Creating A Communicatins Planv1-0
Creating A Communicatins Planv1-0
MANAGEMENT
Information Technology Project Management
Magister Sistem Informasi
Universitas Komputer Indonesia
SOURCE:
PINTO, J.K. 2010, 2ND. ED.
PROJECT
• Promotion Risk
• Market Risk, volume
• Market Risk, price
• Political Risks
• Technical Risks
• Financing Risks
• Environmental Risks
• Cost Estimate Risk (completion risk)
• Schedule Risk (delay risk)
• Operating Risk
• Organizational Risk
• Integration Risk
• Acts of God
ANALYSIS OF PROBABILITY & CONSEQUENCES
Consequences
Low Medium High
D
Likelihood
B
Medium
high
C A
Low
DETERMINING LIKELY RISKS & CONSEQUENCES
Probability of Failure (Pf)
SCORE MATURITY COMPLEXITY DEPENDENCY
Low (0.1) Existing software Simple design Not limited to existing system
Minor (0.3) Minor redesign Minor increase in Schedule or performance depend on existing
complexity system
Moderate (0.5) Major change Moderate increase Moderate risk to schedule or performance
Significant (0.7) Tech. available but Significant increase Schedule or performance depend on new
complex design system or process. Significant cost or risk
Major (0.9) State of art, some Extremely complex Schedule or performance depend on new
research complete system or process. Very high risk.
Low (0.1) Budget estimate not Negligible/ Minimal or no reliability Minimal or no performance
exceeded no impact consequences consequences
Minor Cost estimate exceeds Minor slip in Small reduction in Small reduction in system
(0.3) budget < 5% schedule reliability performance
Moderate Cost estimate exceeds Small slip in Some reduction in Some reduction in system
(0.5) budget < 15% schedule reliability performance
Significant Cost estimate exceeds Slips excess 1 Significant degradation in Significant degradation in
(0.7) budget < 30% month reliability system performance
Major Cost estimate exceeds Large Reliability goals cannot be Performance goals cannot
(0.9) budget < 50% schedule slip achieved under current plan be achieved
CALCULATING A PROJECT RISK FACTOR
• Use the project team consensus to determine the scores for each
Probability of Failure Category: Maturity (Pm), Complexity (Pc),
Dependency (Pd).
• Calculate Pf by adding the three categories and dividing by 3:
Pf=(Pm+Pc+Pd)/3.
• Determine the scores for each Consequences of Failure Category: Cost
(Cc), Schedule (Cs), Reliability (Cr), Performance (Cp).
• Calculate Cf by adding the three categories and dividing by 4:
Cf=(Cc+Cs+Cr+Cp)/4.
• Calculate Overall Risk Factor for the project by using the formula:
RF=Pf+Cf-(Pf)(Cf)
• Rule of Thumb: Low risk Rf < 0.3
Medium risk Rf = 0.3 to 0.7
High risk Rf > 0.7
QUANTITATIVE RISK ASESSMENT
• Assume your project team has decided upon
the following risk values:
• Pm = .1, Pc = .5, Pd = .9
• Cc = .7, Cs = .5, Cr = .3, Cp = .1
• Determine the overall Project Risk using
qualitative method
RISK MITIGATION STRATEGIES
• Accept Risk
• Minimize Risk
• Share Risk
• Transfer Risk
• Use of Contingency Reserves
CONTROL AND DOCUMENTATION
• Control and documentation methods help
manager classify and codify the various risks
the firm faces, its responses to these risks, and
the outcome of its response strategies.
• Control document has to coherently identify
the key information: what, who, when, why,
how.
PROJECT RISK ANALISYS & MANAGEMENT
(The European Association for Project Management)
• Define
• Focus
• Identify
• Structure
• Clarify Ownership of Risk
• Estimate
• Evaluate
• Plan
• Manage