Tech - Spec. UPS
Tech - Spec. UPS
TECHNICAL SPECIFICATIONS
FOR
1
TECHNICAL SPECIFICATIONS
FOR
3 X 200 KVA UPS SYSTEM
INDEX
PAGE
S. NO. SECTION DESCRIPTION
NO.
1 SECTION –1 SCOPE OF WORK 3
TECHNICAL SPECIFICATIONS FOR 3 x 200
2 SECTION –2 13
KVA UPS AND BATTERY
TECHNICAL SPECIFICATIONS FOR 415 MCCB
3 SECTION –3 21
PANELS
TECHNICAL SPECIFICATIONS FOR XLPE
4 SECTION –4 30
POWER CABLES
5 SECTION –5 TECHNICAL PARTICULARS 35
6 SECTION –6 LIST OF RECOMMENDED VENDORS 42
2
SCOPE OF WORK
FOR
SECTION – 1
3
SCOPE OF WORK
1. INTRODUCTION
CDRI has taken up a project for construction of new campus at Sitapur Road, Lucknow.
This portion of tender is for works related to supply, installation, testing & commissioning
of 3x 200 KVA UPS System with 15 minutes battery back-up & required accessories,
MCCB panels for UPS input power, MCCB panels for UPS output power distribution,
flexible XLPE insulated copper conductor power cables. All these equipment/items shall be
installed in main substation of new CDRI campus. The UPS system planned under this
contract shall cater to meet power requirements of laboratory equipment, sensitive
electronic equipment, computers and networking devices in new CDRI campus.
2. SCOPE OF WORK
In general the scope of works to be performed under this contract shall include but not
limited to:
(i) Design, engineering manufacture, inspection & testing at works, supply, transportation to
site, storage, installation, testing ,commissioning and integrated commissioning of :
(a) 3 nos. UPS of 200KVA to be run in 2+1 parallel redundant load sharing configuration,
complete in all respects with Lead Acid SMF batteries to provide 15 minutes back-up at full
load to feed UPS power to laboratory equipment, networking devices and computers etc. in
different buildings.
(b) Single core flexible copper conductor XLPE insulated power cable 1c x 185sqmm
(minimum size) conforming to IS 7098, Part-1 (latest revision) and other applicable relevant
IS for cables. This cable shall be used for interconnection between UPS and MCCB panels
(Ref. Drg.No:NI-499-I-001-Rev 00 ). Termination of power cable at both ends ( UPS and
MCCB panels) with required hardware and accessories shall be in the scope. Bidder to
check & confirm the suitability cable ( size- 1c x 185 sqmm) for interconnection between
UPS & MCCB panels.
(c) UPS input power supply panel (MCCB Panels) and UPS outgoing power supply panel(
MCCB panels)) with required accessories. (Ref. Drg.No:NI-499-I-001,Rev.00)
4
( iii ) Supply, installation, testing & integrated commissioning of the complete system as per the
approved drawings/documents.
( vi ) All statutory approvals / license for the equipment(s) / system(s) shall be obtained by the
contractor as needed including approval of relevant drawings from the electrical
inspectorate of UP Govt. / competent authority & approval of the entire installation, after
completion of work as per the approved drawings/documents.
( vii ) Effective co-ordination with the other agencies ( internal & external) to carry out the work
smoothly.
( viii ) Proper handing over of the installations in satisfactory working conditions alongwith
required as built drawings, documents and items as specified in the tender.
( ix ) The work shall also include all incidental job connected with the installation of equipment.
(x) All electrical equipment except battery shall be designed considering 50 C as ambient
temperature.
(xiii) Providing complete set of final drawings & documents ( 6 sets of hard copy & 2 soft
copy)
( xiv ) Any work like chipping/breaking of existing structure like walls ,floors, fabrications etc.
required for installation shall be done without any extra cost and after prior approval of the
EPI/CDRI representative.
(xv) Repairing of the damaged structure to the satisfaction of the EPI/CDRI representative
without extra claim, in case any existing structure is affected/damaged due to the
installation work.
( xvi ) Any modification/rework required to be done on account of wrong practices .No extra claim
is admissible for this type of work.
5
The specification defines the requirements for a continuous duty; highly reliable, latest and
state of art technology; solid state type microprocessor based true on-line double conversion
Uninterruptible Power Supply System. The UPS shall provide high quality AC power to
sensitive electronic equipment, laboratory equipment, computers , servers and networking
devices etc. The output load for UPS system (3X200 KVA) shall be 400KVA ( Approx.).
