O - Labour Rates
JADUAL KADAR HARGA UPAH BURUH
2002
0.00
O001
Labourer (Unskilled)
Day
45.00
05/07/2005
O001A
Semi-skilled labour
Day
70.00
26/04/2011
O001B
Skilled labour
Day
100.00
26/04/2011
O002
Drainlayer
Day
60.00
05/07/2005
O003
Concrete Leveller and Screeder
Day
65.00
05/07/2005
O004
Mason
Day
65.00
05/07/2005
O005
Bricklayer
Day
65.00
05/07/2005
O006
Carpenter and Joiner
Day
65.00
05/07/2005
O007
Steel Barbender and Fixer
Day
65.00
05/07/2005
O008
Pneumatic Tool Operator
Day
65.00
05/07/2005
O009
Fitter
Day
70.00
05/07/2005
O010
Welder
Day
70.00
05/07/2005
O011
Plumber
Day
65.00
05/07/2005
O012
Painter
Day
60.00
05/07/2005
O013
Roofer
Day
65.00
05/07/2005
O014
Glazier
Day
65.00
05/07/2005
O015
Ironworker
Day
70.00
05/07/2005
O016
Pavior/Plasterer
Day
65.00
05/07/2005
O017
Tile Fixer
Day
70.00
05/07/2005
O018
Watchman
Day
50.00
05/07/2005
O019
Labour (Skilled)
Day
65.00
05/07/2005
O020
Pipelayer
Day
60.00
05/07/2005
O021
Fence Fixer
Day
60.00
05/07/2005
O022
Labour to erect formwork
m2
22.00
26/04/2011
O023
Labour to cut, bend & fix steel bar
tonne
550.00
26/04/2011
O024
Labour to cast concrete
m3
35.00
26/04/2011
O025
Labour to lay bricks; 115 mm thick
m2
8.50
26/04/2011
O026
Labour to install lintol 100m x 100mm
9.00
26/04/2011
O027
Labour to lay damp proof course, 230mm wide
0.30
26/04/2011
O028
Labour to lay cement & sand acreed to floor;
25mm thick, steel trowel
Labour to plaster wall; cement & sand; 28mm
thick; 3 coats; external
m2
5.50
26/04/2011
m2
12.50
26/04/2011
O029
CHEW FU KEONG
Page :
of
15
Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
Price List
Ref Code
Trade Heading:
Name : PCK1
Item Description
Unit
Rate
O - Labour Rates
Mark
Supp
Last
Up %
Code
Updated
(Continued)
m2
8.50
26/04/2011
O031
Labour to plaster wall; cement & sand; 28mm
thick; 3 coats; internall
Labour to lay tiles; homogeneous
m2
16.00
26/04/2011
O032
Labour to fix corner beading
2.30
26/04/2011
O033
no
36.00
26/04/2011
no
39.00
26/04/2011
O035
Labour to install timber door frame for single
leaf door including sub-frame
Labour to install timber door frame for double
leaf door including sub-frame
Labour to install timber door; single leaf
no
50.00
26/04/2011
O036
Labour to install timber door; double leaves
no
70.00
26/04/2011
O030
O034
Skilled And General Workers
O037
Concretor
day
50.00
18/12/2008
O038
Concretor 'Kepala'
day
62.00
18/12/2008
O039
Steel bar bender & fixer
day
53.00
18/12/2008
O040
Bar bedber 'Kepala'
day
66.00
18/12/2008
O041
Formwork carpenter
day
54.00
18/12/2008
O042
Formwork carpenter 'Kepala'
day
68.00
18/12/2008
O043
Bricklayer
day
52.00
18/12/2008
O044
Bricklayer 'Kepala'
day
65.00
18/12/2008
O045
Blocklayer
day
57.00
18/12/2008
O046
Blocklayer 'Kepala'
day
71.00
18/12/2008
O047
Roofer
day
55.00
18/12/2008
O048
Roofer 'Kepala'
day
71.00
18/12/2008
O049
Joinery carpenter
day
57.00
18/12/2008
O050
Joinery carpenter 'Kepala'
day
82.00
18/12/2008
O051
Structural steel worker
day
65.00
18/12/2008
O052
Structural steel worker 'Kepala'
day
94.00
18/12/2008
O053
Welder
day
71.00
18/12/2008
O054
Welder 'Kepala'
day
101.00
18/12/2008
O055
Plumber
day
61.00
18/12/2008
O056
Plumber 'Kepala'
day
83.00
18/12/2008
O057
Plasterer
day
57.00
18/12/2008
O058
Plasterer 'Kepala'
day
75.00
18/12/2008
O059
Tiler
day
61.00
18/12/2008
O060
Tiler 'Kepala'
day
85.00
18/12/2008
O061
Painter
day
55.00
18/12/2008
CHEW FU KEONG
Page :
of
15
Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
Price List
Ref Code
Trade Heading:
Name : PCK1
Item Description
Unit
Rate
O - Labour Rates
Mark
Supp
Last
Up %
Code
Updated
(Continued)
O062
Painter 'Kepala'
day
70.00
18/12/2008
