Eco Valley Homes Construction Report
Eco Valley Homes Construction Report
BACHELOR OF TECHNOLOGY
In
CIVIL ENGINEERING
PRABHJOT SINGH
(11504053)
[Link]. 8thSemester
PUNJABI UNIVERSITY
PRABHJOT SINGH
11504053
DATE……………………
Certified that the above statement made by the student is correct to the best of our
knowledge and belief.
ACKNOWLEDGEMENT
3. Site investigation…………………………………………………….5
B) Concrete Test……………………………………………………15
C) Brick test………………………………………………………….17
5. Estimation:…………………………………………………………..19
A) Method of estimation…………………………………………….19
B) Estimation of brickwork……………………………………………20
6. Demarcation:…………………………………………………………….27
8. Excavation :………………………………………………………………….33
B) Concreting………………………………………………………………..35
9. Foundation:……………………………………………………………..37
A) Type of Foundation………………………………………………..38
12. Beams:…………………………………………………………………..52
C) Lintel Beam…………………………………………………………..54
13. DPC………………………………………………………………………56
14. Slab:………………………………………………………………………58
A) Procedure……………………………………………………………58
15. Various other works and features at site……………………………...63
A) Sunken slab…………………………………………………………..63
B) Duct…………………………………………………………………….64
C) Sewer work……………………………………………………………65
G) Bent up bars…………………………………………………………….70
H) Overlapping of bars……………………………………………………..71
I) Vibrator …………………………………………………………………72
Project Details :
There Would Be Three Blocks Of Size 94’X115’ is Being
Constructed Each Block Consist Of 6 Floors and 4 apartments
The Foundation For These Blocks is Isolated footing
At our site cement of 43 grade was used
Aggregates used at our site:
o Coarse aggregates of 12.5 and 20 mm sizes.
o Fine aggregates in the form of coarse sand.
At our site reinforcement bars of 8,10,12 and 16mm were used.
At our site mortar of ratio 1:6 (cement:sand) was used in brick
masonry work.
At our site English Bond was used in brick masonry in all
buildings
M20 Concrete was used in every building
Our Project
Current Status
Steps Involved In Construction Of
Residential Building:-
Construction of residential building required following paper work before the
start of actual construction. These steps are;
Purposes:-
1. To evaluate the general suitability of the site for the proposed project
3. To disclose and make provision for difficulties that may arise during
construction
1. Desk study
2. Preliminary reconnaissance
4. Laboratory test
5. Report writing
Phase 1 (Desk Study) :-
This is the phase where all the information that are available, are collected.
The information which needs to be collected are as follows
Site plan
Type, size & importance of the structure
Loading conditions
Previous geo-technical reports
Topographical maps
Still photographs etc.
Soil Tests :-
The first step in this connection is the inspection of the site and its vicinity
to get a preliminary idea of the site conditions. This includes the study of
the existing buildings in the neighborhood and if possible the type of their
foundations. The cuts made in the nearby areas should also be looked into.
The subject can be discussed with those persons who were associated in
constructing buildings in the surroundings with regard to their experiences
and difficulties encountered by them.
Test Pits
Test pits are dug by hand or by excavating machines. The size of the pit
should be such that a person can easily enter the pit and have a visual
inspection. Both disturbed and undisturbed soil samples are collected from
the pit for detailed analysis.
Probing
This will give a rough idea of the underlying soil. In this, a steel bar of 25 to
40 mm (1 inch to 1.5 inch) in diameter is driven into the ground until a hard
stratum is met with. The bar is driven by a hammer. The bar is then drawn
out at intervals and the soil sticking to the bar is examined to get an idea of
the type of thesoil. An experienced workman can assess the nature of the
soil by observing the way the rod is penetrated into the soil.
