Critical Path Method
Critical Path Method
Slack or float is the amount of time an activity can be delayed without delaying a succeeding activity or the project finish date.
CPM - Approach
Free slack or free float is the amount of time an activity can be delayed without delaying the early start of any immediately following activities. Total slack or total float is the amount of time an activity can be delayed from its early start without delaying the planned project finish date. A forward pass through the network diagram determines the early start and finish dates. A backward pass determines the late start and finish dates.
ES Float
Backward Pass
EF
Forward Pass
LS
LF
ES: Early Start LS: Late Start EF: Early Finish LF: Late Finish
6
Activity 4 Float=0
14
0
Start 0
Activity 1 Float=0
14 14
18
Activity 5 Float=0
3 3 9
Activity 3 Float=5
14
18
Activity
Activity 1 Activity 2 Activity 3 Activity 4 Activity 5
Duration
3 3 6 8 4 8
14
Paths
Start, 1, 2, 4,5, End Start, 1, 3, 5, End
Duration
18 13 End
The critical path does not necessarily contain all the critical activities; it only accounts for time.
Example
like growing grass was on the critical path for Disneys Animal Kingdom.
There can be more than one critical path if the lengths of two or more paths are the same. The critical path can change as the project progresses.
the duration of critical activities or tasks by adding more resources or changing their scope.
Crashing
activities by obtaining the greatest amount of schedule compression for the least incremental cost.
tracking activities by doing them in parallel or overlapping them.
Fast
It is important to update project schedule information to meet time goals for a project.
The critical path may change as you enter actual start and finish dates. If you know the project completion date will slip, negotiate with the project sponsor.
Thank You
Q & A Session