The UPS system and components shall comply in all respects with the requirements of the
latest editions of the relevant codes and Indian Standards./International Standards .
The UPS system shall conform to the latest issue of relevant applicable International
standards/IEC standard /Indian standards for design, manufacturing, safety, inspection and
installation.
The system shall also conform/comply to the provision of Indian electricity rules and other
statutory regulations in force time to time and IEEE requirementsfor UPS and battery
design.
4. SITE CONDITIONS:
The system should be suitable for installation and satisfactory operation in the indoor
substation building with restricted natural air ventilation in humid and corrosive atmosphere
5. POWER SUPPLY :
6. INSPECTION OF SITE :
The bidder to inspect and examine the site and its surrounding and shall satisfy as to the
nature of the ground and sub soil, the quantities and nature of work, materials necessary for
completion of the work and their availability, means of access to site and in general to
obtain all necessary information as to risks, contingencies and other circumstances which
may influence or affect his offer. No extra claim consequent on any misunderstanding or
otherwise shall be allowed.
7. PRICE :
Price shall be inclusive of all taxes & duties whatsoever, excise duty, sales tax,
CST/VAT, service tax, octroi (if any), work contract tax, commissioning spares,
labour, tools & plants, packing, freight/ transportation & insurance up to the site,
loading, unloading, fee (s) for testing, license, inspection, documents, etc, where
applicable.
CDRI does not give any confessional forms/ certificates/ permits towards any taxes,
duties & other levies like sales tax, customs duty, road taxes/ permits, etc.
Prices shall be firm through out the contract period.
6
8. BOQ QUANTITIES:
The quantities given in the tender BOQ may vary as per the site / system/CDRI’s
requirements. Only required items & quantities are to be supplied/ installed. The rate shall
remain valid for any variations in the estimated quantities given in price bid. Contractor
shall take detailed site measurements for the items like supply of power cables; earth
strips/wire etc., before placing purchase order/taking procurement action.
9. MAKES :
In general make of various items shall be as per the list enclosed. Wherever makes have
not been indicated in the list, the items shall be of ISI marked subject to approval by
EPI/CDRI.
Sample of the items or makes or the items for manufacture/ supply/ use in the work
irrespective of appearing in the approved list shall be got approved from Engineer- in-
charge before incorporation.
10. SPARES :
The bidder shall indicate and include in quoted price, all the start-up and commissioning
spares. The bidder shall also furnish the complete list of recommended spares with unit rate
of each item for 3 years of normal operation of all equipments alongwith the bid.
All equipment, materials used in the work shall be brand new and free from manufacturing
defects.
All defective/damaged items shall be replaced with the good ones without any extra cost
as per guarantee clause.
All the required special tools & tackles for executing this work shall be in the scope of
the vendor
7
15. QUALITY OF WORK & WORKMANSHIP:
The quality of work, workmanship, finishing etc should be satisfactory to the CDRI / EPI.
16. ACTION PLANS/ PROGRAMME/ WORK SCHEDULING/ CPM & PERT CHARTS
/ PROGRESS REPORTS/ BAR CHARTS /REPORTS & RECORDS :
The successful bidder shall submit the necessary reports during various stages of contract
which include action plans/ programme/ work scheduling/ CPM (Critical Path Method) &
PERT (Project Evaluation and Review Technique) charts / progress reports/ bar charts and
various records, statements, reports, documents related to the work.
A comprehensive action plan/programme/schedule has to be made based on the completion
period, inter related activities and got approved from CDRI/EPI
As and when required contractor shall attend the review meetings and take necessary
actions with regard to the pending works, targets, co-ordination with other agencies.
senior/ competent officials/ engineers who can take decisions and implement from the
vendor side to take stock of the situation and do the needful shall also make regular site
inspections.
Dispatch schedules are to be informed and got approved by the vendor from Engineer in
charge, before dispatch of materials.
-All acceptance and routine tests as per relevant standards and specifications shall be carried
out. Charges for all the tests shall be deemed to be included in the bid price. Routine
test/acceptance test shall be carried out in the presence of the inspecting officer
fromEPI/CDRI.
- All major items listed in list of approved makes for electrical items
shall be factory inspected. The decision to inspect/waive shall rest with the CDRI/EPI. .The
list of approved makes enclosed is indicative, CDRI/EPI can add/delete/modify the same in
the interest of organization/work from time to time considering cost, quantity, significance,
completion schedules etc.
