Group_1_-_Project_Management_Presentation[1]
Group_1_-_Project_Management_Presentation[1]
MBA844 - PRESENTATION
COME UP WITH A PROJECT LOGIC TABLE FOR A PROJECT
WITH AT LEAST 14 ACTIVITIES SHOWING THEIR
PRECEDENCIES
a) COME UP WITH A NETWORK DIAGRAM
b) SHOW PROJECT DURATION
c) SHOW THE CRITICAL PATH
d) DEMONSTRATE THE CONCEPT OF RESOURCE LEVELLING
AND RESOURCE SMOOTHING
e) SHOW HOW A PROJECT MANAGEMENT STRATEGIST CAN
CREATE VALUE THROUGH NETWORK TECHNIQUES (PERT,
CPA)
2
14 ACTIVITIES SHOWING THEIR PRECEDENCIES
Event Activity Description Predecessor Duration
NUMBER (Days)
1 A Acquire and identify the land site _ 2
2 B Site clearance and preparation A 5
3 C Source excavating equipment A 3
4 D Deliver excavating equipment C 3
5 E Foundation pegging and marking B 2
6 F Excavation and site preparation D,E 3
7 G Deliver all building materials to site B 4
8 H Foundation casting and laying F,G 10
9 I Build the superstructure (walls, columns, H 20
beams)
10 J Inspect the superstructure for quality and I 1
safety
11 K Install roofing and waterproofing J 5
12 L Electrical, plumbing, and HVAC installations K 3
13 M Plastering and flooring installations K 2
14 N Painting (interior and exterior) L.M 5
15 O Final inspection and handover to the N 3
community
a) COME UP WITH A NETWORK DIAGRAM
CC
D
Project Duration and Critical Path
• Project managers often view resource leveling as being the preferable approach when
increasing the supply of resources would be less feasible than adjusting the project’s deadline.
They frequently believe that resource smoothing is better than the existing activity scheduling
when the project's deadline is a more strict constraint.
Benefits
Benefits of Resource Leveling
• Prevents Over-Allocation: Ensures that no single resource is overburdened, reducing the risk of burnout and
errors.
• Improves Resource Utilization: Balances the workload across available resources, making better use of the
team’s capabilities.
• Enhances Project Feasibility: By addressing resource constraints, it makes the project more realistic and
achievable.
• Reduces Stress: Creates a more manageable workload for team members, leading to a healthier work
environment.
• Minimizes Delays: Helps identify and resolve potential bottlenecks early, preventing unexpected delays later
in the project.
Plan and schedule projects: PERT is used to plan and schedule projects by
identifying the tasks, dependencies, and timelines required to complete the
project.
Analyze and manage risk: PERT helps to identify potential risks and uncertainties
in the project, and to develop strategies to mitigate them.
Estimate project duration: PERT is used to estimate the minimum project
duration, taking into account the dependencies and timelines of the various
tasks.
Identify critical path: PERT helps to identify the critical path, which is the longest
path through the network diagram and determines the minimum project
duration.
Monitor and control project progress: PERT is used to monitor and control
project progress, by tracking the actual completion of tasks and comparing it to
the planned schedule.
Advantages and Disadvantages of PERT
Advantages of PERT:
• 1. Helps to identify and manage risk: PERT helps to identify potential risks and
uncertainties in the project.
• 2. Provides a clear project schedule: PERT provides a clear project schedule, including the
tasks, dependencies, and timelines.
• 3. Helps to identify the critical path: PERT helps to identify the critical path, which
determines the minimum project duration.
Disadvantages of PERT:
• 1. Can be complex and time-consuming: PERT can be complex and time-consuming to
implement, especially for large and complex projects.
• 2. Requires accurate estimates: PERT requires accurate estimates of task durations and
dependencies.
• 3. Does not account for resource constraints: PERT does not account for resource
constraints, such as availability of personnel and equipment.
CRITICAL PATH ANALYSIS / METHOD
What is Critical Path Method (CPA)
• The Critical Path Analysis (CPA) is a technique used in project
management to identify the critical path, which is the longest
path through the network diagram. Kelley (1961) defined CPA
as a method for determining the minimum duration required
to complete a project, taking into account the dependencies
between tasks.
• By using CPA, project managers can identify the critical path
and prioritize tasks and allocate resources effectively.
• CPA can also be used to identify potential bottlenecks and
areas for optimization, and to create a more realistic project
schedule.
• Some popular tools and techniques used in CPA include
Microsoft Project, Primavera P6 and Oracle Primavera.
What CPA is used for
• Manage risk: CPA helps to identify potential risks and uncertainties in the
project, and to develop strategies to mitigate them for example, using the
same house-building might have potential risks and uncertainties such as
delays in obtaining building permits or inclement weather affecting
construction
• Identify the critical tasks: Critical tasks are those that determine the minimum
project duration. CPA helps to identify these tasks by analyzing the network
diagram for example, in building a house the critical tasks are foundation work
( Task A), framing (Task B), roofing (Task C). CPA would identify these tasks as
critical because they determine the minimum project duration.
• Prioritize tasks: CPA helps to prioritize tasks based on their criticality and
impact on the project duration. By analysing the network diagram and
calculating the longest path(s), the project management strategist can
identify the critical activities that must be closely monitored and managed.
• Identify dependencies: CPA helps to identify the dependencies between tasks,
including predecessor and successor tasks.
Advantages and Disadvantages of
CPA
Advantages of CPM
• 1. Improved project planning: CPA helps to create a realistic project schedule and identifies
potential risks and uncertainties.
• 2. Increased efficiency: CPA helps to prioritize tasks and allocate resources more efficiently.
• 3. Better risk management: CPA helps to identify potential risks and uncertainties, and to develop
strategies to mitigate them.
• 4. Reduced project duration: CPA helps to identify the critical path and optimize the project
schedule, reducing the project duration.
Disadvantages of CPM
• 1. Complexity: CPA can be complex and difficult to implement, especially for large and complex
projects.
• 2. Time-consuming: CPA requires a significant amount of time and effort to create and maintain
the network diagram.
• 3. Assumptions: CPA is based on assumptions about the project, such as the task durations and
dependencies.
• 4. Limited flexibility: CPA can be inflexible, making it difficult to respond to changes in the project
scope or schedule.
Value created through Network
Techniques (PERT,CPA)
Improved Project Planning – creating a realistic project schedule and
ensuring timely completion.
Enhanced Risk Management- identifying potential risks and uncertainties
using PERT's probability and impact assessments
Optimized Resource Allocation- ensuring that resources are allocated to
critical tasks and milestones.
Increased Efficiency- eliminating non-essential tasks and activities.
Improved Monitoring and Control- Ensuring that the project stays on
track and making adjustments as needed.
Enhanced Stakeholder Management- identifying and engaging
stakeholders, ensuring their needs and expectations are met.
Better Communication- providing regular project updates, highlighting
progress, risks, and issues.
THANK YOU