Boring
In this process, bore holes are made in the ground and the soil samples
collected. Boring helps in obtaining 1) extent of each strata of soil/rock 2)
nature of each stratum and the engineering properties of the soils 3)
location of ground water table. The depth and number of boreholes will
depend upon the type of the structure and nature of thesoil as obtained
from preliminary examination. The depth of boreholes is governed by the
depth of the soil affected by the loading. As a rough estimate, it is advisable
to investigate the subsoil to a depth of at least twice the width of the
anticipated largest size of the foundation. In case of a pile foundation, the
depth of boring should extend into the bearing stratum.
Methods of Boring for Soil Investigations
The different methods of boring are:
Auger Boring
The examination of the soil for ordinary buildings can be done by a post
hole auger. The auger is held vertically and is driven into the ground by
rotating its handle. At every 30 cm of depth, the auger is taken out and the
soil samples collected
Wash Boring
Wash boring is commonly used for boring in difficult soil. The hole is
advanced by an auger and then a casing pipe is pushed to prevent the
sides from caving in. A stream of water under pressure is forced through
the rod into the hole. The loosened soil in suspension in water is collected
in a tub.
Percussion Boring
In this method, the substrata is broken by repeated blows by a bit or chisel.
Water is circulated in the hole and then the slurry is bailed out of the hole.
Core Drilling
When rocks are to be penetrated for examination, core drilling is resorted
to. In this process, a hole is made by rotating a hollow steel tube having a
cutting bit at its end.
Bearing Capacity
The bearing capacity of a soil is defined as the capacity of the subsoil to
support the load of the structure without yielding. The bearing capacity of
the soil depends upon the characteristics such as cohesion, friction, and
unit weight. The bearing capacity can be determined in the field and also
from the results of tests conducted in the laboratory on the soil samples.
Field Tests
The commonly adopted field tests are:
Standard penetration test, Dynamic cone penetration test, Static cone
penetration test, Plate load test, Vane shear test, and Pressure meter test.
Laboratory Tests
A set of laboratory tests are required to be done to obtain the soil
parameters for the design of foundation. These tests are: Shear strength,
Compressibility, Permeability, Chemical and Mineralogical Composition,
and Soil Classification.
Add water to it and leave it in air tight container for 20hrs. Mix the soil and
divide it into 6 – 8 parts. Position the mold and pour one part of soil into the
mold as 3layers with 25 blows of ramming for each layer.
Remove the base plate and Weight the soil along with mold. Remove the
soil from mold and take the small portion of soil sample at different layers
and conduct water content test. from the values find out the dry density of
soil and water content and draw a graph between them and note down the
maximum dry density and optimum water content of the compacted soil
sample at highest point on the curve.
Points To Remember :-
1. For non-cohesive soils the values should be reduced by 50% if the
water table is above or near base of footing.
2. These values should be used only for preliminary design. The actual
bearing capacity of soil should be calculated as per the standard codes
3. F.O.S varies from 2 to 3 depending upon the type of structure and site
condition.
4. In order to get reliable test result, perform this test on different types of
soil and then use your judgment to reach at any conclusion.
5. Instead of using solid steel ball or square cube, we can also use CBR
test plunger, or Cone (used for cone penetration test)
Concrete Tests :-
Slump Test :-
Equipments
Mould for slump test, non porous base plate, measuring scale,
temping rod. The mould for the test is in the form of the frustum of a
cone having height 30 cm, bottom diameter 20 cm and top diameter
10 cm. The tamping rod is of steel 16 mm diameter and 60cm long
and rounded at one end.
Procedure
When the slump test is carried out, following are the shape of the
concrete slump that can be observed:
o True Slump – True slump is the only slump that can be measured in
the test. The measurement is taken between the top of the cone and
the top of the concrete after the cone has been removed as shown in
figure-1.
o Zero Slump – Zero slump is the indication of very low water-cement
ratio, which results in dry mixes. These type of concrete is generally
used for road construction.
o Collapsed Slump – This is an indication that the water-cement ratio
is too high, i.e. concrete mix is too wet or it is a high workability mix,
for which a slump test is not appropriate.