8
- At least 15 days advance notice to be given for factory inspection.
While inspection call is given, the actual status and details of test to be offered shall be
communicated. Relevant applicable Indian standards & International standards shall be
made available.
Due care to be taken for loading, handling, unloading, shifting, lifting, jacking etc by
suitable means like Cranes, Fork lifts, Chain pulley blocks, mechanized means etc. and
experienced man power.
Contractor shall obtain necessary entry pass/ token/ identity card for work force from
CDRI/BCAS/CISF/CRPF etc who is in charge of security matters. It is the responsibility of
the contractor to fulfill all the relevant formalities viz. police verification, photographs,
addresses and keeping in safe custody etc and bear the fee, if any.
Following information and documentations in addition to what has been asked for in
respective equipment specification shall be furnished by the contractor
Following information and documentations in addition to what has been asked for in
respective equipment specification shall be furnished by the successful bidder after award
of contract for approval/reference/record of the purchaser.
All drawings submitted shall provide sufficient detail indicating type, size, general
arrangement & foundation drawing, weight, the external connections, fixing
arrangement required, the dimensions required for installation and interconnections
with other equipment and materials, clearances and space required between various
portions of equipment and any other information specifically requested.
All the above document shall be furnished in 4 sets to EPI/CDRI for review. One set
shall be returned with comments / approval. The document shall be modified
incorporating the comments given by EPI/CDRI and 4 sets of corrected documents shall
be submitted by contractor within 10 days time.
Wherever special tools & tackles are required for operation & maintenance of
units/systems, the contractor supplying the equipment shall provide the same free of cost.
10
25. STATUTORY LAWS/RULES/APPROVALS/LICENSE:
The contractor/agency shall abide by the relevant statutory rules, laws, and guidelines and
arrange for the approvals, if any required. That include adhering to labour laws, abiding
local electricity rules etc.
Where ever formal approvals/ license are essential like CEA approval, clearance by the
Electrical inspectorate etc,. the same shall be arranged by the bidder
Unless otherwise specified, the fees/charges involved for this purpose shall be borne by the
bidder.
Necessary site tests/ performance tests shall be conducted on the equipment to ascertain the
functional / design/ site requirements. Reports shall be prepared recording the various
values, parameters, observations, settings made etc. In case of unsatisfactory results, the
same shall be replaced/ rectified as per the requirement without any extra cost.
Up on the satisfactory commissioning of the entire system, the system shall be observed for
15 days. After this satisfactory trial period, the work shall be handed over officially and
completion date recorded by Engineer-in- charge with all the prescribed formalities for
handing over.
This date shall be reckoned, as the certified date of completion and the defects liability
period shall commence from this date.
Until the handing over of the installation, the responsibility lies with the vendor for safety,
upkeep etc.
30 COMPLETION PLANS:
11
Bill of Quantities indicating makes, Technical specs, quantity etc.
Details of Inventory
2 sets of Photographs, 4x6 size, of all the major equipment to be submitted. One set
shall be displayed in the substation and one set shall be submitted in a good quality
photo album.
Defects liability period shall be 12 months from the certified date of satisfactory completion
& handing over of entire work to Engineer-in-charge of work.
During this period, the contractor shall hold himself responsible for reinstallation or replace
with good ones free of cost to the CDRI in respect of any defective
item/material/equipment/component supplied and installed by the contractor. Contractor
shall bear all the cost involved for supply, transportation and installation etc. of such items.
32 GUARANTEED PERFORMANCE:
The performance figures quoted in Guaranteed Technical Particulars shall be with in the
tolerance permitted by relevant Indian Standards unless otherwise stated in Technical
Specification. Incase of failure of the equipment to meet the guarantee parameters the
equipment may be liable for rejection.
12
TECHNICAL SPECIFICATIONS
FOR
UPS
13
SECTION – 2
1.0 General:
The specification defines the requirements for a continuous duty, three phase, highly
reliable, latest and state of art technology, solid state true on-line double conversion fully
microprocessor controlled, IGBT based ( Rectifier and Inverter) Uninterruptible Power
Supply system to provide high quality AC power to sensitive electronic equipment,
laboratory equipment, computers and networking devices etc. The output load for UPS
system shall be 400 KVA (approx.).The UPS system design should be based on latest
generation of technology with proven performance.
The UPS system should be suitable for installation and satisfactory operation in a closed
substation building with restricted natural air ventilation in a humid & corrosive
atmosphere, ambient temperature upto 43˚C, relative humidity 95% and altitude to 1000m
above MSL.