O063
General worker (Male)
day
40.00
18/12/2008
O064
General worker (Female)
day
35.00
18/12/2008
Piling
OO01
Sheet pile
OO01A
Handle, pitch and drive
O065
FSP 3A, 12m lenght
pcs
80.00
16/12/2008
O066
FSP 3A, 9m lenght
pcs
70.00
05/11/2008
OO02
Extracting
O067
FSP 3A, 12m lenght
pcs
70.00
05/11/2008
O068
FSP 3A, 9m lenght
pcs
60.00
05/11/2008
OO03
600mm diameter pretensioned spun concrete
pile
Allow for the provision of all necessary injection
piling equipment, plant, tools and ancillary
equipment (for the execution of all piling work
in this contract) and for their transportation to
site handling, assembling, erecting, dismantling
and removal on completion of the work for any
idle standing time
Allow for moving and handling piling
equiment, plant, tools, and ancillary equipment
about the site as often and whenever necessary
for the execution of the whole piling operation
(as covered under this contract) including any
excavation and filling required for moving the
plant, tools and ancillary equipment from
differing places and levels of the site, erection
of any staging required and dismantling and
removal on completion.
Handle, transport and pitch 600mm Diameter
spun pile; 12.00m long
Drive only by injection method 600mm
Diameter spun pile; 12.00m long (In No. 766)
12.70mm (overall) Butt weld connection
1884mm girth between edges of mild steel
extension head and base cap plates including
coated heavily with bituminous compound.
Cut off 600mm diameter pre-tensionedspun
concrete pile to be required level and roughen
the inner surface to detail.
Allow for Pile Dynamic Analysis (PDA) test and
submission of analysis.
500mm diameter prestressed spun concrete
pile
Item
42,250.00
04/03/2009
Item
9,833.33
04/03/2009
No
44.00
04/03/2009
45.67
04/03/2009
No
58.00
04/03/2009
No
59.25
04/03/2009
No
1,700.00
04/03/2009
O069
O070
O071
O072
O073
O074
O075
OO04
CHEW FU KEONG
Page :
of
15
Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
Price List
Ref Code
Trade Heading:
Name : PCK1
Item Description
Unit
Rate
O - Labour Rates
Mark
Supp
Last
Up %
Code
Updated
(Continued)
Item
O079
Allow for mobilisation of labour, plants and
hydraulic hammer piling equipment to site,
moving around and demobilisation from site
Handle, sling and pitch initial and extension
vertical piles not exceeding 12m long
Handle, sling and pitch initial and extension
raked 1:4 piles not exceeding 12m long
Drive vertical pile to the required depth
O080
18,000.00
16/12/2008
no
64.00
16/12/2008
no
80.00
16/12/2008
45.00
16/12/2008
Drive raked 1:4 piles to the required depth
60.00
16/12/2008
O081
Fillet weld vertical extension pile joints
no
97.50
16/12/2008
O082
Cut off piles to the required level and roughen
inner surface of pile
Provide labours, plants, temporary staging,
kentledge, testing equipment and load 500mm
diameter test pile to 1200KN
Subsequent load test
no
120.00
16/12/2008
no
15,000.00
10/12/2008
no
10,000.00
10/12/2008
Item
14,666.67
23/12/2008
no
33.20
23/12/2008
13.93
23/12/2008
no
36.00
23/12/2008
Cut off pile head, strip concrete and exposed
reinforcement to a length of 600mm including
bending and binding exposed reinforced rods to
the reinforcement in the pile cap
Supply and fix 'concrete plug'
no
39.00
23/12/2008
no
70.00
23/12/2008
Provide all equipments, hydraulic jack,
deflection gauge, kentledge and other related
items for initial load testing to a vertical load of
130 ton or 1300KN
Subsequent load test
no
13,333.33
23/12/2008
no
6,933.33
23/12/2008
40,000.00
23/12/2008
40.00
23/12/2008
no
27.67
23/12/2008
no
37.50
23/12/2008
no
14,500.00
23/12/2008
O076
O077
O078
O083
O084