o Shear Slump – The shear slump indicates that the result is
incomplete, and concrete to be retested
Brick Tests :-
3. Efflorescense test
The presence of alkalies in bricks is harmful and they form a gray or white
layer on brick surface by absorbing moisture. To find out the presence of
alkalis in bricks this test is performed. In this test a brick is immersed in
fresh water for 24 hours and then it’s taken out from water and allowed to
dry in [Link] the whitish layer is not visible on surface it proofs that
absence of alkalis in brick. If the whitish layer visible about 10% of brick
surface then the presence of alkalis is in acceptable range. If that is about
50% of surface then it is moderate. If the alkalis’s presence is over 50%
then the brick is severely affected by alkalies
4. Hardness test
In this test a scratch is made on brick surface with a hard thing. If that
doesn’t left any impression on brick then that is good quality brick.
6. Soundness test
In this test two bricks are held by both hands and struck with one another. If
the bricks give clear metallic ringing sound and don’t break then those are
good quality bricks.
7. Structure test
In this test a brick is broken or a broken brick is collected and closely
observed. If there are any flows, cracks or holes present on that broken
face then that isn’t good quality brick.
Methods Of Estimation
1. Long wall – short wall method
2. Centreline method.
In this method, the wall along the length of room is considered to be long
wall while the wall perpendicular to long wall is said to be short [Link] get
the length of longwall or shortwall, calculate first the centre line lengths of
individual walls. Then the length of long wall, (out to out) may be calculated
after adding half breadth at each end to its centre line [Link] the
length of short wall measured into in and may be found by deducting half
breadth from its centre line length at each end The length of long wall
usually decreases from earth work to brick work in super structure while the
short wall increases. These lengths are multiplied by breadth and depth to
get quantities.
Centreline method.
This method is suitable for walls of similar cross sections. Here the total
centre line length is multiplied by breadth and depth of respective item to
get the total quantity at a time.
When cross walls or partitions or verandah walls join with main wall, the
centre line length gets reduced by half of breadth for each junction.
Such junction or joints are studied carefully while calculating total centre
line length. The estimates prepared by this method are most accurate and
quick.
Estimation of Brickwork :-
We are going to discuss,
Cement mortar ratio should be 1:6 for 9” Brickwork and 1:4 41/2” brickwork
Mortar thickness should not be more than 10 mm between the courses and
sides of the bricks
So, first of all, we are going to find the volume of bricks with mortar
thickness and then volume of bricks alone.
Volume of 1 brick with mortar = 200 X 100 X 100 (10 mm mortar thickness
on all sides)
Therefore,
= 1 – 0.7695
We know the mortar ratio is 1:6 (1 part Cement & 6 Part Sand = 7 Part)
63 kg of cement
0.263 m3 of sand.
Estimation Of Brickwork , Cement And Sand :-
Here I have calculated the quantity of cement , brickwork and sand in My
project 2BHK Apartment
Total Volume
43.775m³
Spacing = 5”
Here I will calculate quantity of concrete required for the highlighted portion
(Bedroom) in m3 .
Demarcation:-
Demarcation means the action of fixing the boundary or limits of something
or a dividing line.A Demarcation is a line, boundary, or other conceptual
separation between things. DEMARC stands for
[Link] is defined as a limit or boundary, or the act of
establishing a limit or boundary. An example of a demarcation is a city limit
[Link] the objective of measurements is to show relative positions
of various objects on paper. Such representation on paper is called plan or
map. A plan may be defined as the graphical representation of the features
on, near or below the surface of the earth as projected on a horizontal
plane to a suitable scale. However, since the surface of the earth is curved
and that of the paper is plane, no part of the earth can be represented on
such maps without distortion. If the area to be represented is small,
the distortion is less and large scale can be used. Such representations are
called plans. If the area to be represented is large, small, scales are to be
used and distortion is large. Representations of larger areas are called
maps. Representation of a particular locality in a municipal area is a plan
while representation of a state/country is a map. There is no exact
demarcation between a plan and map.
