of
those resources within the range of their availability. A resource can often have too much scheduled work
when they are assigned to two or more tasks at the same time. Re-assigning some work to another
resource is one possible solution. A less desirable solution might be to reschedule one of the two tasks to
occur later in time.
Best Practices
The following best practices are recommended for the practice of Project Scheduling:
Develop Jointly Input from knowledge experts and other stakeholders from across the organization
should be leveraged to develop a reasonably accurate schedule.
Decompose Decompose schedule activities to no less than ~8hrs and no more than ~2wks of work
effort.
Leverage Past Work When creating the project schedule review examples of similar projects, project
templates, expert judgment, etc.


CDC UNIFIED PROCESS
PRACTICES GUIDE

PROJECT SCHEDULING

UP Version: 06/30/07 Page 4 of 4
Review Review the completed schedule with project stakeholders before baselining and continuously
review the schedule and update stakeholders as part of the project status reporting.
Make Updates As the project environment changes updates in the form of appended change
requests should reflect any changes to the WBS and/or the WBS Dictionary.
No Acronyms Use actual system names and nomenclature instead of acronyms to avoid confusion.
Practice Activities
For projects the following practice activities are appropriate:
Define the planned work by decomposing WBS work packages into schedule activities
Sequence schedule activities in the order in which they will be performed
Identify resources needed to complete the work
Estimate the level of effort required to complete the work utilizing the available resources
Develop a project schedule. Ensure that adjustments are made to the sequence of activities that
account for resource availability
Control the schedule by identifying, monitoring, and influencing factors that cause schedule change
Practice Attributes
This section provides a list of practice attributes to help project teams determine when and how applying
Project Scheduling impacts a project.

Practice Owner CDC UP Project Office NCPHI
Criteria
All projects regardless of type or size should have some type of document
that outlines how work will be performed, in what order, by whom, and when
(a project schedule).
Estimated Level of
Effort
Moderate
Prerequisites Completed WBS
Practice
Dependencies
WBS
Practice Timing in
Project Life Cycle
Developing a project schedule is an activity that takes place early in the
project life cycle with updates and refinements made throughout the
projects life, as necessary.
Templates/Tools
Project scheduling Practices Guide, Microsoft Project Practices Guide,
Project Schedule Template, Project Scheduling Checklist
Additional
Information
N/A
Key Terms
Follow the link below to for definitions of project management terms and acronyms used in this document.
http://www2.cdc.gov/cdcup/library/other/help.htm
Related Templates/Tools
Below is a list of template(s) related to this practice. Follow the link below to download the document(s).
http://www2.cdc.gov/cdcup/library/matrix/default.htm
Microsoft Project Practices Guide
Project Schedule Template
Project Scheduling Checklist

You might also like