OO05
O085
O086
O087
O088
O089
O090
O091
O092
OO06
O093
O094
O095
O096
O097
CHEW FU KEONG
350mm diameter prestressed spun concrete
pile
Allow for mobilisation of labour, plants and
hydraulic hammer piling equipment to site,
moving around and demobilisation from site
Handle, transport and pitch initial and extension
pile not exceeding 12m long
Drive initial and extension pile to the required
depth
Fillet weld pile joint
300mm diameter prestressed spun concrete
pile
Allow for mobilisation of labour, plants and
jacked -in piling equipment to site, moving
around and demobilisation from site
Handle, transport, pitch and drive initial and
extension pile to the required depth
Fillet weld pile joint
Item
Cut off and remove surplus length and strip off
pile head, bend back reinforcement for
connection
Initial pile test to 1100KN
Page :
of
15
Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
Price List
Ref Code
Trade Heading:
Name : PCK1
Item Description
Unit
Rate
O - Labour Rates
Mark
Supp
Last
Up %
Code
Updated
(Continued)
O098
Subsequent load test
no
7,166.67
23/12/2008
O099
PDA test
no
1,450.00
23/12/2008
OO07
350 x 350mm R.C Pile
O100
Allow for the provision of necessary hydraulic
hammer piling equipment, plant and tools and
for their transportation to the site, handling,
assembling and removal after the completion of
operation
Allow for moving and handling piling
equipment about the site
Allow for submission of records of all piles
Item
15,000.00
19/02/2009
Item
3,000.00
19/02/2009
Item
3,700.00
19/02/2009
Allow for the provision of necessary testing
equipment, plant and tools and for their
transportation to the site, handling, assembling
and removal after completion including all
idling and standing time
Handle, transport, pitch and drive initial and
extension pile to the required depth
Fillet weld pile joint
Item
4,750.00
19/02/2009
16.50
19/02/2009
no
34.00
19/02/2009
no
35.80
19/02/2009
O107
Cut off pile head to required level, strip off
concrete to expose reinforcement, bend the pile
reinforcement excess length to dispose to
Contractor's own dump site
Initial pile test to twice working load of 1500KN
no
29,030.00
19/02/2009
O108
Subsequent load test
no
18,720.00
19/02/2009
O109
PDA test including preparation of pile head,
submission of test report
300 x 300mm R.C Pile
no
960.00
19/02/2009
Item
13,666.67
16/12/2008
Item
4,000.00
16/12/2008
O112
Mobilisation & Demobilisation of hydraulic
hammer piling frame and equipment
Moving and handling piling equipment, plant
and tools about the site
As built survey
Item
4,000.00
16/12/2008
O113
Submission of piling record
Item
1,500.00
16/12/2008
O114
no
43.00
16/12/2008
O115
Handle, transport and pitch only, 12m long
initial/extension pile
Drive only initial/extension pile
14.50
16/12/2008
O116
Filler weld pile joint
no
30.00
16/12/2008
O117
no
35.00
16/12/2008
O118
Cut off pile head and cart away surplus length
from site
Preliminary load test 2 x 1000KN
no
14,166.67
16/12/2008
O119
PDA test
no
1,333.33
16/12/2008
OO09
250 250mm R.C Pile
O101
O102
O103
O104
O105
O106
OO08
O110
O111
CHEW FU KEONG
Page :
of
15
Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
Price List
Ref Code
Trade Heading:
Name : PCK1
Item Description
Unit
Rate
O - Labour Rates
Mark
Supp
Last
Up %
Code
Updated
(Continued)
Allow for moving and handling jacked-in piling
equipment, plants, tools at the site as often and
whenever necessary for the operation of the
whole piling operation including for moving the
plants, tools and ancillary equipment from
different levels of the site and all necessary
staging, platform and any idling standing time.