However, since the surface of the earth is curved and that of the paper is
plane, no part of the earth can be represented on such maps without
distortion. If the area to be represented is small, the distortion is less and
large scale can be used. Such representations are called plans. If the area
to be represented is large, small, scales are to be used and distortion is
large. Representations of larger areas are called maps. Representation of a
particular locality in a municipal area is a plan while representation of a
state/country is a map. There is no exact demarcation between a plan and
map.
We also use Screen sand , Lime powder And Theodelite for Demarcation
In which depth of the footing from ground level was 3’6” and width of
the footing was 5’ And other necessary details of the isolated column
footing in the 2BHK flat and plan of the building are given on the next
page :-
Layout of the 2BHK Flat no. 911 A
Excavation
In construction terms, excavation is the process of removing earth to form a
cavity in the ground.
In the case of soft soils continuous or “close” planking is adopted and the
vertical boards are kept touching each other without any gap as shown .
o The extent of soil and rock strata is found by making trial pits in the
construction site. The excavation and depth is decided according to
the following guidelines in the site
i. For Isolated footing the depth to be one and half times the width of the
foundation
ii. For adjacent footings with clear spacing less than twice the width (i.e.)
one and half times the length
Dewatering of Excavation
Several operations have to be carried out within the excavation, like laying
bed concrete, laying of RCC raft slab and construction of masonry etc.
Therefore, work can be carried out more efficiently if the excavation area is
kept dry.
The masonry work over the bed concrete can be started after 3 days of
laying the concrete but curing along with that of masonry shall be
continued.
For RCC column footings and raft foundations, a levelling course of lean
concrete of 75 mm is laid in order to have an even and soil free surface for
placing the reinforcement.
Foundation
A foundation (or, more commonly, base) is the element of an architectural
structure which connects it to the ground, and transfers loads from the
structure to the ground. Foundations are generally considered either
shallow or [Link] is a structural part of a building on which a
building stands. Foundation transmits and distributes its own load and
imposed loads to the soil in such a way that the load-bearing capacity of
the foundationbed is not exceeded.
The solid ground on which the foundation rests is called foundation bed.
There are various types of foundation. They can be categorized into two
types.
Types of Foundation
Foundations are mainly two types.
1. Shallow Foundation,
2. Deep Foundation.
Shallow Foundation
A shallow foundation is a type of foundation that transfers loads to the very
near the surface. Shallow foundations typically have a depth to width ratio
of less than 1. The shallow foundation itself can be various types.
Isolated footing
These are most economical. They are usually in square or rectangle size
with the column sitting in the middle of the square. It’s a kind of pad footing.
IsolatedfootingCombined Footing
Combined Footing
Combined footings are provided when distance between two columns is
small and soil bearing capacity of soil is lower and their footings overlap
with each other. When two columns are close together and separate
isolated footings would overlap, in such case, it is better to provide a
combined footing than isolated footing.
Strap Footing
A strap footing is a component of a building's foundation. It is a type of
combined footing, consisting of two or more column footings connected by
a concrete beam. This type of beam is called a strap beam. A strap footing
is often used in conjunction with columns that are located along a building’s
property or lot line. Typically, columns are centered on column footings, but
in conditions where columns are located directly adjacent to the property
line, This results in an eccentric load on a portion of the footing, causing it
to tilt to one side. The strap beam restrains the tendency of the footing to
overturn by connecting it to nearby footings.
Raft Foundation
Raft Foundations, also called Mat Foundations, are most often used when
basements are to be constructed. In a raft, the entire basement floor slab
acts as the foundation; the weight of the building is spread evenly over the
entire footprint of the building. It is called a raft because the building is like
a vessel that 'floats' in a sea of soil. Mat Foundations are used where the
soil is week, and therefore building loads have to be spread over a large
area, or where columns are closely spaced, which means that if individual
footings were used, they would touch each other.
Wall Footings
Wall footings are used to distribute loads of structural load-bearing walls to
the soil.
Deep Foundations
Deep foundations are those founding too deeply below the finished ground
surface for their base bearing capacity to be affected by surface conditions,
this is usually at depths of 3 meter below finished ground-level. Deep
foundations can be used to transfer the load to a deeper, more competent
strata at depth if unsuitable soils are present near the surface.
