GP- Mode of Measurment

The document presents an overview of IS 1200, which outlines the units of measurement and payment for various civil engineering works, including earthwork, concrete, brickwork, and more. It details specific measurement units for different types of construction tasks, such as cubic meters for volume and square meters for area. Additionally, it provides a breakdown of payment structures for each type of work, ensuring clarity in estimating costs.

Uploaded by

shang chi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
3 views59 pages

GP- Mode of Measurment

The document presents an overview of IS 1200, which outlines the units of measurement and payment for various civil engineering works, including earthwork, concrete, brickwork, and more. It details specific measurement units for different types of construction tasks, such as cubic meters for volume and square meters for area. Additionally, it provides a breakdown of payment structures for each type of work, ensuring clarity in estimating costs.

Uploaded by

shang chi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 59

www.menti.

com

 What is IS 1200
 Use the code – 1607709 – for giving answer
Measurements
in
Estimating
Mr. Ghanshyam Pal
Assistant Professor
Thakur College of Engineering & Technology
Kandivali.
Content of the presentation

 Units of Measurement and  Painting


Payment  Woodwork
 Earth work
 Steel work
 Concrete
 Miscellaneous

 Brickwork  Materials

 Stonework  Electrical items

 Roofing  Plumbing

 Road
 Flooring
 IS Code -1200 Reference
 Finishing
Units of measurement & Units of payment

• The unit of different works depend on their nature, size & shape.
• In general, the units of different item of work are based on the
principals mentioned further :-
• Mass, voluminous and thick works shall be taken in cubic unit or
volume. the measurements of length, width and height or depth shall
be taken to compute the volume or cubic contents
• Shallow, thin and surface works shall be taken in square unit or in
area. the measurement of length and width or height shall be taken
to compute the area.
• Long and thin work is taken in running unit.
• Piece work, job work is taken in number.
EARTHWORK
UNITS OF MEASUREMENT & PAYMENT
Earth Work
PARTICULARS OF ITEMS Measure Payment

•Earth filling under floors cu.m % cu.m

•Rock excavation cu.m %cu.m

•Puddle clay core cu.m %cu.m


PARTICULARS OF ITEMS Measure Payment

•Surface dressing and leveling,etc. Sq. m per sq. m

•cutting of trees no per no.

•Sand filling cu m per cu m

7
Concrete
CONCRETE

PARTICULARS OF ITEMS measure payments


•Cement concrete 1:4:8 in

foundation cu m per cu m

•Plain cement concrete 1:2:4 cu per cu m

•R.C.C chajja and sun shade m per cu m

cu m
PARTICULAR OF ITEMS measure payments
•Precast cement concrete cu m per cu m

• Cement concrete jali work sq. m per sq. m

• Cement concrete bed plates cu m per cu m


BRICK WORK
BRICK WORK

PARTICULARS OF ITEMS measure payment


• First class burnt bricks in mud

mortar in foundation and plinth cu m per cu m

•First class burnt bricks in mud

mortar in super structure cu m per cu m


PARTICULARS OF ITEMS measure payment
• First class B.B in cement mortar 1:5

in foundation and plinth cu m per cu m

• First class B.Bin cement mortar 1:5 in

superstructure cu m per cu m

First class B.B in cement mortar 1:6 in

foundation and plinth cu m per cu m


STONE WORK
STONE WORK

PARTICULARS OF ITEMS measure payment

• Coursed rubble masonry in

mud mortar in foundation and cu m per cu m

plinth
cu m per cu m
• Coursed rubble masonry in

mud mortar in super structure


PARTICULARS OF ITEMS measure payment

•Coursed rubble masonry in lime

mortar 1:3 in foundation and plinth cu m per cu m


•Coursed rubble masonry in cement

mortar 1:7 in foundation and plinth cu m per cu m


•Coursed rubble masonry in

cement mortar 1:7 in super cu per cu


ROOFING
ROOFING

PARTICULARS OF ITEMS measure payment

• R.C.C slab roofing cu m per cu m

• R.B slab roofing cu m per cu m

• First class mud roofing sq per sq m

•Second class mud roofing m per sq m

sq m
PARTICULARS OF ITEMS measure payment

•Third class mud roofing sq m per sq m

•Expension joint metre per m

• Allahabad tile roofing sq m per sq m

• Eave board sq m per sq m


FLOORING
FLOORING

PARTICULARS OF ITEMS measure payment

•Conglomerate floor 2.5 cm thick of

cement concrete 1:2:4 over 7.5 cm lime

concrete sq m per sq m
PARTICULARS OF ITEMS measure payment

•Flate brick flooring in cement over


10cm thick cement concrete 1:6 :18
over 10 cm thick sand filling sq m per sq m
•Brick on edge flooring over 10 cm
thick line concrete over 10 cm sand
filling sq m per sq m
PARTICULARS OF ITEMS measure payment

• Dry brick on edge flooring

with sand grouting over


sq m per sq m
consolidating earth

• Toping of cement concrete sq per sq m


1:2:4
m
• Terrazo flooring over 10 cm per sq m
thick cement concrete 1:2:4 over
FINISHING
FINISHING

