ID Task Task Name Duration Start Finish Predecessors Week -2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week
2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16
Mode
1 Technology 50 days Tue 26-05-20Mon 03-08-20
2 Student Interphase20 days Tue 26-05-20 Mon 22-06-20 Engineer1,Engineer2,Engineer3
3 Teacher Interphase20 days Tue 26-05-20 Mon 22-06-20 Engineer4,Engineer5,Engineer6
4 Chat Option 10 days Tue Mon 2,3 Engineer1
(Platform) 23-06-20 06-07-20
5 Interrupt Option 10 days Tue Mon 4 Engineer1
(Raise a Doubt) 07-07-20 20-07-20
6 Recording Feature 10 days Tue 07-07-20 Mon 20-07-204 Engineer5
7 Community Platform
20 days Tue 23-06-20 Mon 20-07-202,3 Engineer2,Engineer3,Engineer4
8 Roaster Management
10 days Tue 07-07-20 Mon 20-07-204 Engineer6
9 Payment Integration
10 days Tue 21-07-20 Mon 03-08-208,7,6,5 Engineer2,Engineer3,Engineer4
10 Upload Content Feature
10 days Tue 23-06-20 Mon 06-07-202,3 Engineer5
11 Chatboat(Website) 10 days Tue 23-06-20 Mon 06-07-202,3 Engineer6
12 Finish 0 days Mon 03-08-20Mon 03-08-2011,10,9 03-08
Task Inactive Task Manual Summary Rollup External Milestone
Split Inactive Milestone Manual Summary Deadline
Project: Project1
Milestone Inactive Summary Start-only Progress
Date: Tue 26-05-20
Summary Manual Task Finish-only Manual Progress
Project Summary Duration-only External Tasks
Page 1