Types
Pile Foundation
Pile foundation is a type of foundation where a slender member of wood or
concrete or steel is inserted into the ground for transferring the load of a
structure. The load is transferred to stronger stratum by friction or by
bearing.
Caisson Foundation
Caisson is a watertight structure made of wood, steel or reinforced
concrete which excavates for the foundation of bridges, piers etc.
Caisson Foundation Pile Foundation
Generally, in a building corner most columns are biaxial columns and side
column is uniaxial column and internal columns can be any of these.
1. Column layout work: In this stage of works the location of columns are
determined practically in field. It is done by laying rope according to grids
shown in the drawing and then mark the location of columns related to
rope.
Or
Check The Straightness of column with Plumb Bob:- This method you
can be adopted on the site to instantly find out the vertical alignment of any
type of column. For this firstly we have to place the plumb bob on any side
at the top of column, and observe the status of Bob, neither it should be
lying on the column nor it should be hanging like a pendulum, it should just
touch the column boundary. Repeat the same procedure on the adjacent
side of the column. Acc. To Bob we will know that whether the column is
aligned or not, if not then in which direction it is inclined.
Masonary
Brick Masonary :-
Brick masonry is built with bricks bonded together with mortar. For
temporary sheds mud mortar may be used but for all permanent
buildings lime or cement mortars are used.
Stretcher Bond :- A stretcher is the longer face of the brick as seen in the
elevation. In the brick of size 190 mm × 90 mm × 90 mm,(190 mm × 90
mm) face is the stretcher. In stretcher bond masonry all the bricks are
arranged in stretcher courses as. However care should be taken to break
vertical joints.
This type of construction is useful for the construction half brick thick
partition wall.
Header Bond :- A header is the shorter face of the brick as seen in the
elevation. In a standard brick it is 90 mm × 90 mm face. In header bond
brick masonry all the bricks are arranged in the header courses. This type
of bond is useful for the construction of one brick thick walls.
English bond Construction of flemish bond needs greater skill. It gives more
pleasing appearance. But it is not as strong as English bond. Flemish bond
may be used to get good aesthetic view. If plastering is going to be used, it
is better to use English bond.
At Site , for all the construction purposes there was use of English
bond
Brick Masonary In Footing :-
In the case of brick walls, the width of section is increased by 114 brick (5
cm) offset on either side. The base rests on a plain concrete footing which
projects 10 to 15 cm beyond the last brick offset
1. Use bricks of good quality with uniform colour, well burnt, with exact
shape and size.
2. Before using the bricks in masonry, they should be soaked in water for 2
hours so that bricks do not absorb water from the mortar.
3. Bricks should be laid with the frog pointing upward.
4. Construction of brick wall should start from the end or corner.
5. Brick courses should be perfectly horizontal.
6. Verticality of the wall should be ensured by frequently checking with
plumb-bob.
7. Mortar used should be as per specification.
8. Whenever work is stopped brick masonry should be left with toothed
end.
9. Use of brick bats should be avoided.
10. Walls should be raised uniformly. In no case difference between
adjoining walls be more
than 1 m. In a day no wall should be raised by more than 1.5 m.
11. To get proper key for plastering or pointing, the face joints should be
raised to a depth of 12 to 20 mm, when the mortar is green. If plastering or
pointing is not to be provided, face joints should be stuck flush and finished
neatly.
12. Holdfasts for doors and windows should be embedded in brick masonry
with cement mortar or concrete, at the time of constructing the wall itself.
13. Brick masonry should be regularly cured for 2 weeks.
14. For carrying out brick work at higher levels, only single scaffolding
should be used.
