Daily Program Nov-2011
Daily Program Nov-2011
S.l. No. Description 1 Segment 1A CC casting of pipe fixing 2 3 Segment 2A Segment 1 PVD Driving Wall casting 2nd lift CH 800-840/Country side 4 Open deep drain Rod binding 2nd lift CH 840-860/Country side Sub base work (CH 240-340) 5 6 7 8 9 10 11 12 13 14 Road Work Improved sub grade work (180-240) Rail Relocation Sheet Pile RCC Drainage Pipe Electric Substation Wasa Relocation Electric Relocation Laboratory Interlocking Block Dismantling work ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3 ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress Sub base preparation (CH 400-580) Concrete Pouring Concrete Pouring of Pipe Concrete Pouring of Colun & Grade beam Connection work of relocated line Connection of relocated line in process Improved sub grade work (180-240) in progress Sub base preparation (CH 400-580) in progress Concrete Pouring in progress Concrete Pouring of Pipe in progress Concrete Pouring of Column & Grade beam in progress Connection work of relocated line in progress Circuit (33/33/11/0.44 KV ) overhead cable fixing complete Rebar fabrication in progress Sub base work (CH 240-340) in progress PVD Driving in progress Rebar fabrication & shuttering executed Settlement Record Sand bagging for Surcharge material placement CC casting of pipe fixing in progress Settlement Record in progress Sand bagging in progress Work Program of 1st Nov. 2011 Drainage pipe installation Achievement of 31th Oct.2011 Drainage pipe installation in progress
Remarks
Achievement of 21th Nov Nov.2011 Drainage pipe installation in progress Sub-base materials laying in progress Settlement Record in progress Sand bagging for preloading work in progress Surcharge material placement in progress PVD Driving in progress
Remarks
Earth Excavation,Soling,CC(CH 865-885) Sub base work (CH 240-340) Sub base work (CH 240-340) in progress Improved sub grade work (180-240) in progress Sub base preparation (CH 400-580) in progress Concrete Pouring of Column in progress
Sub base preparation (CH 400-580) Concrete Pouring of Column Newly installed line is functioning
Laboratory / Field Test Interlocking Block Dismantling work ILB production Mosque dismantling ILB production in progress Mosque dismantling work in progress
MS Rod deposit to CPA store-1in progress
Achievement of 22th Nov Nov.2011 Drainage pipe installation in progress Sub-base materials laying in progress Settlement Record in progress Sand bagging for preloading work in progress Surcharge material placement in progress PVD Driving in progress Earth excavation executed Sub base work (CH 240-340) in progress Improved sub grade work (180-240) in progress Sub base preparation (CH 400-580) in progress Concrete Pouring of Column in progress Shuttering of slab in progress
Remarks
Work Program of 24th Nov. 2011 Drainage pipe installation Sub-base materials laying Settlement Record Sand bagging for preloading work
Achievement of 23th Nov Nov.2011 Drainage pipe installation in progress Sub-base materials laying in progress Settlement Record in progress Sand bagging for preloading work in progress Surcharge material placement in progress Earth excavation executed
Remarks
Sub base work (CH 240-340) in progress Improved sub grade work (180-240) in progress Sub base preparation (CH 400-580) in progress Concrete Pouring of Column in progress Shuttering of slab in progress
Sub base work (CH 240-340) 5 6 Road Work Improved sub grade work (180-240) Rail Relocation Sub base preparation (CH 400-580) Concrete Pouring of Column 7 Electric Substation Shuttering of slab Newly installed line is functioning 8 Wasa Relocation Old line removing 9 Laboratory / Field Test ILB production Mosque dismantling
Sub base work (CH 240-340) in progress Improved sub grade work (180-240) in progress Sub base preparation (CH 400-580) in progress Concrete Pouring of Column in progress Shuttering of slab in progress
10 Dismantling work
11
10 Dismantling work
11
10 Dismantling work
11