3341 - GUP - Presentation
3341 - GUP - Presentation
Project Name /Job # 3341 : Modification/Renovation of Technical Building in GUP at Ruwais Refinery
Client : M/s. TAKREER
Contract Duration : 12Month
Contract Commencement Date : 07-May-2013
Contract Completion Date : 02-MAy-2014
Actual Commencement Date : 07- May-2013
Actual Completion Date : 02- May- 2014
Initial Budget as
Expenses as Cost to Cost at
SI. No. Cost Head Workout as per site Remarks
of AUG 2013 Complete completion
per Tender condition
A. DIRECT WORKS
1 Civil
781,677.00 781,677.00 147,460.52 610,116.40 757,576.92
2 Electrical
3 HVAC
Total (A)
B INDIRECT WORKS
3 HVAC
Total (B)
OTHER COST
3 HVAC
Total (C)
GRAND TOTAL
(A+B+C) 937,925.00 937,925.00 180,938.44 724,444.48 905,382.92 -
PROFIT
CONTRACT PRICE
BREAKDOWN OF BUDGET AND COST SUMMARY FOR CIVIL WORKS - AS OF AUGUST -2013
B INDIRECT WORKS
6 Preliminaries 2,750.00
2,750.00 582.38 582.38 2,167.62 2,750.00
Tools, Periodic
7 Consumables ,Maintenance & 0.00
- - -
Utilities 0.00 0.00
Total (B) 2,750.00 2,750.00
582.38 - 582.38 2,167.62 2,750.00
OTHER COST
8 Site Staff 151,978.00
151,978.00 16,132.00 15,794.00 31,926.00 111,610.00 143,536.00
9 Finanace Charges 1,520.00
1,520.00 969.54 969.54 550.46 1,520.00
Total (C)
153,498.00 153,498.00 17,101.54 15,794.00 32,895.54 112,160.46 145,056.00
GRAND TOTAL (A+B+C)
937,925.00 937,925.00 131,474.44 49,464.00 180,938.44 724,444.48 905,382.92
PROFIT
104,214.00 104,214.00
CONTRACT PRICE
BREAKDOWN OF BUDGET AND COST SUMMARY FOR ELECTRICAL WORKS - AS OF
_____________2013
Expenses as
Initial Budget as
SI. of Cost to Cost at Cost at
Cost Head Workout as per site
No. ___________2 Complete completion completion
per Tender condition
013
A. DIRECT WORKS
1 Labour :
a. Basic Salary
b. Overtime
c. LRC
2 Materials
Formwork, Plant &
3
Machinery
4 Sub-contract
5 Contingency
Total (A)
B INDIRECT WORKS
6 Preliminaries
Tools, Periodic
7 Consumables, Maintenance
& Utilities
Total (B)
OTHER COST
8 Staff salary & SRC
9 Finance charges
Total (C)
GRAND TOTAL (A+B+C)
PROFIT
CONTRACT PRICE
VARIATION
BREAKDOWN OF BUDGET AND COST SUMMARY FOR HVAC WORKS - AS OF _____________2013
Expenses as
Initial Budget as
SI. of Cost to Cost at Cost at
Cost Head Workout as per site
No. ___________20 Complete completion completion
per Tender condition
13
A. DIRECT WORKS
1 Labour :
a. Basic Salary
b. Overtime
c. LRC
2 Materials
Formwork, Plant &
3
Machinery
4 Sub-contract
5 Contingency
Total (A)
B INDIRECT WORKS
6 Preliminaries
Tools, Periodic
7 Consumables, Maintenance
& Utilities
Total (B)
OTHER COST
8 Staff salary & SRC
9 Finance charges
Total (C)
GRAND TOTAL (A+B+C)
PROFIT
CONTRACT PRICE
VARIATION
REVISED CONTRACT
PRICE
PROGRESS OF WORK AS OF 20-SEP -2013
Description
No. Over all Construction Over all Construction Over all Construction
2 Civil
3 Electrical
4 HVAC
100.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
0.00%
30-Apr-13
6-May-13
12-May-13
18-May-13
24-May-13
30-May-13
5-Jun-13
11-Jun-13
17-Jun-13
23-Jun-13
PLANNED
29-Jun-13
5-Jul-13
11-Jul-13
17-Jul-13
23-Jul-13 ACTUAL PROGRESS :
29-Jul-13
4-Aug-13
10-Aug-13
16-Aug-13
ACTUAL
22-Aug-13
28-Aug-13
38.13%
PLANNED PROGRESSS: 35.68%
3-Sep-13
9-Sep-13
15-Sep-13
21-Sep-13
27-Sep-13
3-Oct-13
9-Oct-13
15-Oct-13
21-Oct-13
27-Oct-13
2-Nov-13
8-Nov-13
14-Nov-13
20-Nov-13
26-Nov-13
2-Dec-13
8-Dec-13
14-Dec-13
OVER ALL - Progress'S'Curve
20-Dec-13
26-Dec-13
1-Jan-14
7-Jan-14
13-Jan-14
19-Jan-14
25-Jan-14
31-Jan-14
6-Feb-14
12-Feb-14
18-Feb-14
24-Feb-14
2-Mar-14
8-Mar-14
14-Mar-14
20-Mar-14
26-Mar-14
1-Apr-14
7-Apr-14
13-Apr-14
19-Apr-14
25-Apr-14
1-May-14
7-May-14
100.00%
0.00%
10.00%
20.00%
30.00%
40.00%
50.00%
60.00%
70.00%
80.00%
90.00%
30-Apr-13
8-May-13
16-May-13
24-May-13
1-Jun-13
9-Jun-13
PLANNED
17-Jun-13
PROGRESS
25-Jun-13
3-Jul-13
11-Jul-13
ACTUAL PROGRESS
28-Aug-13
25.98 %
5-Sep-13
13-Sep-13
21-Sep-13
29-Sep-13
7-Oct-13
15-Oct-13
23-Oct-13
31-Oct-13
8-Nov-13
16-Nov-13
24-Nov-13
2-Dec-13
10-Dec-13
18-Dec-13
26-Dec-13
3-Jan-14
Construction - Progress'S'Curve
11-Jan-14
19-Jan-14
27-Jan-14
4-Feb-14
12-Feb-14
20-Feb-14
28-Feb-14
8-Mar-14
16-Mar-14
24-Mar-14
1-Apr-14
9-Apr-14
17-Apr-14
25-Apr-14
3-May-14
SUBMITTAL STATUS AS OF ____AUG____-2013
Sl.
