G+4 Building Internship Report
G+4 Building Internship Report
INTRODUCTION
I was assigned as a field trainee at the site which had several ongoing
construction works. The buildings were RCC framed and earthquake resistant
structure. When I started my field training, at that time brickwork, internal &
external plastering, electrification, tiling and plumbing works are going on
simultaneously of the whole building. Lintels for doors and windows are also
being constructed using reinforcement like that of beams. On 1st June 2019, I
joined for field training. On the very 1st day, I was introduced with each and
every work that I am going to view in detail in the latter stage. After showing
the layout map and some of the architectural designs adapted in the site, I was
introduced with tiling, plumbing and electrification work, fitting of doors &
windows on the rooms in which up to the plastering work has seen already
completed. On the second half of the day, I was introduced about the casting
of lintels, their formwork, internal plastering very briefly. Concrete mixing is
being generally achieved by hand mixing i.e. Volume Batching.
In this period of field training, the site engineer Mr. Aniket Jadhav
gave lot of information about site. He gave us detailed information about
planning & construction of building.
Project details:
Type of the project: 4 X G+4 Residential Buildings (Mangalmurti Skyline)
Contractor: Mr. Manohar Jadhav
Architect: Mr. Suhas Jadhav
Type of contract: Civil, Electrical, Plumbing, and Firefighting
Estimated Cost: 8 Crores
Duration of Project: 36 months
Project commencement Year: March-2018
Area of site: 70000 sq. ft.
General Description
It is near to Sai Garden, Vidyanagar. Site is situated in nature’s beauty
i.e. it has fresh air and is pollution free the project has various units concerns
to different department with separate entrances to maintain privacy. All the
units are intelligently conceived to maximize natural ventilation & sunlight.
Training Site Details: Behind Sai Garden, Vidyanagar.
Training In-charge/Site Engineer: Mr. Aniket Jadhav.
Merits
Delay can be avoided.
There is unity of control and authority.
Easy to understand and strong in discipline.
Labor Rates:
Being a field trainee on the site, I got a very fine opportunity to witness
a lot of work mostly related with building services. However, as the structural
work was completely over when I visited the site, I only witnessed the
structural work of lintels and chajjas. So, in this chapter I would like to give
the details of my everyday observations on the site during my training.
Mixing and Pouring of Concrete: The mixing for such purposes was
generally being achieved as volume batching. Since, the grade of concrete
for lintel casting is M15 & the proportion is 1:2:4. The labors took a bag of
50 kg (considered as 35 liters) cement bag and added fine sand and coarse
aggregates in the requisite proportion using the gauge boxes of (27 cm X
27 cm X 48 cm). Then finally 30 liters of water is being added for this
whole mix. Then a mason mixes the components thoroughly for about 10
minutes. Then they pour a layer of mix into the formwork above the door
opening & compacted it. After this, they pour & compact it in 4 layers.
The whole process from centering to compacting took almost 1½ hours,
for just a single lintel.
In this way, they have done it for 1 more door and 3 windows. However, in
case of windows the bearing ends width was made at 20 cm as the width of
opening for window is 2 m and the depth was made same.
Then he mentioned the factors for selection of size, shape, location and
number of doors and windows in a room which were as follows:
1) Size of the room
2) Location of the room
3) Utility of the room
4) Direction of the wall
5) Direction of wind
6) Climatic conditions
Since the wooden frames for doors were already fitted, so they just
need to fit the doors at the required places by combining the panel with frame
using the butt hinge. The doors were already provided with the lever handle
lock for the main external door and for the internal doors handles were
provided along with the aldrop bolt. The same procedure is being performed
for the fitting of casement windows for the kitchen, which was already being
provided with the barrel bolt.
On that very day complete fitting of doors and windows for 6 flats
were being achieved.
Now, the frame for doors and a kitchen window was getting placed in the
following steps:
1) The prepared opening in which frame is to be fixed was cleared and exact
position of the frame was marked by drawing chalk lines along the
verticals and head and sill of the respective frame.
In the whole day there is only the application of single coat of plaster
of 2 rooms in a single flat and only fitting of frames of all rooms in a single
flat.
For addition of safety features, they were blocking all the entrances of
the lift shafts from different floors using the waste wooden planks that had
already been utilized in the formwork purpose.
Now, for getting a rough idea the masons were striking the concrete of
lintels which were cast earlier with a light hammer. Much of them were giving
a metallic sound which means the concrete has hardened sufficiently and the
formwork can be safely removed. The concrete lintels which were not giving
the usual sound were left as to harden properly. First they remove the props
which were put under the lintels so as to support the lintels were removed. So,
they were removing the formwork gradually so as to prevent sudden
imposition of loads on the structure. After the complete removal of the
formwork from over the lintels, they placed the gunny bag over the lintels so
as for the purpose of clearing and also to prevent shrinkage of concrete.
