Project Management II Module
Project Management II Module
1. The first is that is helps more accurately and specifically define and organize
the scope of the total project. The most common way this is done is by using
a hierarchical tree structure. Each level of this structure breaks the project
deliverables or objectives down to more specific and measurable chunks.
2. The second reason for using a WBS in your projects is to help with assigning
responsibilities, resource allocation, monitoring the project, and controlling
the project. The WBS makes the deliverables more precise and concrete so
that the project team knows exactly what has to be accomplished within each
deliverable. This also allows for better estimating of cost, risk, and time
because you can work from the smaller tasks back up to the level of the entire
project.
3. Finally, it allows you double check all the deliverables’ specifics with the
stakeholders and make sure there is nothing missing or overlapping.
• Process of Creating a WBS
There are several inputs you will need to get you off on the right foot:
• The Project Scope Statement
• The Project Scope Management Plan
• Organizational Process Assets
• Approved Change Requests
These inputs should give you all the information you and your team needs to
create your WBS. Along with these inputs, you will use certain tools as well.
Finally, using these inputs and tools you will create the following outputs:
The second factor is how long each individual activity will take. This is
discussed in the section on estimating activity duration. It includes
methods for estimating durations, problems with estimates, and
remedies to those problems.
The third factor is how many key resources are available at
specific points in the project. For example, if six rooms were
available to be painted at the same time, and fewer than six
painters were available, progress would be slowed. This is
discussed in
The fifth and final factor is cash flow. Projects may not start until
money is approved, but progress may also be slowed until enough
revenue arrives to cover expenses.
Develop Project schedules
You need to complete all of the scheduling processes discussed up
to this point even if you use Microsoft Project or another
scheduling tool. At this point, you have defined, sequenced, and
estimated the duration for all the schedule activities.
Early start date (ES):the earliest possible point in time on which uncompleted portions of a
schedule activity can start, based upon the schedule network logic, the data date, and any
schedule constraints
Early finish date (EF):the earliest possible point in time on which uncompleted portions of a
schedule activity can finish, based upon the schedule network logic, the data date, and any
schedule constraints
Late start date (LS):the latest possible point in time in which uncompleted portions of a
schedule activity can start, based upon the schedule network logic, the project completion date,
and any schedule constraints
Late finish date (LF):the latest possible point in time when the uncompleted portions of a
schedule activity can finish based upon the network logic, the project completion date, and any
schedule constraints
First or Forward Pass
SECOND OR BACKWARD PASS
The second pass is sometimes called the backward pass. The
backward pass is “a critical path method technique for calculating
the late start and late finish dates by working backward through
the schedule model from the project end date.
When performing the backward pass, teams start at the end and
work backward asking, “How late can each activity be finished
and started?” Unless there is an imposed date, the late finish for
the last activity during planning is the same as the early finish
date.
SECOND OR BACKWARD PASS
Enumeration Method