Cost Management Chapter 4
Cost Management Chapter 4
CHAPTER FOUR
Project Cost Control
CV = EV – AC
SPI = EV/PV
CPI = EV/AC
EVM Rules
Example (1)
The cost data for a small construction project are
given in the following table; the schedule
duration is 20 months the project has been
worked on for 15 months. PERFORM EVM
ANALYSIS for the mentioned data date.
Solution
Cost Prediction
9
Q&A
BAC = 200 PV= 100 AC= 120 EV= 80
A. 200.
B. 220.
C. 240.
D. 260.
Answer: C
10
Q&A
BAC = 200 PV= 100 AC= 120 EV= 80
A. 300.
B. 325.
C. 350.
D. 375.
Answer: A
11
Q&A
BAC = 200 PV= 100 AC= 120 EV= 80
A. - 80.
B. - 100.
C. + 100.
D. + 200.
Answer: B
12
Q&A
BAC = 200 PV= 100 AC= 120 EV= 80
A. 120.
B. 140.
C. 180.
D. 200.
Answer: A
13
Q&A
BAC = 200 PV= 100 AC= 120 EV= 80
A. 0.67.
B. 1.00.
C. 1.50.
D. 2.00.
Answer: C
14