0% found this document useful (0 votes)
238 views11 pages

WBS

The document outlines the work breakdown structure and procurement process for a substation project. It includes stages for engineering design, civil works, equipment procurement, installation, testing and commissioning. Key stages include primary and secondary engineering, approval of designs, procurement of circuit breakers, transformers, panels, cables, installation works, testing of equipment and energization.

Uploaded by

qasim7575
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
238 views11 pages

WBS

The document outlines the work breakdown structure and procurement process for a substation project. It includes stages for engineering design, civil works, equipment procurement, installation, testing and commissioning. Key stages include primary and secondary engineering, approval of designs, procurement of circuit breakers, transformers, panels, cables, installation works, testing of equipment and energization.

Uploaded by

qasim7575
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Task Name 132kV Grid stations Initiation Submission of Performance Security Contract Agreement Submission of Advance Payment Guarantee

Civil Works of Grid Stations Finalization of Civil SubContractor Issuance of PO / Contract Finalization

Electrical Mechanical Design Issuance of PO to Engineerg Primary Engineering

Design of CHB, Foundation Single Line Diagram & Misc drawings Archit. Drawings of CHB Structural drawings of CHB Equipment Layout Plan Foundation & Trench Layout General Overall layout Control House Building Plan and sections

Release of Advance Payment Foundation Drawings Opening of LC Request Misc. drawings Submission & Approval of Civil Drawings Archit. Drawings of CHB

Opening of LC Handing over of site Sites visit with Engineering , NTDC Design & MEPCO Fixation of SY Zero Level & Entry of TL Handing over of Site Kick off meeting with Client Execution Procurement Plan Sent to SPD Procurement Initiation Geotechnical Survey Issuance of PO Geotechnical Survey / Topographical Survey Submission of reports

Approval of Layouts Earthing Layouts & Material List Approval of Earthing Layout and design Steel Structure Drawings Hardware material List Other Layouts & Drawings Primary design freezed Secondary Engineering Control & Protection Schematics Approval of Schematics cable schedule and quantities Secondary Design freezesubmitted to EA

Structural drawings of CHB Foundation Drawings Misc. drwaings Mobilization of SubContractor Construction of Site Office Site Grubbing/Clearance Startup/Marking of Civil Works Foundations & Misc Works readiness CHB & Associated Works readiness Punch list clearance / End of Civil Works

Monitoring & Controlling Installation Works Steel structure Testing of Power T/F by MEPCO Staff at Store

Testing and Commissioning Dehydration of Power Transformers Testing of HV Equipment Testing of Power Transformers

Shifting of Power T/F from MEPCO Store Circuit breaker Disconnector Surge Arrestors Current and Potential Transformer MV Panels & PMT Relay and Control Panels Grounding material and connectors Stringing conductor for Bus Bars Connectors / Jumpering of Equipment Battery bank Battery chargers Cable laying Glanding of Panels / Cable Termination Testing

Loop Testing Scheme & Panel Commissioning of Circuit Breakers Preparation of Red Marked Drawings Energization

Circuit Breakers Issuance of PO Technical Submittal for Approval Approval of Technical Data and Drawings Manufacturing / Delivery Time period FAT Schedule Issuance of Inspection Certificate / Waiver Expected Transportation/ shipment Time

Disconnectors Issuance of PO Technical Submittal for Approval Approval of Technical Data and Drawings Manufacturing / Delivery Time period FAT Schedule Issuance of Inspection Certificate / Waiver Expected Transportation/ shipment Time

Current & Potential Transformers Issuance of PO Technical Submittal for Approval Approval of Technical Data and Drawings Manufacturing / Delivery Time period FAT Schedule Issuance of Inspection Certificate / Waiver Expected Transportation/ shipment Time

MV Panels & PMT Issuance of PO Technical Submittal for Approval Approval of Technical Data and Drawings Manufacturing / Delivery Time period FAT Schedule Issuance of Inspection Certificate / Waiver Expected Transportation/ shipment Time

Expected Delivery at site Issuance of DN

Expected Delivery at site Issuance of DN

Expected Delivery at site Issuance of DN

Expected Delivery at site Issuance of DN

Relay and Control Panels Issuance of PO Technical Submittal for Approval Approval of Technical Data and Drawings Manufacturing / Delivery Time period FAT Schedule Issuance of Inspection Certificate / Waiver Expected Transportation/ shipment Time

