(LEC-2)
(LEC-2)
name of
Allah, the
Most
Gracious
the Most
Merciful
2
CONSTRUCTION
ESTIMATES
Preparing Construction Estimates
There are three further factors that have a significant influence on how an
estimator goes about preparing a construction estimate:
3. The type of project to be built
4. The delivery system used to move from the developer’s project idea to a
finished structure
5. The nature of the contract(s) used in the delivery system
3
4
Project
delivery
systems
5
Traditional (Design- Bid- Build) Delivery
6
7
Construction Management Delivery
• This form of organization seeks to facilitate overlap between
project stages, often referred to as fast tracking, to allow
earlier completion of the project.
• Fast tracking is achieved by dividing the project into several
phases. This approach allows construction work to begin
after the design and bid for phase one only are complete.
• Phase one may consist of nothing more than demolition and
site preparation that require very little time for design.
• While the work on this first phase proceeds, the design
continues for phase two, which may be the building
foundation system
• With this organization structure, the construction manager
assumes the responsibility for overall control and
coordination of the construction work that was provided by
the general contractor under the traditional organization 8
9
Design-Build Delivery
10
11
Contracts
A contract is a legally binding document that recognizes and
governs the rights and duties of the parties to the agreement. A
contract is legally enforceable because it meets the requirements
and approval of the law.
12
Contract System
1. Single contract
13
Contract System
2. Separate contracts
15
Lump-Sum contracts
16
Unit Price Contract or Bill of
Quantities Contract
• In a unit price contract, the work to be
performed is broken into various parts,
usually by construction trade, and a fixed
price is established for each unit of work.
For example, painting is typically done on a
square foot basis. Unit price contracts are
seldom used for an entire major
construction project, but they are frequently
used for agreements with sub-contractors.
17
Schedule of Rates Contract
19
Cost-Plus-Fee Contracts
20
Build , Operate and Transfer ( BOT )
Contract
• This type of contract is sometimes known as “ Build ,
Own , Operate and Transfer ( BOOT ) contract ” . The
client will layout a series of required end products with
specification , terms and conditions ; and the contractor
must finance , design , construct , maintain , manage
and operate the finished work for an agreed period say
10 years , 20 years or so.
• During this agreed period , the contractor has the
temporary ownership of these finished works and can
charge the end users for recovery of its investment
together with the expected profit . However, when the
agreed period expires , the finished work will have to be
transferred back to the client in specified conditions .
21
22