Handle, transport, pitch and drive initial and
extension pile to the required depth
Fillet weld pile joint
no
42,500.00
23/12/2008
29.50
23/12/2008
no
22.75
23/12/2008
no
29.50
23/12/2008
O124
Cut off and remove surplus length and strip off
pile head, bend back reinforcement for
connection
Initial load test to 660KN
no
10,350.00
23/12/2008
O125
Subsequent load test
no
8,750.00
23/12/2008
O126
PDA test
no
1,187.50
23/12/2008
OO10
200 x 200mm R.C pile
O127
no
9.00
16/12/2008
O128
Handle, transport and pitch, 6m long
initial/extension pile
Drive initial/extension pile to the required depth
4.50
16/12/2008
O129
Fillet weld pile joint
no
8.00
16/12/2008
O130
Cut off pile head and cart away surplus length
from site
150 x 150mm R.C pile
no
Allow for the provision of necessary hydraulic
hammer piling equipment, plant and tools and
for their transportation to the site, handling,
assembling and removal after the completion of
operation
Allow for moving and handling piling
equipment about the site
Allow for submission of records of all piles
Item
4,500.00
19/02/2009
Item
1,000.00
02/01/2009
Item
2,000.00
02/01/2009
Allow for the provision of necessary testing
equipment, plant and tools and for their
transportation to the site, handling, assembling
and removal after completion including all
idling and standing time
Handle, transport, pitch and drive initial and
extension pile to the required depth
Fillet weld pile joint
Item
10,000.00
02/01/2009
4.38
19/02/2009
no
8.83
19/02/2009
Cut off pile head to required level, strip off
concrete to expose reinforcement, bend the pile
reinforcement, excess length to dispose to
Contractor own dump site
Subsequent load test to twice working load of
400KN
no
16.83
19/02/2009
no
5,250.00
19/02/2009
O120
O121
O122
O123
OO11
O131
O132
O133
O134
O135
O136
O137
O138
CHEW FU KEONG
Page :
of
15
Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
Price List
Ref Code
Trade Heading:
O139
Name : PCK1
Item Description
Unit
Rate
O - Labour Rates
Mark
Supp
Last
Up %
Code
Updated
(Continued)
PDA test including preparation of pile head,
submission of test report
no
958.33
19/02/2009
Concretor
O140
Concretor
m3
16.00
13/02/2009
O141
Lean Concrete
m3
16.00
26/02/2009
OO12
O144
Lean concrete, 50mm thick including
necessary trimming base of excavation
To underside of pile cap, footing, ground beam,
apron slab, ground floor slab, trench beam,
trench slab, pit slab and the like
Reinforced concrete including vibrating and
trowelling to a smooth and uniform level in
Pile cap, footing, column stump, ground beam,
trench beam and lift pit
Column
O145
03/12/2008
m2
1.50
17/02/2009
m3
19.00
03/12/2008
m3
20.00
03/12/2008
Stiffener and lintol
m3
21.00
03/12/2008
O146
Roof beam
m3
20.00
03/12/2008
O147
150mm thick ground floor slab and apron slab
m3
19.00
03/12/2008
O148
m3
19.00
03/12/2008
O149
150mm thick suspended floor slab and
suspended floor beam
150mm thick roof slab
m3
19.00
03/12/2008
O150
200mm thick wall
m3
20.00
03/12/2008
330.00
13/02/2009
O142
OO13
O143
Bar Bender
O151
Bar-Bender
tonne
O152
Fabric BRC
m2
1.35
24/10/2008
OO14
O153
Rods, 12mm, 16mm, 20mm, 25mm, 32mm and
40mm diameter
In foundation
kg
0.33
03/12/2008
O154
In column
kg
0.33
03/12/2008
O155
In beam
kg
0.33
03/12/2008
O156
In wall
kg
0.33
03/12/2008
OO15
Strirrups and Links
O157
6mm, 10mm and 12mm diameter
kg
0.33
03/12/2008
OO16
BRC Fabric
O158
In ground floor slab, apron slab, trench slab,
