0% found this document useful (0 votes)
4 views23 pages

11 - Pert-Cpm Gantt Chart

The document discusses project scheduling techniques, focusing on CPM, PERT, and Gantt charts. It emphasizes the importance of logical dependencies in constructing project networks and provides examples of activity sequencing and precedence relationships. Additionally, it outlines the process for calculating earliest start and finish times for activities within a project network.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
4 views23 pages

11 - Pert-Cpm Gantt Chart

The document discusses project scheduling techniques, focusing on CPM, PERT, and Gantt charts. It emphasizes the importance of logical dependencies in constructing project networks and provides examples of activity sequencing and precedence relationships. Additionally, it outlines the process for calculating earliest start and finish times for activities within a project network.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 23

Project Scheduling

Basic CPM/PERT & Gant-


Chart
MS321-Manajemen Industri
& Proyek
INTRODUCTION
 Schedule converts action plan into
operating time table
 Basis for monitoring and controlling project
 Scheduling more important in projects than
in production, because unique nature
 Sometimes customer specified/approved
requirement-e.g: JKR projects
 Based on Work Breakdown Structure (WBS)
NETWORK TECHNIQUES
PERT CPM

• Program Evaluation  Critical Path Method


and Review Technique
 Developed by El Dupont for
Chemical Plant Shutdown
• developed by the US Project- about
Navy with Booz  same time as PERT
Hamilton Lockheed
• on the Polaris
Missile/Submarine
program 1958
Both use same calculations, almost similar
Main difference is probabilistic and deterministic in time
estimation
Gantt Chart also used in scheduling
NETWORK
 Graphical portrayal of activities and
event
 Shows dependency relationships
between tasks/activities in a project
 Clearly shows tasks that must
precede (precedence) or follow
(succeeding) other tasks in a logical
manner
 Clear representation of plan – a
powerful tool for planning and
Example of Simple Network –
Survey
Example of Network –
More Complex
DEFINITION OF TERMS IN A
NETWORK
 Activity : any portions of project (tasks) which
required by project, uses up resource and consumes
time – may involve labor, paper work, contractual
negotiations, machinery operations Activity on
Arrow (AOA) showed as arrow, AON – Activity on
Node
 Event : beginning or ending points of one or more
activities, instantaneous point in time, also called
‘nodes’
 Network : Combination of all project activities and
the events
Emphasis on Logic in Network
Construction
 Construction of network should be based on
logical or technical dependencies among
activities
 Example - before activity ‘Approve Drawing’ can
be started the activity ‘Prepare Drawing’ must be
completed
 Common error – build network on the basis of
time logic (a feeling for proper sequence) see
example below

WRONG !!! CORRECT 


Example 1- A simple network
 Consider the list of four activities for making a simple
product:

 Activity Description Immediate


predecessors
A Buy Plastic Body -
B Design Component -
C Make Component B
D Assemble product A,C

 Immediate predecessors for a particular activity are


the activities that, when completed, enable the start
of the activity in question.
Sequence of activities
 Can start work on activities A and B
anytime, since neither of these activities
depends upon the completion of prior
activities.
 Activity C cannot be started until activity
B has been completed
 Activity D cannot be started until both
activities A and C have been completed.
 The graphical representation (next slide)
is referred to as the PERT/CPM network
Network of Four Activities
Example 2
 Develop the network for a project with following
activities and immediate predecessors:
Activity
Immediate
predecessors
A -
B -
C B
D A, C
E C
F C
G D,E,F
Try to do for the first five (A,B,C,D,E) activities
Network of first five activities

A D
1 3 4

E
B

C 5

2
We need to
introduce a
dummy activity
Network of Seven Activities
1 A 3 D 4 G
7
dummy E
B
C 5 F
2 6

 Note how the network correctly identifies D, E, and F as the immediate


predecessors for activity G.

 Dummy activities is used to identify precedence relationships correctly


and to eliminate possible confusion of two or more activities having
the same starting and ending nodes

 Dummy activities have no resources (time, labor, machinery, etc) –


purpose is to PRESERVE LOGIC of the network
EXAMPLES OF THE USE OF
DUMMYACTIVITY
Network concurrent activities
a
a 2

1 2 1 Dummy

b 3
b
WRONG!!! RIGHT 

Activity c not WRONG !


required for e
a
a e
d
1
b 1 b
e
d
c
2
c
WRONG
RIGHT
!!!

RIGHT 
 WRONG!!!  RIGHT!!!

 a  d  a  d
 1  1

 b  e  b
 2  2  4  e

 c  f  c  f
 3  3

 a precedes d.
 a and b precede e,
 b and c precede f (a does not precede f)
Scheduling with activity
time
Activity Immediate Completion
predecessors Time
(week)
A - 5
B - 6
C A 4
D A 3
E A 1
F E 4
G D,F 14
H B,C 12
I G,H 2
Total …… 51
 This information indicates that the total time required
to complete activities is 51 weeks. However, we can
see from the network that several of the activities can
be conducted simultaneously (A and B, for example).
Earliest start & earliest finish time
 We are interested in the longest path through the
network, i.e., the critical path.

 Starting at the network’s origin (node 1) and using a


starting time of 0, we compute an earliest start (ES)
and earliest finish (EF) time for each activity in the
network.

 The expression EF = ES + t can be used to find the


earliest finish time for a given activity.
 For example, for activity A, ES = 0 and t = 5; thus
the earliest finish time for activity A is
 EF = 0 + 5 = 5
Arc with ES & EF time
EF = earliest finish time

ES = earliest start time

Activity

2
,5]
A [0
5
1
t = expected activity
time
Network with ES & EF time
D[5,8] 5
2 3
E[ 10]

G[ 14
] 5,
6 [ 6,
5

10
F 4
0,

1 7

,24
A[

26]
C[5,9]

4 4 ,
I[2
4
]

]
5

2
1 6
, 21]
B[ H[ 9
0,6 12
6 ]
3
 Earliest start time rule:
 The earliest start time for an activity leaving a
particular node is equal to the largest of the earliest
finish times for all activities entering the node.
Tugas : Buatlah Network dari Tabel
berikut
 Dikumpulkan _____,
__ Desember 2014
 Sebelum jam 12.00
 Sebagai kuliah
pengganti
KLONE COMPUTERS, INC
 Precedence Relationships Chart
Immediate Estimated
Activity Predecessor Completion Time
A None 90
B A 15
C B 5
D G 20
E D 21
F A 25
G C,F 14
H D 28
I A 30
J D,I 45
Terima kasih atas
perhatiannya

You might also like