The UPS system shall conform to the latest issue of relevant applicable International
Standards/IEC standard /Indian standards for design, manufacturing, safety, inspection and
installation. The system shall also be conforming to the provision of Indian electricity rules
and other statutory regulations in force time to time and IEEE requirements for UPS and
battery design.
During the normal operation when mains power is available all the three UPS operating in
parallel equal load-sharing mode shall supply synchronized output power to load though
common output panel. In case, if one UPS fails, the other two UPS should be able to
takeover equally the connected full load and faulty unit should disconnect automatically.
Upon repair of the faulty UPS, it shall be reconnected to the load to resume redundant
operation.Any UPS unit should be capable of being taken off the load manually for
maintenance without disturbing the output load.
14
The input raw power to UPS shall be fed from MCCB panels and the output power shall
be distributed to load through common output panel ( Ref: Drg no. NI-499-I-001-Rev.00).
Both input and output panels shall have all required electrical protection swithes, Isolators,
MCCBs and metering devices etc.
The UPS system shall have redundant communication cable and control with paralleling kit
for synchronization among each other. When a disturbance/fault occurs, the faulty unit
should be isolated and power to entire load should be fed from the other two UPS.. When
two UPS develop fault, the complete load should be transferred to bypass supply through
static switch (If static bypass switch is in enabled condition) with status indications.
3.1 Static bypass switch and manual bypass switch (for each UPS)
3.2 Control system to control all the three phases individually in case of unbalancing. there
should not be any change in regulation in phase voltage. with 100% unbalancing.
3.3 Forced ventilation through redundant fan for UPS cabinet for normal as well as emergency
conditions. All the air entries to the cabinet shall be protected with cleanable filters.
3.6 a) Inbuilt alarm record facility with capacity to store minimum 100 events.
b) Inbuilt digital fault diagnostic facility through stored events to supervise the UPS
operation & failure with printout facility of faults and input/output voltage and current
waveforms display.
3.9 Surge protective devices at Input/Output to protect system and load equipment against any power
surges due to lightning, switching etc.
3.12 A suitably sized earth bus at the bottom of the UPS panel with provision for earth
connection at both ends.
3.13 When battery taken out for maintenance during that period inverter should continue to
operate taking power from rectifier.
15
3.14 All the control wiring in plastic channels, neatly bunched together, each wire should be
identified at both ends by self sticking wire maker tapes or PVC ferrules as per the
standard.
3.15 Inside the panel power and control wiring with suitably sized PVC insulated copper
conductors.
Indoor lead acid SMF battery bank of 172800 VAH capacity to meet 15 minutes back-up
requirements for each UPS complete with suitable battery racks of power coated MS
material stand, connectors, isolator, MCCBs, interconnecting cables. between UPS and
batteries for each UPS and other required accessories Earthing arrangement shall be
provided for batteries rack earthling. From UPS to batteries the cable routing length is to be
considered as 30 meters (approx.).Bidder to supply required length of cable as per the UPS
and battery room layout drawings (Refer NIT Drg no-NI-499-I-002-Rev.01) .
3.17 Provision for on-line automatic battery testing facility and display of status indications (in
battery mode) with connected load for:
(i) Actual battery AH capacity left.
(ii) Actual battery back-up time available in battery mode.
(iii) Bad battery status.
16
4.10 Overall efficiency (AC to AC) : > 91 %
4.22. Indications and Alarms : All indications shall be backlit LCD Type including
temperature of system, ambient, battery room, inverter
section and rectifier section (Bidder to furnish the list
of all indications and alarms).
4.27 Controls : The system shall have controls for Input circuit
breaker/switch, Bypass circuit breaker/static bypass
switch, maintenance bypass switch, Inverter On/Off
switch, rectifier On/Off,
Alarm acknowledge switch, Output switch, battery test
etc.
4.30. UPS failure : During failure in the UPS system the static switch
shall automatically transfer the A.C. load directly to
the AC line without affecting equipment operation, if
static bypass switch is in enabled condition.. (System
shall have facility to enable/disable the static
bypass)
4.31. Maintenance by- pass : Each UPS shall have inbuilt maintenance bypass to
connect the mains/alternate supply to critical load.
4.32. Battery disconnect switch : To electrically isolate the storage batteries from UPS
module.