Beams
Beam is a 2d structural element of a frame structure or a beam
supportedstructure. The basic purpose of providing a beam is to transfer
the imposed load both dead and live to a wall or column whatever is
designed on the basis of structural requirement of a [Link] are
meant to resist bending or flexural stresses as a major one with shear
stresses as minor [Link] reason and/or purpose for providing a beam
in a building is to span a gap or to have some space or opening like that
of a door or awindow. Various types of beams are :-
Plinth Beams :-
Plinth level is basically the level of the ground floor top which is usually kept
higher than the ground level. The reason to make plinth level a bit higher
than the ground level is to prevent the rain or other runoff water from
coming inside the building and on the other hand provide sufficient
drainage to the surface water of the building. The Plinth Beam is the
beam at the plinth level.
Plinth beam in a frame structure is meant to join all the columns thereby
reducing the effective length and thus reducing the slenderness of the
columns.
Height :- A tie beam is usually recommended for a column when its height
is more than 4 to 5 meters. However, the designer must keep in check the
bending length of the column to make them non slender.
Lintel Beam :-
Lintel beam is a comparitively thin horizonal member which is provided
on the openings in walls like windows, doors etc so as to carry the load
of the wall above the opening and transfer it to the sides of the opening.
Sometimes a band lintel beam is also provided in some buildings if the
lintel level of all the building openings are uniform
3. Rigid Materials: Materials like first class bricks, stones, slate, cement
concrete etc.
For DPC above ground level with wall thickness generally not exceeding 40
cm, any one of the type of materials mentioned above may be used.
Cement concrete is however commonly adopted material for DPC at plinth
level, 38 to 50mm thick layer of cement concrete M15 ([Link] mix) serves
the purpose under normal conditions.
For greater wall thickness or where DPC is to be laid over large areas such
as floors, roofs, etc., the choice is limited to flexible materials which provide
lesser number of joints like mastic, asphalt, bitumen felts, plastic sheets
etc.
The felts when used should be properly bonded to the surface with bitumen
and laid with joints properly lapped and sealed.
In cavity wall construction, like cavity over the door or window should be
bridged by flexible material like bitumen felt, strips or lead etc.
Slab:-
A flat piece of concrete, put on the walls or columns of a structure. It serves
as a walking surface but may also serve as a load bearing member, as in
slab homes.
Functions of Concrete
Procedure
Reinforcement in slab
The slabs having ratio of longer length to its shorter length (Ly/Lx) greater
than 2 is called One way slab otherwise as Two way slabs. In one
way slab Main reinforcement is parallel to shorter direction and
the reinforcement parallel to longer direction is called Distribution steel.
Main Bar is provided at bottom and distribution bar above the main bar.
Main bar is provided to resist bending momemtsafely ,whilwdistribuition
bars are provided for resisting temperature variation, shrinkage and for
supporting the mesh
The maximum diameter of bar used in slab should not exceed 1/8 of the
totalthickness of slab. Maximum spacing of main bar is restricted to 3
times effective depth or 300 mm whichever is less. For distribution
bars themaximum spacing is specified as 5 times the effective depth or
450 mm whichever is less.
Concreting
Construction joint
The construction joint shall be pre decided and fixed prior to start of the
concreting. It is planned to have two construction joints for main building as
decided. In case of major break down of the Batching plant, the additional
Construction joint may be left. The location of the construction joint shall be
at the one-third span. Construction joint shall be straight and have profile of
‘L’shape so that successive layer of concrete shall be perfectly bonded with
previous laid layer
Concrete of grade M-25 shall be produced from our batching plant and
directly pumped to the location of concrete placement through the pipeline.
The pouring sequence shall be from grid A towards construction joint.
Proper walkways/platforms shall be arranged so that the supports of the
pipeline and manpower are not directly stand on reinforcement.
Curing
The curing shall be started immediately after thumb set of the concrete laid.
Hessian clothe /Plastic shall be covered over the set concrete to reduce
moisture evaporation from the concrete during hardening and thus to
minimize shrinkage crazy cracks. These cracks are inheriting property of
the concrete specially appears during casting of flat surfaces.
Final curing shall be done by ponding and stacking water for minimum
period of 7 days.
At our site
spacing
The slab which is provided below the normal floor level at a depth of
200mm to 300 mm and filled with broken pieces of bricks is called
sunken slab.
