01 - Pembaikan Cerun SK Puchong - Bbs Eng SDN BHD - Kick Off Slide

The document outlines the kick-off meeting details for a slope repair project at Sekolah Kebangsaan Pusat Bandar Puchong, scheduled for February 21, 2025. The project, managed by JKR Malaysia and contracted to BBS Engineering Sdn Bhd, has a budget of RM 1,490,770.50 and a construction period of 52 weeks, starting from February 17, 2025, to February 16, 2026. Key technical issues identified include visible cracks, damp patches, and the absence of a drainage system at the site.

Uploaded by

sharifah atiqah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
27 views16 pages

01 - Pembaikan Cerun SK Puchong - Bbs Eng SDN BHD - Kick Off Slide

The document outlines the kick-off meeting details for a slope repair project at Sekolah Kebangsaan Pusat Bandar Puchong, scheduled for February 21, 2025. The project, managed by JKR Malaysia and contracted to BBS Engineering Sdn Bhd, has a budget of RM 1,490,770.50 and a construction period of 52 weeks, starting from February 17, 2025, to February 16, 2026. Key technical issues identified include visible cracks, damp patches, and the absence of a drainage system at the site.

Uploaded by

sharifah atiqah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 16

JABATAN KERJA RAYA MALAYSIA

PROJEK PEMBAIKAN CERUN DAN KERJA-KERJA BERKAITAN DI SEKOLAH


KEBANGSAAN PUSAT BANDAR PUCHONG (2), DAERAH PETALING, SELANGOR
KICK-OFF MEETING

Tarikh: 21 Februari 2025


Masa: 10.30 AM
Tempat: Bilik Mesyuarat Utama Tingkat 3, JKR Daerah Petaling Kompleks Pejabat
Kerajaan Daerah Petaling Persiaran Atmosfera, Seksyen U5, Shah Alam

Kontraktor Reka dan Bina:


BBS Engineering Sdn Bhd
No. 35-1, Jalan Damai Raya 1, Alam Damai
Cheras, 56000 Wilayah Persekutuan Kuala
Lumpur
SITE ORGANIZATION CHART
MANAGER
NOORDIRAN BINTI
AWANG

PROJECT MANAGER
DAING MOHD HAFIZI
012-317 4400

SITE SUPERVISOR
MOHAMAD HAIRRY BIN
HASHIM
011-1066 5395

CARPENTE
BLACKSMITH CONCRETOR GENERAL WORKER
R
SITE INFORMATION
CLIENT : JABATAN KERJA RAYA MALAYSIA (JKR)
MAIN CONTRACTOR : BBS ENGINEERING SDN BHD

CONTRACT SUMP : RM 1,490,770.50

COMMENCEMENT DATE : 17 FEBRUARY 2025

COMPLETION DATE : 16 FEBRUARY 2026

CONSTRUCTION PERIOD : 52 WEEKS


SITE LOCATION
The site is located near the school field
about 23.4km from Kuala Lumpur. The
site can be accessed via Lebuhraya
Sungai Besi to MRR2.

Location Slope Failure


SK Pusat Bandar
Puchong

Coordinate :
3°02'92.4''N
101°62'89.5''E
SITE LOCATION

View from entrance at


school gate
Technical Issues observed at site:
• Visible cracks and patches on the road
surface
• Presence of damp patches and discolored
SITE LOCATION
SITE LOCATION

No drainage system at
the toe slope
METHOD STATEMENT
01 02 03

Site Survey & Temporary Access Mob & Demob


Setting Out

04 05 06

Site Clearance Soil Nailing Netting & Hydroseed


METHOD STATEMENT
07 08 09

Gabion Drainage Fencing


MATERIAL APPROVAL
• Reinforcement - Tensile Test
• Concrete – Design Mix Test
• Netting – JKR standard

INSPECTION
TESTING
• Pull-out test
PULL-OUT TEST
SOIL NAILING
WORK PROGRAMME (CPM)