Chapter-02 - Overview of Project Management
Chapter-02 - Overview of Project Management
CSC 307- System Analysis and Design Prepared by Dams G. L. & Kameel B. Chapter 2: Slide 2
Topics Overview
• What is a Project?
• What shapes a Project.
• Project Management Triangle
• System Analyst as a Project
Manager
• Responsibilities of a Project
Manager
• Activities of a Project Manager
• Tools for planning, Scheduling and
Monitoring
CSC 307- System Analysis and Design Prepared by Dams G. L. & Kameel B. Chapter 2: Slide 3
What is a Project?
• What is a Project?
CSC 307- System Analysis and Design Prepared by Dams G. L. & Kameel B. Chapter 2: Slide 6
What is a Project
Management Triangle?
CSC 307- System Analysis and Design Prepared by Dams G. L. & Kameel B. Chapter 2: Slide 9
What does a Project Manager
do?
• Step 1 – Create a Work Breakdown
Structure
CSC 307- System Analysis and Design Prepared by Dams G. L. & Kameel B. Chapter 2: Slide 10
Step 1 – Create a Work
Breakdown Structure
• Dividing the project into manageable
tasks
• WBS aids in making the project
manager to:
– Identify the tasks
– List the tasks
– Estimate duration of each task
CSC 307- System Analysis and Design Prepared by Dams G. L. & Kameel B. Chapter 2: Slide 11
Example of Work Breakdown
Structure
• Conducting a research that requires
using a questionnaire.
CSC 307- System Analysis and Design Prepared by Dams G. L. & Kameel B. Chapter 2: Slide 12
Step 2 – Identify Task Patterns
• WBS must clearly identify each task
and include an estimated duration.
CSC 307- System Analysis and Design Prepared by Dams G. L. & Kameel B. Chapter 2: Slide 14
Main Types Task Patterns.
1. Dependent tasks
– One task must be completed before
another starts
CSC 307- System Analysis and Design Prepared by Dams G. L. & Kameel B. Chapter 2: Slide 15
Step 3 – Calculate the Critical
Path?
• What is a Critical Path?
– A series of tasks which, if delayed, would
affect the completion date of the overall
project.
CSC 307- System Analysis and Design Prepared by Dams G. L. & Kameel B. Chapter 2: Slide 16
How do I Calculate a Critical
Path?
• Review task patterns, determine start and
finish dates, which will determine the critical
path.
– Tasks depend on each other and must be
performed in a sequence. The types of task
patterns could be:
• Dependent Tasks
– When tasks must be completed one after another
– Similar to relay race.
CSC 307- System Analysis and Design Prepared by Dams G. L. & Kameel B. Chapter 2: Slide 18
What is Gantt Chart?
• A graphical representation of a project that
shows each task as a horizontal bar whose
length is proportional to its time for
completion.
CSC 307- System Analysis and Design Prepared by Dams G. L. & Kameel B. Chapter 2: Slide 20
Examples of Gantt Chart
CSC 307- System Analysis and Design Prepared by Dams G. L. & Kameel B. Chapter 2: Slide 21
Examples of Gantt Chart
CSC 307- System Analysis and Design Prepared by Dams G. L. & Kameel B. Chapter 2: Slide 22
What is a PERT chart?
• Program Evaluation and Review
Technique (PERT)
– Provides a visual representation of a
project’s timeline and breaks down
individual tasks.
– Developed by the U.S. Navy to manage
complex projects
CSC 307- System Analysis and Design Prepared by Dams G. L. & Kameel B. Chapter 2: Slide 23
Example of PERT Chart
• In the PERT chart below. Task 1 is a dependent
task and has multiple successor task.
• Task 4 has multiple predecessor tasks.
• In this figure, the analyst has arranged the
tasks and entered task names, IDs and
durations
CSC 307- System Analysis and Design Prepared by Dams G. L. & Kameel B. Chapter 2: Slide 24
What is a CPM chart?
• Critical Path Method (CPM)
– Similar to PERT, developed by a private
industry
– Technique used for identifying tasks that
are necessary for project completion.
CSC 307- System Analysis and Design Prepared by Dams G. L. & Kameel B. Chapter 2: Slide 25
Example of CPM Chart
• In the CPM of 5 charts below, the
analyst has entered the start and finish
times.
CSC 307- System Analysis and Design Prepared by Dams G. L. & Kameel B. Chapter 2: Slide 28
Gantt Versus PERT
• Gantt
– offers a valuable snapshot view of the project
– Visually shows duration of tasks
– Visually shows time overlap between tasks
– Visually shows slack time
• PERT
– more useful for scheduling, monitoring and
controlling the actual work
– displays complex task patterns and relationships
– chart boxes can provide more detailed
information
– Visually shows dependencies between tasks
– Visually shows which tasks can be done in
CSC 307- Systemparallel
Analysis and Design Prepared by Dams G. L. & Kameel B. Chapter 2: Slide 29
Project Management Software
• Microsoft Project is a full-featured program
that holds the dominant share of the
market
• Gantt chart
– As you enter the tasks, the program
automatically performs the calculations, detects
the task patterns and creates a Gantt chart.
• Network diagram
– View is similar to a PERT chart
• Calendar view
– View similar to a PERT chart as an overlay on a
CSC 307- System Analysis and Design Prepared by Dams G. L. & Kameel B. Chapter 2: Slide 30
The Bottom Line
• The system analyst as a project managers
must be alert, technically competent and
highly resourceful.
CSC 307- System Analysis and Design Prepared by Dams G. L. & Kameel B. Chapter 2: Slide 31
Q&A
CSC 307- System Analysis and Design Prepared by Dams G. L. & Kameel B. Chapter 2: Slide 32