ID
Task
Mode
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
Project: proyecto 1
Date: Wed 18/01/17
Task Name
Duration
Start
Finish 13 Feb '17 06 Mar '17 27 Mar '17 17 Apr '17 08 May '17 29 May '17 19 Jun '17 10 Jul '17
W T F S S M T W T F S S M T W T F S S
proyecto 1
inicio
fase 1
fase 1.1
fase 1.2
fase 1.3
fase 2
fase 2.1
fase 2.2
fase 2.3
fase 2.3.1
fase 2.3.2
fase 3
fase 3.1
fase 3.2
fase 4
fin
89 days
0 days
19 days
4 days
12 days
3 days
46 days
12 days
8 days
34 days
18 days
16 days
27 days
12 days
22 days
14 days
0 days
Mon 20/03/17Wed 12/07/17
Mon 20/03/17Mon 20/03/17
Mon 20/03/17Wed 12/04/17
Mon 20/03/17Thu 23/03/17
Fri 24/03/17 Fri 07/04/17
Fri 07/04/17 Wed 12/04/17
Fri 07/04/17 Wed 07/06/17
Fri 07/04/17 Tue 25/04/17
Wed 12/04/17Mon 24/04/17
Tue 25/04/17 Wed 07/06/17
Tue 25/04/17 Wed 17/05/17
Thu 18/05/17 Wed 07/06/17
Wed 07/06/17Wed 12/07/17
Wed 07/06/17Wed 21/06/17
Tue 13/06/17 Wed 12/07/17
Thu 18/05/17 Mon 05/06/17
Wed 12/07/17Wed 12/07/17
20/03
12/07
Task
Inactive Task
Start-only
Split
Inactive Milestone
Finish-only
Milestone
Inactive Summary
Deadline
Summary
Manual Task
Critical
Project Summary
Duration-only
Critical Split
External Tasks
Manual Summary Rollup
Progress
External Milestone
Manual Summary
Page 1
10 Jul '17 31 Jul '17 21 Aug '17 11 Sep '17 02 Oct '17 23 Oct '17 13 Nov '17 04 Dec '17 25 Dec '17 15 Jan '18 05 Feb '18 26 Feb '18 19 Mar '18 09 Apr '18 30 Apr '18 21 May '18 11 Jun '18
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
12/07
Project: proyecto 1
Date: Wed 18/01/17
Task
Inactive Task
Start-only
Split
Inactive Milestone
Finish-only
Milestone
Inactive Summary
Deadline
Summary
Manual Task
Critical
Project Summary
Duration-only
Critical Split
External Tasks
Manual Summary Rollup
Progress
External Milestone
Manual Summary
Page 2