4.33. Static bypass: Each UPS shall have in-built static bypass .In event of
any fault in one UPS ,the faulty UPS shall isolate itself
and the other two healthy UPS shall take over the full
load. All the loads shall be transferred to the static
bypass if the two UPS fail simultaneously or if
overload beyond 150% for 1 minutes is faced by UPS,
18
4.35. Product Documentation : Manufacturer shall supply product documentations in
hard copy and in CD (soft copy) as specified.
i) Installation
ii) Operation
iii) Maintenance
This should include complete outline and external connection drawings and schematic and
physical wiring diagrams as well as parts list and parts layout down to the smallest
components level. It should include startup and service manuals with complete privation
and remedial maintenance and trouble showing instructions. This should include all
ancillary equipment and accessories.
ii) All material shall be supplied latest and of best commercial grade.
iii) Brackets and securing hardware shall be electroplated with corrosion resistance material.
iv)Internal wiring conductors shall be combined into cable or bundles and shall be tied
securely together and numbered or coded to correspond with documentation.
v)The UPS panes and other panels shall be provided with lifting hooks, detachable gland plates
for bottom cable entry.
4.37. Battery
4.37.1 The battery shall be lead acid, sealed maintenance free (SMF).
4.37.2 Batteries shall conform to all type test as per relevant applicable IS/IEC standards. All
acceptance tests as required by the relevant applicable IS/IEC shall be carried out at site after
completion of installation work.
4.37.3 The contractor shall arrange all necessary equipment including the variable resistor, tools,
tackles and instruments. A set of special tools & tackles which are necessary for maintenance
and overhauling of the batteries shall be supplied.
4.37.4 The battery shall be supplied with racks, connecting hardware and standard service
resistance material, accessories. The battery shall be delivered charged and ready for service
alongwith accessories, mats etc.
4.37.5 The UPS should continue to function and meet all the performance criteria specified, If
the batteries are taken out for maintenance by manually disconnecting the switch.
19
UPS system shall be inspected and tested as per the relevant applicable standards and
approved QAP. Quality assurance plan shall be submitted by the supplier for approval
before the inspection, alongwith all the internal test reports, type test
reports/certificates and necessary documents.
7.0 Training
Training on operation and maintenance of UPS shall be provided to purchaser’s
representatives/operators by the UPS vendor.
20
*To be submitted with technical offer
TECHNICAL SPECIFICATIONS
FOR
SECTION – 3
21
TECHNICAL SPECIFICATION FOR 415 V MCCB PANEL
1. DESCRIPTION OF WORK :
This section covers the detailed requirements for design, manufacture, inspection,
transportation to site, installation testing & commissioning of MCCB. Panels
suitable for 415 Volts, 3 phase, 50 HZ, 4 wire system, in line with single line
diagram ( NI-499-I-001), schedule of quantities and as specified.
415V MCCB Panels shall conform to latest applicable IS, IEC standard as listed
below and other relevant standards / code as applicable.
3. SPECIFICATIONS :
3.1 GENERAL
3.1.1 The panels shall be capable of fault withstand capacity of 35 KA for duration of one
second.
3.1.2 The panel shall be metal enclosed, indoor type having sectionalisation of incoming,
and outgoing supply. The design shall be cubicle type as specified.
22
3.1.3 The panel shall be floor mounted free standing totally enclosed and extensible type.
The panel shall be with lockable arrangement with degree of protection IP - 54 and
shall be suitable for the climate conditions as specified. The design shall include all
provisions for safety of operating and maintenance personnel.
3.2 CONSTRUCTION
3.2.1 The panel shall be shall be fabricated out of CRCA sheet steel 2.0 mm thick.
Wherever necessary, such sheet steel member shall be stiffened by angle iron
frame work. General construction shall employ the principle of
compartmentalization and segregation for each circuit. Unless otherwise approved,
incomer and bus section panels or sections shall be separate and independent and
shall not be mixed with sections required for feeders. Each section of the rear
accessible type board shall have hinged access doors at the rear. Overall height of
the board shall not exceed 2.40 meters. Operating levers, handle etc. of highest unit
shall not be at a height more than 1.8 m, and that of the lowest unit shall not be less
than 300 mm above finished floor level. Multi-tier mounting of feeders is
permissible. The general arrangement for multi-tier construction shall be such that
the horizontal tiers formed present a pleasing and asthetic look. The general
arrangement shall be got approved before fabrication. Cable entries for various
feeders shall be either rear or from the front through cable alleys located in between
two sections of minimum 300 mm width. There shall be separate gland plate for
each cable entry so that there will not be dislocation of already wired circuit when
new feeders are added. Cable entry plates shall therefore be sectionalised. The
construction shall include necessary cable supports for clamping the cable in the
cable alley or in rear cable chamber.All cable entries shall be from the top/bottom as
specified. Gland plate shall be minimum 3 mm thick.The panels colour shall be
-7032 siemenes gray ( Subject to approval of CDRI/EPI). Enclosure protection class
of panel shall be IP-54.
