Ministry of Transport: URRAP-Training of Trainers For Contractors and Coordinators
Ministry of Transport: URRAP-Training of Trainers For Contractors and Coordinators
Project
Management
Framework
2
Outline
Leadershipand Human
Resource Management
3
Outline
Contemporary themes of
Construction planning
◦ Scheduling
◦ Resourcing
4
Introduction
The prevailing facts of the road
sector
◦ Cost overrun
◦ Time overrun
◦ Quality reduction
5
Introduction
6
Introduction
7
Introduction
Inefficiencies
and ineffectiveness are part
in day today activity in the construction
sites
◦ weak site organization;
◦ Improper construction method;
◦ Work discontinuity;
◦ Rework: 10-15% contract value;
◦ Improper resource allocation( Human, material,
equipment) and under-utilization;
9
Overview of the Construction
Industry
High work demand in the market… 100s of
thousands Kms
Relay on importation
10
Overview of the Construction
Industry
11
Overview of the Construction
Industry
12
What is a project ?
A project is a
temporary endeavour
undertaken to create a
unique product,
service, or result.
(Source: Source: Project Management Institute ,PMIBoK)
13
What is Project Management ?
14
The Three Main Pillars of Project Management
15
.... and emphasise on people !
16
Triple Constraints of Projects
Project
Management
Time
Start End
Project
Management
!
Cost Scope What happens if the plan
was based on the wrong
assumptions
17
Another View of the Triple Constraints
Cost
Project
Budget
Contingency
Scope
Contingency Time
18
Why do we have projects ?
•Profitability
•Market share
•Competitive advantage
Business Goals
Projects Outcomes
Outputs Benefits
19
Projects Take up
Investment
The Firm: An organization that bring
together different factors of production such
as labor, land and capital to produce a
product or services which it hoped can be sold
for a profit
Firm
Entrepreneurs: Profits are a rewards of the
Entrepreneurs to take risks
Workers
20
Projects Take up
Investment
Normal profit : minimum level of reward to
keep/attract the entrepreneur in the particular economic
activity
Return on
Investme Investment
nt
Project duration
Start End
Goal = Finish As Soon As
Possible
Goal of the firm: Profit maximization is a
target
23
Project Management Framework
Project Project
Procureme Integratio
nt n
Managem Managem
ent ent
Project Project
Risk Time
Managem Managem
ent ent
Project Scope
Management
Project Project
Communicati Cost
on Managem
Management ent
Project
Project
Human
Quality
Resource
Manageme
Managem
nt
ent
24
Project Management Framework– Construction Extension
Slide 25
Project Scope Management
26
Project Manager
27
The Role of Project
Manager
The planning and coordination of a
project from inception to completion
on behalf of a client, to deliver the
client's objectives in terms of
Function, Time and Cost
28
Project Manager’s Responsibilities
Liaison with the client/sponsor
Develop and maintain project plans
Team leadership/Teambuilding ability
Cost effective work progress control
Cost control
Planning and technical decision
making
Quality and safety management
Business and administrative aspects
29
Higher Order Objectives
Complete all projects efficiently &
profitably
31
Managing Clients
Agree project objectives –
deliverables
Initial start up meeting
Interim reporting & reviews
Problem resolution
Manage the relationship
Under promise & over deliver
Always negotiate
32
Establish Client's objectives +
priorities
Business aims
Project aims + scope
Priorities - quality, time, cost
Timescales
Understand uncertainty + risks
33
Design an Organisation
Structure
participants
relationships
decision points, key +
operational reporting
integrating + coordinating
34
Common forms of
structure
Functional
Product based
Geographical
Divisionalised
Matrix
1 Functional
2 Divisional
3 Matrix
4 Teams
Selection + appointment of
project team
40
Develop brief for project
team
translate client's objectives
state in terms of needs +
outcomes
alternatives + evaluation
clarity + communication
41
Uncomfortable Facts
Leftalone people will tend
toward;
◦ First come – first served
◦ Enjoyable / familiar tasks first
◦ Easy rather than difficult tasks
◦ Simple vs complex tasks
◦ Gain easy wins –short term rewards
◦ Not favour releasing key resources /
people
◦ Provide the answer you want to hear
42
Establish Information and
Communication Structure
Measurement of data +
presentation
Communication channels
Meetings
Reporting mechanism
43
Facilitate the Decision
Making
What?
By whom?
When?
At what Cost?
44
Question – in groups
45
Projects – Direction Finder
46
P. O. L .C. MODEL
Setting standards and Establishing objectives &
assessing success in planning work
achieving objectives
PLANNING
CONTROLLING ORGANISING
LEADING
Influencing and motivating Organising people,
team members in doing the materials and scheduling
work
Leadership involves:
ENVIRONMENT MOTIVATORS
Working conditions Recognition
Interpersonal relations Responsibility
Job Security
Achievement
Salary
Advancement
Status
Work itself
Policy
Growth
Empowered Individuals:
Take risks
Gain knowledge, and
Develop new skills
Leadership – The 4 Basic Building
Blocks
Accountability
Trust
Communication
Goal setting
Communication
Takes time
Involves conscious effort
Requires a structure
Team Communications
Could include:
memos
minutes
circulars
notices
meetings
Why do we have meetings?