suspended floor slab and roof slab
m2
1.30
03/12/2008
m2
13.00
13/02/2009
Formwork
O158A
CHEW FU KEONG
Formwork
Page :
of
15
Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
Price List
Ref Code
Trade Heading:
OO17
Name : PCK1
Item Description
Unit
Rate
O - Labour Rates
Mark
Supp
Last
Up %
Code
Updated
(Continued)
Timber formwork fabrication, fixing and
striking not exceeding 3.50m high
To sides of pile cap, footing, column stump,
ground beam, trench beam and lift pit
To sides of column and stiffener
m2
13.00
03/12/2008
m2
13.00
03/12/2008
m2
13.00
03/12/2008
O162
To sides and soffits of suspended floor beam and
roof beam
To sides and soffits of suspended floor slab
m2
13.00
03/12/2008
O163
To sloping soffit of staircase
m2
13.00
03/12/2008
m2
3.43
26/02/2009
m2
5.00
26/02/2009
m2
3.80
26/02/2009
O159
O160
O161
Precast prestressed hollow core slab, plank
and precast beam
Installation & Grouting Works
O166
Installation (Labour Only NOT inclusive
cranage)
Hollow core slabs & planks in thickness 300mm
& below
Hollow core slabs & planks in thickness 300mm
& above
Hollow core slabs & planks in thickness 325mm
O167
Hollow core slabs & planks in thickness 360mm
m2
4.60
26/02/2009
O168
Precast beams, L < 10m
no
103.13
26/02/2009
O169
Precast beams, 10m < L < 15m
no
178.00
26/02/2009
O170
Precast column, 1 tier in one length
no
152.50
26/02/2009
O171
Precast column, 2 tiers in one length
no
200.00
26/02/2009
O172
Precast staircase flight
no
108.80
26/02/2009
O173
Precast landing slab
no
132.00
17/02/2009
O174
Precast wall, 2400 x 1800 x 150mm thick
no
100.00
31/12/2008
O175
Precast wall, 2250 x 1800 x 150mm thick
no
132.00
26/02/2009
OO19
Grouting Works to Precast System (Labour &
Materials)
Grouting to beam dowels connection
no
52.56
26/02/2009
no
104.99
26/02/2009
no
102.74
26/02/2009
O179
Grouting to beam & column gap including
formwork
Grouting to BSF connection gap including
formwork
Grouting to HCS/Plank shearkey joint
(E.mix) to
AV5 - 265
9.13
26/02/2009
O180
EV4-325
14.30
26/02/2009
O181
EV4-460
19.60
26/02/2009
O182
Plank 110
5.90
17/02/2009
OO18
O164
O165
O176
O177
O178
OO20
CHEW FU KEONG
Page :
of
15
Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
Price List
Ref Code
Trade Heading:
Name : PCK1
Item Description
Unit
Rate
O - Labour Rates
Mark
Supp
Last
Up %
Code
Updated
(Continued)
O183
WV6 - 205
5.00
31/12/2008
OO21
O184
Grouting to column base, 50mm in gap in
between; column to pile cap & column to
column
500 x 500mm
no
97.90
26/02/2009
O185
450 x 600mm
no
100.10
17/02/2009
O186
300 x 700mm
no
68.33
26/02/2009
O187
300 x 300mm
no
82.50
17/02/2009
OO22
Grouting to column corrugated connection
O188
4 dowels (300 x 300)
no
138.60
17/02/2009
O189
6 dowels
no
156.25
26/02/2009
O190
8 dowels (500 x 500)
no
278.30
26/02/2009
OO23
O191
Grouting to column corrugated connection at
beam top rebar
2 tiers
no
55.00
17/02/2009
O192
Grouting to staircase flight
no
121.00
17/02/2009
O193
Grouting to landing slab
no
121.00
17/02/2009
O194
Grouting to wall
no
69.75
26/02/2009
OO24
Associated Works On Site
O195
Concrete G30 to topping, 75mm thick
m3
310.00
17/02/2009
O196
Concrete G40 to beam infill & beam top
m3
340.00
31/12/2008
O197
Concrete G40 to beam-column junction
m3
340.00
31/12/2008
O198
Rebar to beam top, span & support
kg
3.25
17/02/2009
O199
Rebar to topping, EB/PB
kg
3.25
17/02/2009
O200
RD6 mesh to topping, 4.44kg/m2, measure nett,