Panel shall be design for cable entry from bottom / top as required. Sufficient space
shall be provided for each of termination and connection. All provision and
accessories shall be furnished for termination and connection of power cables
including removal gland plates, copper / aluminium lugs, double compression brass
glands with tapped washer and terminal blocks. Bus Duct connection shall be from
the top. All provision for Bus Duct connection with accessories shall be provided.
3.2.3 Instruments
All meters shall be Digital type flush mounted type conforming to class 1.0 for
accuracy and of size of 96 mm2 for incoming feeders and outgoing feeders.
3.2.5 Wiring
All wiring controls, indication etc. shall be with minimum 2.5 sq. mm suitable
stranded copper conductor cables PVC insulated. Wiring shall be suitably protected
within the panels. Runs of wires shall be neatly bunched and suitably supported and
clamped. Means shall be provided for easy identification of the wires. Identification
ferrules shall be used at both ends of the wires. All control wiring meant for external
connection are to be brought out on terminal board. Brass/Copper thinbles,
insulation tape etc. shall be provided at joints & terminations as required.
i. All control terminal blocks shall be unbreakable and IP 20 compliant. The metal
parts of the terminal block including the captive screw shall be of Cu. Alloy and its
housing shall be Polyamide class V0/V2 as per UL94. It shall be suitable for
mounting on both C&G type rail and shall be capable to withstand vibration level
upto 5g.
ii. High current carrying terminal blocks suitable for 25-240 sq. mm wire shall contain
individual terminal sleeve cover on each termination which is also individually
separatable, to avoid accidental touch. It housing material shall be Polyamide as per
UL 94 and shall be separated from each other by separating/partition plate.
a. The bus bar shall be of copper (electrolytic grade) and of adequate section.
The bus bar system shall comprise a system of totally enclosed main
horizontal bus bars run at the top and vertical bus bars serving all modules in
vertical section on either side in cable entries. In case of rear access,
horizontal bus system shall run suitably either at the top or bottom. All
connections to individual circuits from the bus bar shall be with solid
connections. All horizontal bus bar, vertical bus bar and connections shall be
suitably sleeved with PVC sleeves or suitably insulated in an approved
manner.
b. The bus bar temperature should not exceed 90o C i.e. 40oC temperature rise
over 50oC ambient. The calculation for temperature rise and bus bar sizing
should be furnished along with shop drawing for approval.
c. Wherever copper bus bar and Aluminum bus bar are connected to each other,
bimetallic strip shall be used.
24
ii. Bus Bar Supports and Attachments
Bus bar shall be firmly fixed on supports constructed from SMC (glass fibre
reinforced thermosetting plastic). The supports shall be sufficiently robust to
effectively withstand electro-mechanical stresses produced in the event of
short circuit.
Connections to bus bars shall be made with bolts and nuts. Holes drilled into
the bus bars may be made. Suitable precaution shall be taken against heating
due to bi-metallic contact. Further for tapping off connections from bus bars,
PVC insulated wire may be used for current capacities upto 100 amps and for
higher current capacities solid conductors/strips suitably insulated with PVC
sleeves/tape shall be used.
iv. Clearances
The minimum clearances to be maintained for open and closed indoor air
insulated bus bars/electrically non-exposed and working at system voltages
upto 600 volts shall be as follows :
--------------------------------------------------------------------------------------------
Between ................................................. Minimum Clearances
Main bus bar connections and auxilliary wiring etc. shall conform to relevant
Indian Standard. A brief from I.S. 375 (revised) is given below:
Bus bars and main connections, when marked shall be marked in accordance
with the following table to indicate the order in which the voltages in phases
reach their maximum values.
--------------------------------------------------------------------------------------------
System As indicated by Phase sequence
Colors or letters as indicated
Vectorially
--------------------------------------------------------------------------------------------
Three Phase Red, Yellow, Blue R, Y, B.
--------------------------------------------------------------------------------------------
Bus bars and main connections which are substantially in one plane shall be
arranged in order given as follows:
a. A.C. System
iv When the system has a neutral connection in the same plane as the
phase connections, the neutral shall occupy an outer position.
v Unless the neutral connections can be readily distinguished from the
phase connections, the order shall be red, yellow, blue and black.
b. Terminations
Incoming terminals shall be suitable for receiving cables.