Duct
Duct
Sewer Works :-
Sewer Pipe :- A Sanitary sewer or foul sewer is an underground carriage
system specifically for transporting sewage from houses and commercial
buildings through pipes to treatment facilities or disposal.
Water Pipe :- A "water line" usually refers to a pipe supplying
pressurized water ready for use while a sewerline refers
a pipe carrying water with human waste at atmospheric pressure.
Roof drains and patio drains are not permitted to enter the sewer system
but must instead drain to the street and the storm drain system
Storm Pipe :- A storm drain, storm sewer surface water drain/ sewer or
storm water drain is designed to drain excess rain and ground water from
impervious surfaces such as paved streets, car parks, parking lots,
footpaths, sidewalks, and roofs.
2. Attach 1 end of the tubing to the flat side of a stake or dowel. Use
nails or tape to attach the tube to the stake, making sure the open
end of the tube is facing upward. Make sure there are no kinks or
knots in the tube so the water can flow easily through the tube.
3. Hold the other end of the tubing and fill it with [Link] the tube
until the water sits 2 to 3 inches (5.1 to 7.6 cm) below the attached
end of the tubeCheck that there are no air bubbles in the water once
you have filled the tube, as this can throw off the level.
4. Use your thumbs or a cap on the ends to prevent the water from
spilling.
5. Bring the water level to the items you want to [Link] can also
use the water level for construction projects where you need to find 2
level areas on different items that are close to one another.
7. Place the other end of the level against the other post. Keep your
thumb over the open end of the tube so no water splashes out. Then,
stand back and see where the water sits in either end of the tube.
Notice if the water appears higher or lower in 1 end. This means the
spots are not level and you need to adjust where the level sits on the
posts so the water levels match.
8. Slide the free end of the tube up or down until the level on both ends
[Link] to check the levels as you slide the free end of the
tube.
9. Mark the items at the level spot. Once the meniscus, or water line, is
level on both ends of the tube, use chalk or a pencil to mark the spot
on both posts or items
Bent Up Bars :-
It is actually economization of material. Normally, for fixed ended beams
positive (sagging) moments are present at the mid span and negative
(hogging) moments at the supports.
So bottom steel is required at the mid span and top steel resists negative
moments at the supports.A bent-up is provided to take the steel on the top
at supports as bottom steel is not normally required at at the supports
Bars are bent near the supports at an angle of 45°. The angle bent may
also be 30° in shallow beams where the (effective depth< 1.5 breadth).
Bent up bars
Overlapping in beams and columns:-
Development length and lap length are two important terms in
reinforcement.
During placing the steel in RC structure if the required length of a bar is not
sufficiently available to make a design length then lapping is done. Lapping
means overlapping of two bars side by side to achieve required design
length.
The vibrations cause the mixture to liquefy, reducing the internal friction of
the mix components of cement, aggregate, and water. This allows the mix
to move around more easily in whatever form you are placing the concrete.
This helps to ensure that enough concrete gets into every little nook and
cranny and eliminate voids. Furthermore, the vibrations and liquification
help to allow air bubbles to escape. There's a lot of air in the mix when
placed, and too much air in the mix allows for a less dense mixture and
therefore can lead to failures and blemishes. The vibrations help to bring
those air bubbles to the surface where they escape.
Lessons Learnt At Site
Flaws :-
Unskilled labour and masons :- usually the masons constructs the wall
without any level due to which the wall doesnot seems good and has less
strength and there were no proper bonds in wall masonary
Low quality roads :- low quality roads were constructed connecting all the
flats , which got damaged after two or three rains
Qualities :-
Punctuality :- all the labours ,site engineers ,masons were present at the
site about 9 am and work continued upto 5 pm and somedays there extra
hours too
Daily visit :- General manager, project manager and project head used to
visit daily and inspect the ongoing works that were on going on the site .