allow lap in rate
Formwork to underside of hcs at perimeter beam
end
Formwork to edge of topping
m2
13.00
17/02/2009
18.00
31/12/2008
18.00
31/12/2008
O201
O202
Bricklayer
O203
Bricklayer
pcs
0.15
24/10/2008
O204
Hoisting brick
pcs
0.02
15/11/2008
OO25
Lay cement and sand brick
O205
110mm thick wall
m2
8.05
03/12/2008
OO26
Lay clay brick
O206
115mm thick wall
m2
8.05
03/12/2008
OO27
Lay hollow concrete block
CHEW FU KEONG
Page :
of
15
Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
Price List
Ref Code
Trade Heading:
O207
Name : PCK1
Item Description
Unit
Rate
O - Labour Rates
Mark
Supp
Last
Up %
Code
Updated
(Continued)
200mm thick wall
m2
8.50
13/01/2009
Plasterer
O208
External
m2
7.53
13/02/2009
O209
Internal
m2
6.99
13/02/2009
OO28
Plaster including mortar mixer, wheel barrow
and trowelling tools and erection of working
platform to a working height of not more than
3.0m high
19mm thick with wood float or sponge finish
in two (2) coats
Brickwall and concrete surface; externally
m2
8.00
04/12/2008
19mm thick with steel trowelled finish in two
(2) coats
Brickwall and concrete surface; internally
m2
7.00
04/12/2008
OO29
O210
OO30
O211
Door
O212
Lintol Small
no
5.00
27/11/2008
O213
Lintol Big
no
15.00
27/11/2008
O214
Lintol Arch
no
100.00
27/11/2008
OO31
Timber/Metal Frame
O215
Door Frame, SL
no
10.00
24/10/2008
O216
Door Frame, DL
no
15.00
24/10/2008
OO32
Timber window frame fixing
O217
Overall size 300mm x 300mm high
no
10.00
04/12/2008
O218
Overall size 1200mm x 1200mm high
no
13.00
04/12/2008
OO33
Timber door frame fixing
O219
Overall size 900mm x 2100mm high
no
13.00
04/12/2008
O220
Overall size 1800mm x 2100mm high
no
19.00
04/12/2008
OO34
Metal door frame fixing
O221
Overall size 900mm x 2100mm high
no
13.00
04/12/2008
O222
Overall size 1800mm x 2100mm high
no
19.00
04/12/2008
OO35
Timber Leaf Including Ironmongery
O223
Door Leaf including ironmongery, SL
no
15.00
24/10/2008
O224
Door Leaf including ironmongery, DL
no
30.00
24/10/2008
OO36
Fire Leaf Including Ironmongery
O225
Door Leaf including ironmongery, SL
no
40.00
24/10/2008
O226
Door Leaf including ironmongery, DL
no
80.00
24/10/2008
CHEW FU KEONG
Page :
10
of
15
Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
Price List
Ref Code
Trade Heading:
Name : PCK1
Item Description
Unit
Rate
O - Labour Rates
Mark
Supp
Last
Up %
Code
Updated
(Continued)
OO37
Partition Leaf Including Ironmongery
O227
Door Leaf including ironmongery, SL
no
10.00
24/10/2008
O228
Door Leaf including ironmongery, DL
no
20.00
24/10/2008
OO38
PVC Leaf
O229
Door Leaf, SL
no
7.00
27/11/2008
OO39
no
17.00
04/12/2008
pair
28.00
04/12/2008
no
30.00
04/12/2008
pair
54.00
04/12/2008
no
42.00
04/12/2008
pair
74.00
04/12/2008
OO42
Timber hollow core door fixing with hinges
and normal/standard lockset
Standard hollow core flush door faced both sides
with plywood; overall size 900mm x 2100mm
high x 40mm thick
Standard double leaf hollow core flush door
faced both sides with plywood; overall size
1800mm x 2100mm high x 40mm thick
Timber solid core door fixing with hinges and
normal/standard lockset
Standard solid core flush door faced both sides
with plywood; overall size 900mm x 2100mm
high x 42mm thick
Standard double leaf solid core flush door faced
both sides with plywood; overall size 1800mm x
2100mm high x 42mm thick
Timber fire door fixing with hinges and
normal/standard lockset