Cables and Conductors Issuance of PO Technical Submittal for Approval Approval of Technical Data and Drawings Manufacturing / Delivery Time period FAT Schedule Issuance of Inspection Certificate / Waiver Expected Transportation/ shipment Time

Expected Delivery at site Issuance of DN

Expected Delivery at site Issuance of DN

WORK
Initiation Submission of Performance Security Engineering

Primary Engineering

Secondary Engineering

Civil Works of Grid Stations

Contract Agreement

Single Line Diagram

Control & Protection Schematics

Finalization of Civil SubContractor

Submission of Advance Payment Guarantee Equipment Layout Plan

Approval of Schematics

Issuance of PO / Contract Finalization Design of CHB, Foundation & Misc drawings

Release of Advance Payment

Foundation & Trench Layout

cable schedule and quantities

Opening of LC Request General Overall layout Opening of LC Control House Building Plan and sections

Secondary Design freeze- Archit. Drawings of submitted to EA CHB Structural drawings of CHB

Approval of Layouts

Foundation Drawings

Earthing Layouts & Material List Approval of Earthing Layout and design Steel Structure Drawings Hardware material List Other Layouts & Drawings Primary design freezed

Misc. drawings Submission & Approval of Civil Drawings Archit. Drawings of CHB Structural drawings of CHB Foundation Drawings Misc. drwaings Mobilization of Sub-Contractor Construction of Site Office Site Grubbing/Clearance Startup/Marking of Civil Works

Foundations & Misc Works readiness CHB & Associated Works readiness Punch list clearance / End of Civil Works

lDSU WORK BREAKDOWN STRUCTURE


Procurement
Circuit Disconne CT & PT Breakers ctors Transformer MV Relay and Cables Panels & Control and PMT Panels Conducto rs
Issuance of PO Issuance of PO Issuance of PO

Issuance of PO

Issuance of PO

Issuance of PO

Issuance of PO

Technical Technical Technical Technical Technical Technical Submittal for Submittal for Submittal for Technical Submittal Submittal for Submittal for Submittal for Approval Approval Approval for Approval Approval Approval Approval Approval of Technical Data and Drawings Approval of Technical Data and Drawings Approval of Technical Data and Drawings Approval of Approval of Technical Technical Data and Data and Drawings Drawings Approval of Technical Data and Drawings Approval of Technical Data and Drawings

Manufacturin Manufacturin Manufacturin Manufacturing / g / Delivery g / Delivery g / Delivery Delivery Time Time period Time period Time period period FAT Schedule Issuance of Inspection Certificate / Waiver Expected Transportatio n/ shipment Time Expected Delivery at site Issuance of DN FAT Schedule Issuance of Inspection Certificate / Waiver Expected Transportatio n/ shipment Time Expected Delivery at site Issuance of DN FAT Schedule Issuance of Inspection Certificate / Waiver Expected Transportatio n/ shipment Time Expected Delivery at site Issuance of DN FAT Schedule Issuance of Inspection Certificate / Waiver

Manufacturin Manufacturin Manufacturin g / Delivery g / Delivery g / Delivery Time period Time period Time period FAT Schedule Issuance of Inspection Certificate / Waiver FAT Schedule Issuance of Inspection Certificate / Waiver Expected Transportatio n/ shipment Time Expected Delivery at site Issuance of DN FAT Schedule Issuance of Inspection Certificate / Waiver Expected Transportatio n/ shipment Time Expected Delivery at site Issuance of DN

Expected Transportatio n/ shipment Time Expected Expected Delivery at Delivery at site site Expected Transportation/ shipment Time Issuance of DN Issuance of DN

Installation Works Installation of Equipment

Testing and Commissioning Testing of All Equipments

Circuit breaker

Dehydration of Power Transformers

Disconnector

Testing of HV Equipment

Current and Potential Transformer

Testing of Power Transformers

Transformer MV Panels & PMT

Loop Testing Scheme & Panel Testing

Relay and Control Panels

Commissioning of Circuit Breakers

Cable laying

Preparation of Red Marked Drawings

Other Installation

Energization

You might also like