At first channels were made using the wall chaser with depth of almost
40 mm and width of 44 mm at different places considering the diameter of
water main pipe of 35 mm and conduits for electric wiring of diameter 20 mm.
Also cuts were made at required places for the purpose of various switch
boards as well as distribution boxes. For the sewage purpose proper cuts were
made at the slab considering the thickness of the slab as well as the diameter
of the pipe. For plumbing purposes cuts are made to install the regulators at
the required places. For the electric switch board boxes, somewhat extra
depths are made to install the metallic switch boxes in the cut.
Now, in lieu of conduits for the purpose of laying electric wires, PVC
channeling is used. Now the cables were made to run through the pipes and on
the next part large head nails are used to fix the pipes in the chase. For
plumbing purposes, the pipes are simply placed leaving the opening for the
required purpose at the proper places.
In both the days, the same cycle is being repeated and the plumbing
works as well as the electrification works for 2 flats were completed.
However, there was no setting up of electric switches, switch boxes as well as
other water and sanitary appliances had been achieved.
Thus, I observed only the preparation of the wall surface for any of the
above process of already plastered flat which consists of the following steps:
1) At first, the plastered walls were cleaned with a piece of cloth to remove
the dirt or other impurities.
2) Then the walls were rubbed as well as scraped to remove any form of
irregularities present.
3) Wherever minute cracks were present, mortar mixture were introduced to
fill the cracks.
4) The efflorescence patches were carefully cleaned out.
Within the whole day, only a single flat was able to be completed by
the workforce. Since the most complicated part of the application was the
ceiling as well as the corners of the room.
The same procedure is applied for the tiling of the walls. Only a single
whole flat was completed in the whole not considering its wall tiling for
the kitchen and the bathroom.
First the MCB and the distribution boxes were installed, in which there
are 4 units i.e. 2 were for the purpose of the switch boards in the rooms of
ratings 800W while 2 were for control of Refrigerators, Air Conditioners,
Geysers etc. Then the wires of respective colors and of required lengths were
introduced into the PVC pipes after considering the connections for switch
boards, socket outlets for the required capacities, ceiling roses, lamp or
fluorescent tube holder etc. with minimum size of wiring as 1.5 sq. mm as per
General Specifications of Electrical Work (Internal) by Central Public Works
Department (2013) for the purpose of conceal piping. Metal conduits were
also placed at the points of the switch boxes for the purpose of earthing. The
PVC pipes carrying wires were placed into the channels which were carved
into the walls.
The height of the different sockets as well as the switch boards were
completely maintained as per the standard guidelines given by the CPWD. At
that day only the wires of required length from the main distribution box
through the various switch boards to the respective points were completed for
a particular flat.
Then next I observed the conceal piping for which the Site Engineer
introduced me with the generalized size that is being adapted for the
residential plumbing is 1 inch pipe for that of the main supply line to each
building and the service piping for each flat is ½ inch. He also added further
for the purpose of 24 hours water supply they were going to construct a water
tank in the terrace of each of the building which would be supplied water
using the pumps installed in the ground floor of the building to maintain the
required pressure for the uplift. Now for the purpose of the sewage water they
were again installing the PVC pipes but of greater diameter i.e. 75 mm pipes
for that of the individual supply from each particular flat which was supplied
by the sewage pipes of the sink of 40 mm, basin of 32 mm, shower tray of 30
mm and water closet of 40 mm. The sewage pipes for that of the whole
building was of 100 mm. The sewage pipes were connected to the walls using
hooks. After the installation of the water pipes in the channels, the channels
were filled completely with the mortar mix.
For wash basins, pillar taps were utilized and for water closet as well
as the sink bib tabs were placed of standard available size. In bathroom also a
set of mix taps were provided if anyone had to use the warm water from the
geyser. For the wash basin full pedestal basins were used, for the kitchen half
pedestal basins were used and for the bathroom counter basins were utilized.
The water closet that is provided is of Orissa pattern Squatting Pan. There was
no provision of the flushing cistern as it is mentioned that it solely depends on
the occupants if they required it or not.
So, in the whole day only fixtures of various water supply and sanitary
appliances were completed for a particular flat.
5 chajjas were casted for a particular flat at different location of the flat
i.e., bathroom ventilation, windows.
Signage: - Important signs that could remind people who are moving within
the working location should be situated in a place where everybody can see or
look.
Accident Administration
After involving the above stated methods of prevention of accident, there
could arise different disastrous calamities within the project, which necessitate
the application of most serious and acute acting administration.
Dr. B.C. Punmia, Er. Ashok Kumar Jain, Dr. Arun K. Jain, “R.C.C. Designs
(Reinforced Concrete Structures)”, Tenth Edition, 2006.