Exchange Information
Discussion on important issues
Make Decision
Team Building
… Management
Planning Meetings:
. Date
Advantages:
• Builds trust
• More people can do more things
• Staff are more involved and committed
• Staff grow and develop
• Skills and knowledge of staff are used more
fully
• Individual performance can be measured
• Opportunity for recognition
• The manager has time for managing
Delegation
Barriers:
• I don’t have time
• I don’t know how
• I don’t know to whom I should delegate
• It’s easier to do it myself
• I don’t want to lose control
• My staff lack experience and competence
• My team members resist responsibility
• My staff are not smart enough
• My staff cannot be trusted to work on their own
Delegation
Principles
1. Delegate the whole task to one person
2. Select the right person
3. Specify the required result
4. Delegate the responsibility and authority
5. Check for understanding
6. Set a date to review progress
7. Maintain open lines of communication
8. Don’t take the project back
9. Evaluate and recognise good performance
Benefits of Effective Work Assignment
The process:
Includes:
• Performance Measures
• Performance Standards
• Performance Monitoring
2. System improvements
3. Coaching
6. Discipline
7. Evaluation
Elements of effective feedback
• Be specific
• Be honest
• Maintain self-esteem
71
The project ‘moodograph’
Scale of
enthusiasm
Handover
New Project
Project Timescale
72
Contemporary Themes of
Planning
Construction is Complex system
◦ Uncertainty
◦ Interdependency of operations
Sequencing of activities
Resource
Construction a Chaotic system:
◦ dynamic
◦ non uniform environment
73
Contemporary Themes of
Planning
75
Contemporary Themes of
Planning
Planning in management concept
◦ Avoidance of Sub-optimization
76
Contemporary Themes of
Planning
Planning in Construction
77
Effective Planning
Contributes...
a disciplined approach
a crucial communication aid
identification of project risks
preparation of risk mitigation
measures
formulation of contingency plans
fundamental project progress
monitoring
anticipation of project delivery issues
evaluation of remedial options
confirmation of achievements
78
Planning in Construction
A multi-staged process
performed by different people at
different stages for various
purpose
79
Planning in Construction
80
Planning View
schedule
project planning
view view
External Conditions
Preceding Activity
Activities
Space
Safe environment
Crew Equipment
82
Preconditions and Stability
Condition Reliability
Reliability Reliability
? 83.3% 95%
Preceding task 83.3% 98%
ROW cleared site 83.3% 96%
Equipment 83.3% 96%
Crew 83.3% 95%
Information 83.3% 100%
Materials 83.3% 95%
External conditions
<30% 70-80%
Overall
Reliability
83
Planning Process
84
Planning Encompasses...
schedule management
◦ recording planned activities and
dependencies
◦ testing plan logic
◦ highlighting critical activities
◦ recording activity progress
achievement projections
resource management
costs management
exploring what-if scenarios
85
S.M.A.R.T. goals
develop a series of goals to define a logical
sequence of achievements that,
cumulatively, build towards successfully
delivering the required project outcomes
86
Preparation of Plan
Major Steps required to develop a schedule
◦ Establish work breakdown structure (WBS)
◦ Sequencing of activities by analysing their
interrelations / interdependencies
◦ Allocation of resources to activities
◦ deciding time required for each activity
◦ developing the overall time schedule of
the project
NB: The above are not a onetime done
activity, need iterative process till optimal
solution is obtained.
87
Preparation of Plan
Resources planning:
◦ Determining the labour requirement
◦ Determining the material requirement
◦ Determining the number of equipment
required
◦ Determining the cash requirement
◦ Schedule the ordering of material,
equipment, recruitment of labour and
cash requirement together with the
provision of lead-time for all.
88
Preparation of Plans ….Major
components
B) Scheduling
Critical Path Method
Critical Chain Method
Location based/Repetitive
Scheduling
The Last planner concept
◦ Site specific
◦ Safe
◦ Reasonably considered social and
environment issues
91
Preparation of Plans
Bar chart
◦Easiest to understand
◦Most commonly used
◦List of activities shown as
“bar” plotted against time
scale (start, duration, Finish)
94
Preparation of Plan
Duration
Activity (days)
A 4
B 8
C 4
D 4
E 2
F 2
G 2
0 4 8 12 16 20 24
Duration (days)
EXAMPLE OF SIMPLE BAR CHART
95
Preparation of Plan
Advantages of bar charts
◦ Very simple presentation, easily
understood
◦ Good form of communication to non-
technical personnel
◦ Requires little training to use
◦ Suitable to be used for planning
time-phased resources (labor,
material, equipment, budget)
96
Preparation of Plan
Disadvantage of bar charts
◦ Can not show interdependencies among the
various activities
◦ Critical activities that need attention and
floats for non‑critical activities are not shown
(complex projects).