3.4.2.1 Moulded case circuit breakers shall comply with the latest Indian Standards and
IEC standards. They shall have the voltage and current ratings, rated duty, rated
short circuit service breaking capacity and rated short-time withstand current as
indicated. All the MCCBs shall be provided with electronic releases
(microprocessor based)
3.4.2.2 MCCB's shall be of the independent manual closing air-break type, rated for an
uninterrupted duty, unless otherwise indicated.
3.4.2.3 Each MCCB shall have a facility for padlocking in the "OFF" position.
3.4.2.4 MCCB shall have front operating extended door operating handle.
Voltage transformers shall be cast resin type with accuracy class of 1.0.
3.7 RELAYS :
The vendor shall furnish, install and co-ordinate all relays to meet the requirement
of protection, interlock and bus transfer scheme as indicated in BOQ, Drawing,
Specification and system requirement. Relays shall be Microprocessor type.
3.8 EARTHING
All components, frame etc. shall be properly earthed. Al. earth bars of 50 mm x 6
mm shall be provided for the MCCB panels for the full length of the panel and
27
connected to the frame work. Provisions shall be made for connection from this
earth bar to the main earthing bar on both sides of MCCB Panels.
3.9 PAINTING
All steel work used in the construction of the MCCB panels shall have undergone a
rigorous metal treatment process as follows :-
Pickling in dilute sulphuric acid to remove oxide scales & rust formation, if any,
followed by cold water rinsing to remove traces of acidic solution.
Primer coating with two coats of a highly corrosion resistant primer, applied wet on
wet and stove dried under strictly controlled conditions of temperature and time.
3.10 LABELS
Anodised Aluminium labels shall be provided on all incoming and outgoing feeder
switches. Circuit diagram showing the arrangement of the circuit inside the LT
panel shall be pasted on inside of the panel door and covered with transparent
laminated plastic sheet. Caution notice place shall be affixed at the back of each
vertical panel.
Each vertical panel shall be provided with thermostat controlled space heater and
5A 3 pin plug socket. Separate transformer for space heating supply has to be
arranged.
5. TESTING
6.
(viii) Bill of material indicating quantity, rating and make of all component.
(iv) Routine test certificates carried out on the panel. (All internal test
reports/certificates)
(v) Type test certificates for any equipment if so desired by the owner.
29
* - To be submitted with technical offer.
TECHNICAL SPECIFICATIONS
FOR
SECTION – 4
30
TECHNICAL SPECIFICATION FOR XLPE INSULATED POWER CABLES
1. SCOPE
This section covers supply and laying of 1c x185 sqmm size XLPE flexible copper
conductor power cables.( UPS supplier to check size and suitability of cable)
All standards, specifications and codes of practice referred to herein shall be the
latest editions including all applicable official amendments and revisions. The
cables shall conform to the following standards and codes:
IS : 7098 (Part-1) Cross linked polyethylene insulated PVC sheathed cables for
working voltages upto and including 1100V
3. INSTALLATION OF CABLES
Cables in UPS room and battery room shall be laid in trench on multi tier trays
covered with trench cover. All cables shall be bent in radius not less than 15 times or
as prescribed by the manufacturer which ever is higher. Cable laying shall be
carried out as per CPWD specifications.
4 POWER CABLE
The cable shall conform to IS: 7098 (Part I) and as specified in schedule.
4.1 GENERAL
31
LT power cable shall be supplied inspected, laid, tested and commissioned in
accordance with drawings, specifications, relevant Indian Standards Specifications
and cable manufacturer’s instructions. The cable shall be delivered at site in
original drums with manufacturer’s name clearly written on the drum.
4.2 MATERIAL
The power cable of 1c x 185 sqmm size shall be XLPE insulated Copper conductor
flexible cable conforming to IS : 7098 (Part-I). Vendor to ensure the suitability of
the cable size specified.
4.3 INSPECTION
All cables shall be inspected upon receipt at site and checked by the Engineer-in-
Charge for any damage during transit.
4 INSTALLATION
5.1 GENERAL
The cable installation shall be carried out in accordance with the specifications
given herein. For details not covered in these specifications, I.S. 1255 shall be
followed.
