LMS Week 7 Lecture 18102024 050850pm
LMS Week 7 Lecture 18102024 050850pm
PERFORMANCE
DOMAIN
Week 7
Initiating Planning
Determine development approach, lifecycle & how to plan each KA
Define and prioritize requirements
Create scope statement
Assess what to purchase and create procurement documents
2
Determine planning team
Create WBS and WBS dictionary
Create, activity list and network diagram
Estimate resource requirements
Estimate activity duration and costs
Determine critical path
Develop schedule and budget
Determine quality standards, procedures and metrics
Determine team charter and all roles & responsibilities (for product & project work)
Plan communication and SH engagement
Perform risk identification, qualitative & quantitative risk analysis & response planning
Go back – Iterations
Finalize procurement strategy and documents
Create change & configuration MPs
Develop realistic Project MP, including baselines
Gain formal approval of the plan from sponsor
Hold kickoff meetings
Request changes
3
M I Minhas (References: RMC’s PMP Exam Prep, 9th Edition; PMI’s PMBOK Guide, 6th Edition)
Scope Management
5
Scope management is the process of defining what work is required and then
making sure all of that work – and only that work – is completed.
Project Scope Management-
6
Processes Output
Plan Scope Scope Management Plan
Management Requirment Management
Plan
Collect Requirment Document
Requirements Requirment Tracibility
Matrix
Define Scope Scope Statement
WBS
Create WBS WBS Dictionary
Managing scope of the
7
project
Managing the scope of a project is
important for several reasons:
1- Defines the Project:
Provides clarity on what the project is
project.
Managing scope of the
8
project
2- Controls Project Scope Creep:
Scope creep is the uncontrolled expansion of a
Why was the project undertaken? What business need is the project
intended to address?
scope
What is WBS
The WBS is a required element of project management and it shows all of the
scope on a project, broken down into manageable deliverables.
Without a WBS, a project will take longer, deliverables and work to produce them
are likely to be missed and your project will be negatively impacted.
Create WBS
Some Points from PMBOK Guide
23
The planned work is contained within the lowest level of WBS components,
which are called work packages.
The total of the work at the lowest levels should roll up to the higher levels so
that nothing is left out (what all is necessary) and no extra work is performed
(only what is necessary), a.k.a. 100% rule.
WBS breakdown: point where it is easy to estimate,
WBS Components
24
Key Concepts
Activity
Distinct, scheduled portion of work performed during the project
Control Account
Management Control Point where scope, budget, actual cost and schedule are
integrated and compared with the earned value
Deliverable
Any unique or verifiable product, result, or capability to perform a service that is
required to be produced to complete a process, phase or project
Planning Package
A control account may have one or more planning packages. It is a WBS
component below the Control Account and above the Work Package with known
work content but without detailed schedule activities
Work Breakdown Structure Component
An entry into WBS Structure
Work Breakdown Structure Element
Any individual component including its WBS attributes is called WBS element
The 100%
Rule
How to create WBS
Work Package
Planned work component or
deliverable contained in the Work
Package
32
A work package in a WBS is usually described using only one or two words, but
assigning a deliverable with such a brief description to a team member allows for
too much possible variation, i.e. it allows for scope creep.
Thus, a PM manager can use WBS dictionary to prevent scope creep before work
even starts, rather than dealing with scope creep while work is being done.
Description of work
Responsible organization
Schedule milestones
Cost estimation
Quality requirements
Acceptance criteria
Example
Example
Work Breakdown Structure (WBS)
37
Breakdown
of Scope
Work
Breakdown
Structure
Breakdown
of Scope
Breakdown of Scope
Easy Management and
Control of Project
Deliverable based
Project Scope
Project Status and
Performance reporting
Everyone knows the
responsibility
You can check the
status
Example of Qurbani
Practice Scenario
42
You have been assigned to manage a construction project to build
a new office building. Develop a WBS for the project that includes
all the major construction phases and the tasks associated with
each phase.
This WBS breaks down the construction project into its major
phases, including initiation, site preparation, design and planning,
foundation and excavation, superstructure, interior construction,
mechanical and electrical systems, exterior and landscaping,
quality control and inspection, project management, safety and
compliance, and project closeout.
Each phase is further divided into specific tasks and activities to
provide a detailed view of the project's structure, ensuring that all
necessary tasks are accounted for and can be assigned to the
appropriate teams or individuals.
Breakdown of Scope