◦ Change in schedule requires redrawing of
the chart.
Despite its disadvantages the bar chart
is the most commonly used tool for
planning and control
97
Preparation of Plan
Network method
◦ Suitable for large complex projects having
many interdependent activities
Two commonly used network methods are
◦ Arrow‑diagram
◦ Precedence‑diagram
Main difference
◦ Arrow diagram represents activities on arrows
and the node represents the event at a time
◦ Precedence diagram shows activities on nodes
and the logical sequence of activities with
arrows
98
Construction Planning(Cont.)
1
ACT.1 ACT. 2 ACT.3
2 3 4
Act. 1
Act. 2 Act. 4 Act. 5
2week
5weeks 3weeks 6weeks
s
SS 2 weeks Act. 3
5weeks
99
Preparation of Plan
Steps in developing a network
diagram
◦ Listing all project activities using WBS
◦ Prepare an arrow‑diagram following
the logical sequence of activities
◦ Estimate activity duration
◦ Calculate the time for events and
determine floats and critical‑path
(time analysis using forward and
backward pass)
100
Critical Path Method: Scheduling
concept
Predecessor
• controls the start or finish of another
activity
Successor
• depends on the start or finish of
another activity
10
1
Activity relationships
Finish to Start (FS)
when A finishes then B can start
(this is the default relationship type)
A B
Predecessor Successor
10
2
Activity Relationships
10
3
Activity Relationships
Finish to Finish A
(FF) Predecessor
when A finishes B
then B can
Successor
finish
10
4
Activity Relationships
10
5
Activity Relationships
Finish to Start with Lag/lead
A B
....days
Predecesso Successor
r
B
Excavation and pipe laying
...days
successor
10
7
Scheduling concept
Forward Pass
calculates the early dates for each
activity
early dates are the earliest times an
activity can start and finish once its
predecessors have been completed
the calculation begins with the
activities without predecessors
11 25
1 10
10
9
Scheduling concept
Backward Pass
• calculates the late dates for each
activity
11 25
1 10
11
1
Float- definitions
Float generally is the amount of time an
activity can slip from its early start without
delaying the project
11
3
Preparation of Plan
Duration
Activity (days)
A 4
B 8
C 4
D 4 FLOAT
E 2
F 2
G 2
0 4 8 12 16 20 24
Duration (days)
ACTIVITIES A, B, C, E, F and G are critical
ACTIVITY D is non critical and has a float of 8 days
114
Preparation of Plan
116
Preparation of Plan
Time space diagram
◦ Suitable for linear construction projects like highways,
cannels, tunnels, sewer lines
km Cut & Fill Protection Works
100 Legend: Drainage
Sub-base
80 Base course
AC Bridge B
60
Culvert 2
40
Culvert 1
20
Bridge A
0 5 10 15 20 25 30
Time (Months)
TIME CHAINAGE DIAGRAM
117
Preparation of Plan
118
Preparation of Plan
119
Plan Information Diffusion
Plans have to be communicated
clearly and ‘no doubt should be left as
to what is to be done and when’.
.
12
1
Cost Flow Forecasting ….
Cont
Helps to :
To provide timely warnings…to take
corrective actions
They also allow you to analyze whether
a project will be sufficiently profitable
to justify the effort put into it.
Be useful for analyzing owners’
personal finances. This is useful when
making difficult financial decisions.
12
2
Cost Flow Forecasting …. Cont
The Process of Cash flow forecast is
similar to the process of
production(Single Project)
Working
capital
Operatio
Cash ns Revenu
( break into
operation manageable
e
size)
expense
Operation
Income 12
3
Cost Flow Forecasting …. Cont
The basic steps in cash flow forecasting
are:
Depreciation
◦ Helps to recover fixed capital early
12
7
Implementation of Plan and
Control
12
8
Implementation of Plans and
Control
• Project performance measurement
should evaluate
◦ Productivity(efficiency)
◦ Overall satisfaction
12
9
Implementation of Plan and
Control
◦ The performance monitoring
system:
Timeliness
Standard,
Honest and
Clearly showing divergence
In
such ever changing and dynamic
environment plans age early:
132
Implementation of Plans and
Control
Earn Value Management has become an
industry standard way to Performance
management and forecast
measure the progress of a projects if
accomplished is as planned in terms
of Cost & Schedule of the work
performed
135
Earn Value Management
• Predicting future cash flow
Simple extrapolation
13
8
Thank you
13
9