PARTICULARS OF ITEM
measure payment

•Mud plaster 12.5 mm thick sq per sq m


m
per sq m
• Cement plaster 12.5 mm thick 1:4 sq
m per sq m

• Cement plaster 12 mm thick 1:5 sq per sq m


m

• Lime plaster 12.5 mm thick sq


PARTICULARS OF ITEMS measure payment
• Gobri leeping sq m per sq m
• Cement pointing 1:2 (deep) sq m per sq m
• Cement pointing 1:2 (flush) sq m per sq m
• Cement pointing 1:3 (flush) sq m per sq m
PAINTING
PAINTING

PARTICULARS OF ITEMS
payment
measure
• Painting doors and windows (3 coat) sq per sq m
m
per sq m
• Painting doors and windows (2 coat) sq
m per sq m

• Varnishing 2 coats sq per sq m


m

• Solignum painting 2 coats sq


PARTICULARS OF ITEMS measure payment

• Coal tarring (no. of coats specified sq. m per sq. m


• Removing of paint or varnish
sq. per sq.

m m
WOOD WORK
WOOD WORK

PARTICULARS OF ITEMS measure payment

• Deodar wood wrought framed in

beams and battened and fixed in

position sq m per sq m

• Doors, windows and almirah of


sq m per sq m
any type
PARTICULARS OF ITEMS measure payment

• Sawing of timber
sq m per sq m
• Ballies(dia. Specified)
per m
• Deodar wood panelled and glazed
metre
doors or windows complete and

fixed in position
per sq m
STEEL
WORK
STEEL
WORK

PARTICULARS OF ITEMS payment


measure
per sq m
•Expended metal (size specified) sq m
per quintal
• Iron work in trusses quintal
per cm
•Threading in iron cm
PARTICULARS OF ITEMS measure payment

Welding cm per cm

Rivets, bolts and nuts quintal per quintal

Boring holes in iron no. per no.

Barbed wire fencing metre per m


MISCELLANEOUS

PARTICULARS OF ITEMS measure payment

•Ornamental cornice metre per m

•Jungle clearance sq m per sq m

•Silt clearance cu m per cu m

•Glazing sq m per sq m
PARTICULAR OF ITEMS asure payment
me
•Glazed panes (supply) sq m per sq m
•Renewing glass panes no.
Per no.
•Fixing of glass panes no. Per no.
Glazed panes
MATERIAL
S

PARTICULARS OF ITEMS measure payment

• Supply of bricks 1000 no. Per 1000 no.

• Supply of cement bag per bag


• Supply of sand per cu m
cu m

,
PARTICULARS OF ITEMS measure payment

• Supply of surkhi cu m per cu m

• Supply of brick ballast cu m per cu m

• Supply of steel quintal per quintal

• Supply of bitumen tonne per tonne


ELECTRICAL INSTALLATION

PARTICULARS OF ITEMS measure payment

•Wiring in the building for all types

of electric filling such as bulb, plug ,

fan, point, power plug , etc. each each


PARTICULARS OF ITEMS me asure payment

• Supply of installated electric wire metre per m


• Supply of bare electric wire
quintal quintal
PUBLIC HEALTH ENGG.
PUBLIC HEALTH ENGG.

PARTICULAR OF ITEMS measure payment

•Supply of water closet no. per no.


•Supply of intercepting trap no.
per
•Supply of wash hand basin no.
no.

per no.
PARTICULARS OF ITEMS measure payment

• Supply of bib cock no. Per no.

• Supply of stop cock no. Per no.

• Supply of water metre no. Per no.

• Supply of C.I pipes metre per m


• bib cock

stop cock
ROADS
ROADS

PARTICULARS OF ITEMS measure payment

•Preparation of sub grade for soling

sq m % sq m
coat

•Collection of bricks of soling coat

including stacking and consolidating

2.5 cm thick layers of clay cu m per cu m


PARTICULARS OF ITEMS measure payment

•Brick on end edging on both sides

with bricks and labour complete rm rm

•Collection of bajri screened and

stacked cu m cu m
IS: 1200 (Part-1 to 27) For measuring
different items in civil engineering
Quantity measurement

1. Earth work in Excavation – m3 (Cubic meter).


2. Earth work in Filing – m3 (Cubic meter).
3. Brick work – m3 (Cubic meter).
4. Plastering work – m2 (Square meter).
5. Concrete work – m3 (Cubic meter).
6. Reinforcement – Kg (Kilogram).
7. Painting – m2 (Square meter)
8. Skirting – r.m. (running meter)
Quantity measurement

9. Flooring – m2 (Square meter).


10. Brick work(4.5 ” thick) – m2 (Square meter).
11. Structural steel work – Kg (Kilogram).
12. Grills – Kg (Kilogram) or m2 (Square meter).
13. Doors and windows – m2 (Square meter).
14. Pointing work – m2 (Square meter).
16. Retaining Wall – m3 (Cubic meter).
17. M.S pipes for steel structure – r.m. (running meter)
18. Water line, sewer line, drainage pipe – r.m. (running meter)
19. Railing – r.m. (running meter).
20. Soling work – m2 (Square meter).
21. Manholes – No. (Number).
22. Chambers – No. (Number).
23. Plumbing and sanitary fittings work – No. (Number).
THANK YOU