Or-Chpter 5 Tutorial (RVU) (1)
Or-Chpter 5 Tutorial (RVU) (1)
An activity is denoted by letters A, B, C, etc. which is marked often above the
arrow and estimated time to accomplish the activity is written below the arrow.
4. Dummy activity: An imaginary activity that does not
consume any time and resources is known as a Dummy
activity.
Dummy activities are denoted by the Dotted line.
The main function of dummy activity is representing a
connection between events to maintain the sequence
logically
When two activities start at the same event and end at
the same event, they should be shown by means of a
dummy activity
Types of activities in network
a). Predecessor activity: Activities that must be completed before starting
another activity
c). Critical activities: Are those activities which if they consume more than their
estimated time, the project will be delayed
4. Critical path (CP): Critical path is the longest path in the network diagram
which is formed by critical activities.
LF - Latest finish time: Latest time at which the activity can be completed without delaying
the project.
Example 1. Based on the following given activities, predecessors and time in
weeks
a). Draw net work diagram b). Identify critical path c). Identify critical activities
d). Compute minimum completion time of the project e). Compute ES, EF for each
activity f). Compute LS, LF and Slack time for each activity
1.A-D-G-I=5+3+14+2=24
2. A-E-F-G-I=5+1+4+14+2=26………..critical path (Represented by tick arrow)
3. A-C-H-I=5+4+12+2=23
4. B-H-I=6+12+2=20
c). Identify critical activities:
Activities on critical path (A, E, F, G and I are critical activities)
d). Minimum time to complete the project=critical path time=26 weeks
e) Compute ES, and EF for each activity
ES = Largest EF of immediate predecessors
EF= ES+t
f). LS and LF time for each activity
To find LS and LF time for each activity, we need a backward pass
calculation.
LS=LS of its successor minus time estimate of the activity
LF=LS of its successor activity
E 5 5 6 6 0 Yes
F 6 6 10 10 0 Yes
G 10 10 24 24 0 Yes
H 9 12 21 24 3 No
I 24 24 26 26 0 Yes
5.4.2. PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT)
In the case of CPM activity times can be estimated with relative certainty, confidence
For many situations this is not possible, e.g Research and development, new products, complex
projects etc.
3 different time estimates
Optimistic time estimate O……………consider ideal condition
Most likely time estimate M and ………mostly nearest to actual requirement
Pessimistic time estimate P………..if condition goes wrong
Expected time estimate for each activity is calculated as: (Te) = (O + 4m + P) /6
Now the probability of completion of project in that given time (t) of 26 days,
can be calculate by below formula,