Standard one (1) hour fire-rated door; overall
size 1070mm x 2100mm high x 50mm thick
Standard double leaf one (1) hour fire-rated
door; overall size 1800mm x 2100mm high x
50mm thick
Ironmongery fixing
O236
Door closer
no
9.00
04/12/2008
O237
Lockset
no
5.00
18/02/2009
O230
O231
OO40
O232
O233
OO41
O234
O235
Pavior
OO43
Mason
O238
Rendering, 25mm thick
m2
5.38
13/02/2009
O239
Rendering, 50mm thick
m2
5.92
13/02/2009
OO44
To floor
O240
25mm thick cement and sand render with steel
trowelled finish to a smooth and level surface
20mm thick cement and sand base screed with
steel trowelled finish to a smooth and level
surface to receive finishing
m2
5.40
04/12/2008
m2
5.40
04/12/2008
O241
Tiling
CHEW FU KEONG
Page :
11
of
15
Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
Price List
Ref Code
Trade Heading:
Name : PCK1
Item Description
Unit
Rate
O - Labour Rates
Mark
Supp
Last
Up %
Code
Updated
(Continued)
OO46
Wall tile including preparation and laying of
cement and sand backing screed
To wall
O242
200mm x 200mm ceramic tile
m2
17.00
04/12/2008
O243
450mm x 450mm granite slab
m2
54.00
04/12/2008
O244
450mm x 450mm marble slab
m2
43.00
04/12/2008
OO47
OO48
Floor tile including preparation and laying of
cement and sand backing screed
To floor
O245
300mm x 300mm ceramic tile
m2
17.00
04/12/2008
O246
300mm x 300mm homogeneous tile
m2
17.50
04/12/2008
O247
600mm x 600mm granite slab
m2
48.00
04/12/2008
O248
600mm x 600mm marble slab
m2
43.00
04/12/2008
OO49
Wall & Floor Finishes
O249
Power float
m2
3.60
24/10/2008
O250
Wall tile
m2
17.22
06/01/2009
O251
Floor tile
m2
17.76
06/01/2009
O252
Skirting
5.25
06/01/2009
O253
Wall tile menara TM Melaka
m2
34.43
24/10/2008
O254
Floor tile Menara TM Melaka
m2
34.43
24/10/2008
O255
Floor tile skirting Menara TM Melaka
2.40
24/10/2008
O256
Carpet tile
m2
9.70
26/11/2008
O257
Carpet roll
m2
14.00
26/11/2008
kg
0.90
04/12/2008
kg
1.00
04/12/2008
kg
0.90
04/12/2008
OO45
Roofer
OO51
Structural steelwork fabrication, erection and
fixing including cranage
Heavy section
O258
Universal beam and universal column
OO52
Hollow section
O259
Square, rectangular and circular hollow sections
OO53
Attached connection
O260
Cleats, stiffeners and plates and the like
OO54
Roof truss
O261
Up to 10.0m span
kg
0.90
04/12/2008
O262
Above 10.0m span
kg
0.90
04/12/2008
OO55
Roofer
OO50
CHEW FU KEONG
Page :
12
of
15
Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
Price List
Ref Code
Trade Heading:
Name : PCK1
Item Description
Unit
Rate
O - Labour Rates
Mark
Supp
Last
Up %
Code
Updated
(Continued)
O263
Lay aluminium foil
m2
2.38
29/10/2008
O264
Lay chicken wire netting
m2
1.81
26/04/2008
O265
Fix fascia board
6.29
26/04/2008
O266
Fix valley gutter
5.58
18/02/2009
O267
Lay concrete roof tile
pc
0.50
24/10/2008
O268
Lay concrete roof tile to pitch not exceeding 30
degree
Lay metal deck to pitch not exceeding 30 degree
m2
6.00
03/12/2008
m2
5.00
03/12/2008
Lay 50mm thick fibre wool insulation & wire
mesh netting to slope
Lay sisalation to slope
m2
1.50
03/12/2008
m2
1.00
03/12/2008
O269
O270
O271
Ceiling Installer
O272
Ceiling board and frame
m2
6.50
13/02/2009
O273
Skim coat
m2
2.00
24/10/2008
OO56
O274
Ceiling framing & finishing fixing
non-suspended ceiling
1200mm x 600mm x 3.2mm thick ceiling board
m2
6.00
04/12/2008
O275
1200mm x 600mm x 4.5mm thick ceiling board
m2
6.50
04/12/2008
Sanitary
O276
Squatting w.c complete set
no
52.50
02/01/2009
O277