5.2 ROUTE
i. Before the cable laying work is undertaken, the route of the cable shall be
decided by the Engineer-in-Charge.
iii. As far as possible, the alignment of the cable route shall be decided taking into
consideration the present and future requirements of other agencies
iv. Whenever cables are laid along well demarcated or established roads, the MV
cables shall be laid further from the kerb line than HV cables.
vi. Cables of different voltages and also power and control cables shall be kept in
different trenches with adequate separation.
v Where cables cross one another the cable of higher voltage shall be laid at a
lower level than the cable of lower voltage.
32
5.3 PROXIMITY TO COMMUNICATION CABLES
5.3.1 Power and communication cables shall as far possible cross at right angles. Where
power cables are laid in proximity communication cables the horizontal and vertical
clearances shall not normally be less than 60 cms.
5.4.1 Cables shall generally be laid in trenches, pipes/closed ducts, in open ducts, direct in
ground or on surface depending on site conditions.
Cable tags shall be made out of 2mm thick aluminum sheets, each tag 1-1/2 inch in
dia with one hole of 2.5mm dia, 6mm below the periphery. Cable designations are
to be punched with letter / number punches and the tags are to be tied inside the
panels beyond the glanding as well as below the glands at cable entries. Trays tags
are to be tied at all bends. On straight lengths, tags shall be provided at every 5
meters.
Prior to installation of cables,the following tests shall be carried out. Insulation test
between phases, phase & neutral, phase & earth for each length of cable.
Before laying.
At the time of issue of cables for laying, the cable shall be tested for continuity and
insulation resistance.
The cables shall be tested for continuity of cores and insulation resistance and the
cable length shall be measured, before closing the trench. The cable end shall be
sealed /covered.
After laying.
Earth Test.
All tests shall be carried out in accordance with relevant Indian Standard code of
practice and Indian Electricity Rules. The Vendor shall provide necessary
instruments; equipment’s and labour for conducting the above tests & shall bear all
expenses of conducting such tests.
34
.
TECHNICAL PARTICULARS
(TO BE FILLED-IN BY THE BIDDER)
SECTION – 5
01 UPS SYSTEM 36
02 MCCB PANELS 38
03 XLPE INSULATED POWER CABLE 40
04 BATTERY 41
35
(A) TECHNICAL PARTICULARS FOR
3 X 200 KVA UPS - PARALLEL REDUNDANT (2+1)
4 Input THDI
7 Inverter Type
8 Rectifier Type
36
19 Transient Response at
-Dynamic condition
-Static condition
20 Recovery Time to Steady State
21 Display Type
22 Load PF Range
23 MTBF
24 Noise Level
25 Communication Protocols
26 Total system losses
27 Recommended operating temperature -
UPS-
Battery -
28 Protection Class UPS
29 UPS Indications (LCD)/Alarms
30 Output Isolation Transformer
(Type and mounting)
31 Switch Over time upon failure of AC
power
32 Input /Output side surge suppression
33 Expandability (nos)
34 Battery VAH - (for 15 minutes back-
up)
35 Battery Type
36 Battery Isolation
38 Make of Battery
37
(B) TECHNICAL PARTICULARS FOR 415V MCCB
PANELS
Sl.
Description Quoted Data
No.
1.0 Assembly
1.1 Make
1.2 Type
1.4 Voltage
1.8 Enclosure
a) Degree of protection
2.0 Construction
3.0 Busbar
3.1 Make
38
Sl.
Description Quoted Data
No.
a) Main busbar
b) Vertical busbar
4.0 MCCB
4.1 Make
4.2 Type
5.1 Make
5.2 Type
5.4 Ratio
5.5 VA rating
5.6 Class
a) Metering CT
6.0 Meter
6.1 Make
6.2 Type
6.4 Size
39
( C ) TECHNICAL PARTICULARS
FOR
XLPE POWER CABLES
a) Continuous C :
b) Short Time C :
1.5 Conductor
a) Material :
b) Size in mm2 :
1.6 Insulation
a) Material :
b) Thickness (mm) :
a) Material
b) Thickness (mm) :
40
( D ) TECHNICAL PARTICULARS
FOR BATTERY
1.1 Make :
41
LIST OF RECOMMENDED MAKES
( CABLES, PANELS & COMPONENTS)
SECTION – 6
42
LIST OF RRECOMMENDED MAKES
Note : Items which are not covered in the above list shall be supplied subject to approval of make
by EPI / CDRI (before procurement)
44
LIST OF DRAWINGS
SECTION – 7
45
List of Drawings
UPS SYSTEM
46