Description
No.
Total Planned Submitted Approved Balance to be
submitted
1
Materials (Elect.) Material (HVAC) 8 8 8 0
Sub-contractors
Sub-contractors (Civil) 2 2 2 0
(Civil)
Sub-contractors
2 Sub-contractors (Elect) 0 0 0 0
(Elect)
Sub-contractors
Sub-contractors (HVAC) 0 0 0 0
(HVAC)
Shop Drawings
Shop Drawings (Civil) 22 22 22 0
(Civil)
3
Shop Drawings
Elect 8 8 6 0
(Electrical)
Shop Drawings (HVAC) HVAC 3 3 1 2
MANPOWER STATUS (STAFF ) AS OF _AUG_ -13
1 Project Manager
2 Construction Manager
3 Sr.Project Engineer 0.25 0.25
4 Planning Engineer
5 Electrical Engineer
6 HVAC Engineer
7 Plumbing Engineer
8 Quantity Surveyor
9 QA/QC Engineer
10 Draftsman
11 Site Engineer 0 0
12 Electrical Supervisor
13 HVAC Supervisor
14 Foreman 1 1
16 Safety Engineer
17 Safety Officer
18 Store keeper
19 Driver 1 1
A B D= A – B
Job Performer / Charge hand/
1 2 2
Foreman
2 Mason 3 3
3 Carpenter 3 3
4 Steel Fixer 4 4
5 Scaffolder
6 Painter 1 1
7 Helper
8 Plumber
9 Muster
10 Electrical Manpower
11 HVAC Manpower
Total 13 13
Manpower Utilization
Sl. Category Total man-day's as per Total man-day's as per Actual man-day's Balance man- Balance
No. Tender workout revised workout as of date day's available as Man
of date Hours
CIVIL - Amount 107257 107119 48180 58939
1
CIVIL –Mandays 1021 1020 458 561 5610
2 Elect – Amount
Elect – Mandays
3 HVAC -Amount
HVAC - Mandays
VI. HSE / QUALITY AND OTHER ISSUES
1) HSE ISSUES
13+08 =21
a) 10 Min. Safety Talk
2) QUALITY ISSUE
a) Site diary implementation - Implemented.
b) Quality Suggestion
- -
received
c) Details of Audits
- -
conducted
d) NCRs status - -
e) Corrective and
- -
Preventive actions
f) Quality issues from client - -
3) OTHER ISSUES
3
-
HSE STATUS AS OF AUG-2013
Sl.
ITEM DESCRIPTION Up to Previous Month Current Month Cumulative as of date
No.
1 Near Miss raised 03 05 08
2 Suggestion raised 02 04 06
4 NCRs Status 00 00 00
Sl. Up to
ITEM Current Cumulative Issuance
Previous Issuance To Designation Reason for Issuance
No. DESCRIPTION Month as of date Date
Month
Mr.Vinodh -148191 Mason
Mr.sanker - 30155
Issuance of 50 Mason.
1 05 09 14 Mr. Ramasamy-43089 Near miss/ suggestion 31.08.2013
EMCOINS Mr. madasamy-107880.
Mason.
Mason
Total
2
AREAS OF CONCERN
Sl. Description
01 Work Station not yet finalized
2
IV. GUARANTEES / INSURANCE POLICIES
Present validity of
SL. Validity as per Submission to
Amount (AED) Amount (AED) Guarantee / Remarks
No contract client
Insurance
Performance
1. AED:178,544.00/- 14.05.2014 09.06.2013
Guarantee
Performance
Guarantee (for any
variation)
2. Insurance Policies
a) Workmen’s 31.12.2013
05.06.2013
compensation