Closed coupled sitting w.c complete set
no
52.50
02/01/2009
O278
Table top wash basin complete set
no
42.50
02/01/2009
O279
Wall hung handicap wash basin complete set
no
45.00
24/12/2008
O280
Sink
no
40.00
02/01/2009
O281
Urinal
no
50.00
02/01/2009
O282
Wall mounted pillar tap
no
15.00
24/12/2008
O283
Hand bidet with flexible hose complete set
no
20.00
24/12/2008
O284
Surface mounted stainless steel paper holder
no
15.00
24/12/2008
O285
Stainless steel vertical liquid soap dispenser
complete set
Single robe hook with door stopper
no
25.00
24/12/2008
no
15.00
24/12/2008
Stainless steel floor trap complete with insect
cage, size 150mm x 150mm
40mm diameter stainless steel grab rail for OKU
no
10.00
24/12/2008
no
35.00
24/12/2008
O286
O287
O288
CHEW FU KEONG
Page :
13
of
15
Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
Price List
Ref Code
Trade Heading:
O289
Name : PCK1
Item Description
Unit
Rate
O - Labour Rates
Mark
Supp
Last
Up %
Code
Updated
(Continued)
On completion of the installation of sanitary
fittings, test all fittings, make good any defects
and leave in perfect working order to the entire
satisfaction of the Architect
Item
500.00
24/12/2008
No
400.00
02/03/2009
No
340.00
02/03/2009
frame
6.00
27/11/2008
frame
3.00
27/11/2008
no
6.00
27/11/2008
no
4.00
27/11/2008
no
3.00
27/11/2008
no
2.00
27/11/2008
no
4.00
27/11/2008
no
2.00
27/11/2008
pc
10.00
27/11/2008
pc
6.00
27/11/2008
WATER TANK
OO57
O290
O291
Approved FRP water storage tank square
type as described complete with cover and all
necessary fixing accessories
3520 Gallons; Ditto; overall size 4000mm x
2000mm x 2000mm high approximately 20m
above ground level
2200 Gallons; Ditto; overall size 5000mm x
2000mm x 1000mm high approximately
600mm above ground level
Scaffolder
O292
O293
O294
O295
O296
O297
O298
O299
O300
O301
Erect frame including cross braces, base plate
and joint pin
Dismantle frame, cross braces, base plate &
joint pin including stacking up properly directed
on site
Fix 6.0m g.i pipe bracing including all
accessories and coupler
Dismantle 6.0m g.i pipe bracing & accessories
and coupler including stacking up properly as
directed on site
Fix 3.0m g.i pipe bracing including all
accessories and coupler
Dismantle 3.0m g.i pipe bracing & accessories
and coupler including stacking up properly as
directed on site
Fix wall tie including drilling hole for anchor
bolt (bolt by Main Contractor)
Dismantle wall tie including making good bolt
hole
Fix netting size 6'0"x17'0" including tying in
position by wires
Dismantle netting including rolling up properly
and return to store as directed
Drainage
OO58
Surface Water
O302
Concrete base & P.C half round drain
18.00
27/11/2008
O303
230mm thick brickwall & plastering
m2
23.50
27/11/2008
O304
R.C Strut
no
10.00
27/11/2008
O305
Brickwall sump including R.C base
no
150.00
27/11/2008
CHEW FU KEONG
Page :
14
of
15
Date of Printing: 21/Jul/11
Global Estimating System (32 Bit) - H
Price List
Ref Code
Trade Heading:
Name : PCK1
Item Description
Unit
Rate
O - Labour Rates
Mark
Supp
Last
Up %
Code
Updated
(Continued)
O306
600mm diameter pipe culvert
75.00
27/11/2008
O307
225mm SGW pipe
no
5.00
27/11/2008
O308
Precast road kerb
no
5.00
27/11/2008
OO59
Rain Water Down Pipe
O309
100mm diameter
10.66
23/12/2008
O310
150mm diameter
10.66
23/12/2008
OO60
Gutter
O311
Galvanised iron
18.05
23/12/2008
8.50
10/12/2008
Road furniture
O312
CHEW FU KEONG