Qualified site engineers :- All the site engineers present at the site were
highly qualified and very hardworking and were present on the site whole of
the day
Proper Checking of Materials :- The material which is to be used for the
construction is first thoroughly checked by the site engineer then it is
passed for construction
Level check of column :- Every column which was cast was thoroughly
checked for straightness after the removal of formwork
Level check of slab :- The slab level is checked before and after the
reinforcement , and even during the reinforcement
2. There should not be any hard lumps on cement, the cement should
be finely powdered. If cement contains hard lumps, then it must be
rejected.
Coarse Aggregate
4. The Stone Chips should not contain organic and other impurities, as
only 5% clay content in concrete can reduce the strength of the
concrete as much as 20%.
Proctor’s Compaction Test ensures accuracy by standardizing the preparation and execution process. Soil is sieved, mixed, and moistened before placement into a mold, where compaction is achieved by prescribed blows per layer . This uniform procedure, combined with subsequent moisture content testing and plotting dry density curves, ensures reliable data on optimum compaction levels and helps assess compaction potential and water retention properties .
The bearing capacity of soil is determined both through field and laboratory tests. Field tests include the Standard Penetration Test, Dynamic Cone Penetration Test, and Plate Load Test, among others, which provide real-time data on soil resistance . Laboratory tests assess characteristics like shear strength and compressibility . This information is critical for designing foundations that can support structural loads without excessive settlement or failure .
Moisture content and dry density are critical for understanding soil's load-bearing and compaction characteristics. Moisture affects soil stability and consolidation, while dry density indicates soil's compactive efficiency and structural integrity . These parameters influence the design of footings and slabs as they affect soil's shrink-swell behavior and settlement, thus determining the adequacy and safety of foundation systems .
Key methods in soil investigation include test pits, probing, and boring. Test pits allow visual inspection and collection of soil samples . Probing gives an initial idea of underlying soil characteristics through physical penetration . Boring provides detailed information about the soil stratum, engineering properties, and groundwater location, crucial for assessing the site's load-bearing capacity . Each method helps evaluate the site's suitability by analyzing soil type and structure depth.
Overlapping in beams and columns, involving lapping bars side-by-side when required lengths aren't available, ensures continuous load paths. Properly calculated lap lengths (40d for beams, 24d for columns) prevent weak points by maintaining stress transfer capability . Avoiding overlaps at maximum stress locations like midspan enhances structural performance, reducing failure risks due to inadequate bonding .
The procedures for a simple field test to estimate soil bearing capacity involve excavating a pit and dropping a solid object from a known height to measure its impact on the soil. The depth of the impression gives insight into soil resistance using the formula R = (w * h) / d . The resistance per unit area is calculated as R / A and adjusted with a safety factor, F.O.S., to find the safe bearing capacity . This methodology helps in preliminary design by providing a basic estimate of soil capability .
Double Flemish bonds feature alternating headers and stretchers on both sides of a wall, offering aesthetic appeal but less strength than English bonds. Single Flemish bonds have this arrangement only on the exterior, making them structurally closer to English bonds yet retaining some aesthetic features. While double bonds may enhance appearance, single bonds balance aesthetics with better structural integrity, impacting the choice based on aesthetic priorities or structural demands .
Bent-up bars in beams address different strain conditions by being positioned to resist negative bending moments at supports effectively, where tension is reversed. This method economizes usage by reducing unnecessary reinforcement where it's least needed, fulfilling roles in shear reinforcement and minimizing brittle failure risks at critical points . Efficient use of material is achieved by focusing reinforcement where structural forces are highest, optimizing cost and performance .
Quality control measures for brick masonry include using uniform, well-burnt bricks, ensuring bricks are soaked to prevent mortar dehydration, and keeping courses horizontal. Other measures involve checking wall verticality, maintaining consistent joint finishes, appropriate use of mortar, embedding door/window fittings during construction, and ensuring staged wall progression and adequate curing . These steps ensure structural efficacy and durability.
Plinth beams distribute loads uniformly across columns, reducing effective length and slenderness, thus enhancing stability . By elevating the building base, plinth beams help prevent water ingress from rain or flooding, contributing to the structure's durability and ensuring effective drainage around the foundation .