Task Name 132kV Grid stations Initiation Submission of Performance Security Contract Agreement Submission of Advance Payment Guarantee
Civil Works of Grid Stations Finalization of Civil SubContractor Issuance of PO / Contract Finalization
Electrical Mechanical Design Issuance of PO to Engineerg Primary Engineering
Design of CHB, Foundation Single Line Diagram & Misc drawings Archit. Drawings of CHB Structural drawings of CHB Equipment Layout Plan Foundation & Trench Layout General Overall layout Control House Building Plan and sections
Release of Advance Payment Foundation Drawings Opening of LC Request Misc. drawings Submission & Approval of Civil Drawings Archit. Drawings of CHB
Opening of LC Handing over of site Sites visit with Engineering , NTDC Design & MEPCO Fixation of SY Zero Level & Entry of TL Handing over of Site Kick off meeting with Client Execution Procurement Plan Sent to SPD Procurement Initiation Geotechnical Survey Issuance of PO Geotechnical Survey / Topographical Survey Submission of reports
Approval of Layouts Earthing Layouts & Material List Approval of Earthing Layout and design Steel Structure Drawings Hardware material List Other Layouts & Drawings Primary design freezed Secondary Engineering Control & Protection Schematics Approval of Schematics cable schedule and quantities Secondary Design freezesubmitted to EA
Structural drawings of CHB Foundation Drawings Misc. drwaings Mobilization of SubContractor Construction of Site Office Site Grubbing/Clearance Startup/Marking of Civil Works Foundations & Misc Works readiness CHB & Associated Works readiness Punch list clearance / End of Civil Works
Monitoring & Controlling Installation Works Steel structure Testing of Power T/F by MEPCO Staff at Store
Testing and Commissioning Dehydration of Power Transformers Testing of HV Equipment Testing of Power Transformers
Shifting of Power T/F from MEPCO Store Circuit breaker Disconnector Surge Arrestors Current and Potential Transformer MV Panels & PMT Relay and Control Panels Grounding material and connectors Stringing conductor for Bus Bars Connectors / Jumpering of Equipment Battery bank Battery chargers Cable laying Glanding of Panels / Cable Termination Testing
Loop Testing Scheme & Panel Commissioning of Circuit Breakers Preparation of Red Marked Drawings Energization
Circuit Breakers Issuance of PO Technical Submittal for Approval Approval of Technical Data and Drawings Manufacturing / Delivery Time period FAT Schedule Issuance of Inspection Certificate / Waiver Expected Transportation/ shipment Time
Disconnectors Issuance of PO Technical Submittal for Approval Approval of Technical Data and Drawings Manufacturing / Delivery Time period FAT Schedule Issuance of Inspection Certificate / Waiver Expected Transportation/ shipment Time
Current & Potential Transformers Issuance of PO Technical Submittal for Approval Approval of Technical Data and Drawings Manufacturing / Delivery Time period FAT Schedule Issuance of Inspection Certificate / Waiver Expected Transportation/ shipment Time
MV Panels & PMT Issuance of PO Technical Submittal for Approval Approval of Technical Data and Drawings Manufacturing / Delivery Time period FAT Schedule Issuance of Inspection Certificate / Waiver Expected Transportation/ shipment Time
Expected Delivery at site Issuance of DN
Expected Delivery at site Issuance of DN
Expected Delivery at site Issuance of DN
Expected Delivery at site Issuance of DN
Relay and Control Panels Issuance of PO Technical Submittal for Approval Approval of Technical Data and Drawings Manufacturing / Delivery Time period FAT Schedule Issuance of Inspection Certificate / Waiver Expected Transportation/ shipment Time
Cables and Conductors Issuance of PO Technical Submittal for Approval Approval of Technical Data and Drawings Manufacturing / Delivery Time period FAT Schedule Issuance of Inspection Certificate / Waiver Expected Transportation/ shipment Time
Expected Delivery at site Issuance of DN
Expected Delivery at site Issuance of DN
WORK
Initiation Submission of Performance Security Engineering
Primary Engineering
Secondary Engineering
Civil Works of Grid Stations
Contract Agreement
Single Line Diagram
Control & Protection Schematics
Finalization of Civil SubContractor
Submission of Advance Payment Guarantee Equipment Layout Plan
Approval of Schematics
Issuance of PO / Contract Finalization Design of CHB, Foundation & Misc drawings
Release of Advance Payment
Foundation & Trench Layout
cable schedule and quantities
Opening of LC Request General Overall layout Opening of LC Control House Building Plan and sections
Secondary Design freeze- Archit. Drawings of submitted to EA CHB Structural drawings of CHB
Approval of Layouts
Foundation Drawings
Earthing Layouts & Material List Approval of Earthing Layout and design Steel Structure Drawings Hardware material List Other Layouts & Drawings Primary design freezed
Misc. drawings Submission & Approval of Civil Drawings Archit. Drawings of CHB Structural drawings of CHB Foundation Drawings Misc. drwaings Mobilization of Sub-Contractor Construction of Site Office Site Grubbing/Clearance Startup/Marking of Civil Works
Foundations & Misc Works readiness CHB & Associated Works readiness Punch list clearance / End of Civil Works
lDSU WORK BREAKDOWN STRUCTURE
Procurement
Circuit Disconne CT & PT Breakers ctors Transformer MV Relay and Cables Panels & Control and PMT Panels Conducto rs
Issuance of PO Issuance of PO Issuance of PO
Issuance of PO
Issuance of PO
Issuance of PO
Issuance of PO
Technical Technical Technical Technical Technical Technical Submittal for Submittal for Submittal for Technical Submittal Submittal for Submittal for Submittal for Approval Approval Approval for Approval Approval Approval Approval Approval of Technical Data and Drawings Approval of Technical Data and Drawings Approval of Technical Data and Drawings Approval of Approval of Technical Technical Data and Data and Drawings Drawings Approval of Technical Data and Drawings Approval of Technical Data and Drawings
Manufacturin Manufacturin Manufacturin Manufacturing / g / Delivery g / Delivery g / Delivery Delivery Time Time period Time period Time period period FAT Schedule Issuance of Inspection Certificate / Waiver Expected Transportatio n/ shipment Time Expected Delivery at site Issuance of DN FAT Schedule Issuance of Inspection Certificate / Waiver Expected Transportatio n/ shipment Time Expected Delivery at site Issuance of DN FAT Schedule Issuance of Inspection Certificate / Waiver Expected Transportatio n/ shipment Time Expected Delivery at site Issuance of DN FAT Schedule Issuance of Inspection Certificate / Waiver
Manufacturin Manufacturin Manufacturin g / Delivery g / Delivery g / Delivery Time period Time period Time period FAT Schedule Issuance of Inspection Certificate / Waiver FAT Schedule Issuance of Inspection Certificate / Waiver Expected Transportatio n/ shipment Time Expected Delivery at site Issuance of DN FAT Schedule Issuance of Inspection Certificate / Waiver Expected Transportatio n/ shipment Time Expected Delivery at site Issuance of DN
Expected Transportatio n/ shipment Time Expected Expected Delivery at Delivery at site site Expected Transportation/ shipment Time Issuance of DN Issuance of DN
Installation Works Installation of Equipment
Testing and Commissioning Testing of All Equipments
Circuit breaker
Dehydration of Power Transformers
Disconnector
Testing of HV Equipment
Current and Potential Transformer
Testing of Power Transformers
Transformer MV Panels & PMT
Loop Testing Scheme & Panel Testing
Relay and Control Panels
Commissioning of Circuit Breakers
Cable laying
Preparation of Red Marked Drawings
Other Installation
Energization