Commissioning of Offshore Installations
Commissioning of Offshore Installations
in Building Yards”
21st September 2011
Nagoya Institute of Technology
Wan Saiful Arini
TA Manager
Centre of Innovation
Marine & Offshore Technology Society of Naval Architects &
Marine Engineers, Singapore Joint Branch Royal Institution of Naval
–
·Mechanical Completion
·Pre- Commissioning
·and Commissioning
1.1 1.2 5
4
23 1.2.1.1
1.3 1.4
1.2.1
1.0
1.5 1.6 Work
Tags
orders
Marked up boundary MC Packs
Drawing
Complete the commissioning schedule first,
(Commissioning Packs) then dictate to construction what needs to be
delivered when.
The construction sequence must follow
the commissioning schedule
Integrated Construction
And Commissioning schedule
Work
Reports PC Order Construct Commission
Datab. Construct Commission
Project Completion
System Database
JEP 110921 Ngee Ann
Project Commissioning
Schedule
Boundary Correctly marked up boundary drawings with all necessary physical
break points identified
Drawings
Minimise at hand-over
Structural
Take Over
Certificate
Package system boundary (part system) Back up documentation Such as:
Punch lists, Marked-up drawings
(as commissioned), Queries status, Signed
Commissioning Procedures, Blinding
Lists, Regulatory check lists etc
Delivered to
Site Engineering YES
For Evaluation NO
During this phase of the work, depending on the regulatory agencies involved and
the area of installation, the authority having jurisdiction (USCS, BOEMER, UK DECC,
NPD, ABS, DNV, etc.), will be involved in many aspects of the testing and approvals to
allow the project to proceed further.
STRUCTURAL, MECHANICAL AND PIPING
Mechanical Completion of the structural, mechanical and piping portion of the
project includes, but is not limited to :-
Verification that the piping systems, mechanical equipment and their supporting
structure are installed, non-destructively examined, hydrostatically tested and
flushed clean. Equipment and piping which required stress analysis and the
resulting line stops, piping spring hangers, anchors, guides, etc, should be verified
that installation is in accordance with the design data. Rotating equipment,
including specialized larger pumps, compressors, generators and engine driven
equipment, are handled differently.
STRUCTURAL
·Visual inspection for complete and correct installation
·QC documentation
·Welding
·Load testing of lifting lugs and monorails
MECHANICAL
·Visual inspection for complete and correct installation
·Internal inspection of tanks and vessels
·Alignment • Load testing of lifting equipment
·Hot oil flushing • Bolt tensioning
·Dimension control • Preservation
PIPING
·Welding procedures
·Removal of all items subject to damage during flushing, cleaning and pressure testing
·Flushing of pipework • Chemical cleaning and testing of pipework
·Drying of tested pipework • Preservation of tested pipework
·Reinstatement of all items after testing
·Final inspection of pipework
·Test ISO's and P&ID's showing the extent of each pressure test
·Pneumatic and hydraulic tubing • Hot oil flushing of pipework
·Bolt tensioning • Pipe supports completed
·Insulation • Flow coding
ELECTRICAL
Verification of the electrical installation / construction is more complicated, as much
of it is field routed for best fit. In addition to normal inspection of each of the cables
and wiring, all terminations should be validated for the quality and accuracy of the
installation.
Some areas of inspection during this phase include, but are not limited to, cable and
tray support, tray fill, grounding, integrity, stress cone installation for medium and
high voltage cable, terminations, continuity and megger testing, as well as checking
the bend radius of the final installation and tie down.
ELECTRICAL
·Visual inspection for complete and correct installation
·Insulation and continuity testing of cables
·Insulation testing of generator, transformers and motors, panels, distribution board, etc.
·Earthing checks • Static check of switches and control devices
·Battery preparations • Lighting and socket outlet checks
·Area completion • Heat tracing
·Preservation
INSTRUMENTATION
Mechanical Completion for instrumentation systems includes validation of the
instruments, valves and valve operators compared to the original design data to assure
that process flow conditions will be met. As with the electrical MC, all wiring will need
to be verified, inspected for continuity and insulation as well as loop checks for
confirmation to the automation system. Both hydraulic and pneumatic tubing will be
cleaned, flushed and pressure tested to assure that there are no leaks and that
cleanliness meets required quality for the system it controls.
INSTRUMENTS / TELECOMS
·Calibration and testing of instruments prior to installation
·Visual inspection for complete and correct installation
·Insulation and continuity testing of cables
·Cleaning, flushing, pressure and leak testing of pneumatic and hydraulic tubing
·Adjustment of control, alarm and shutdown settings
·Loop testing • Function testing of control systems
·Function testing of field instruments • Hot oil flushing of instrument tubing
·Area completion • Preservation
OTHERS
HVAC
SAFETY
All of the support documentation and redline drawings and documents should be
attached. The certificate will be accompanied by the punch list if the sail dates
don’t allow completion of all MC activities prior to moving to the next location.
MECHANICAL COMPLETION
Where practical :-
·Piping should be power flushed and dried;
·Communication systems tested to the fullest extent possible;
·Instrument and electrical loops will be verified;
·Instruments will undergo initial and final calibration;
·Pumps can be operated where possible;
·Motors verified for proper rotation and can be run and tested;
·Rotating equipment can receive initial (cold) alignments.
ORGANISATION AND PLANNING ARE KEY
Data includes, but is not limited to, PFDs, P&IDs, mechanical, electrical motor
and ISA data sheets, instrument and electrical loop drawings, wiring plans
and elevations for skids and modules, as well as the manufacturer’s final data
manuals for purchased equipment.
The key will be to provide a conscious effort to close these gaps early within
the project so as not to impact the planned start-up date.
The PC work normally is broken down into discreet, manageable systems. The
systems are separated according to the logical process flow, rather than by a
package vendor.
For example, a heat media system might include a fired unit, heat recovery unit,
storage unit and pumps, along with interconnect piping, instrumentation, controls
and electrical, all of which have likely been supplied by different vendors and reside
on separate skids. This systems breakdown is the logical process to verify
construction, confirm the integrity of the design, and prepare the system for
handover to operations as the phase goes forward.
The organization also allows for the commissioning of sub-systems within a system,
without having to initiate work on the entire system. This avoids having to work
around a finish to start on a system scenario, thus pushing the overall startup
schedule past the desired outcome.
The PC of utility systems is typically the first to be addressed and completed. This
allows life support for the offshore personnel in addition to minimizing the need for
additional components to PC the process systems later.
Pre-COMMISSIONING
ELECTRICAL EQUIPMENT
(Rev. 1, May 1996)
2) Take the normal size commissioning team of 90 direct men working 60 hours per week
multiplied by duration in weeks normally 24 weeks, about 6 months
701 Where specified by the rules, testing shall be carried out in the presence of a
surveyor, and related requirements for test programmes shall be observed.
702 A test programme for harbour and sea trials shall be prepared by the customer
and accepted by the Society. The programme shall specify systems and components
to be tested, and the testing procedure. The Society may, in order to verify rule
compliance, request additional tests and/or data to be recorded.
703 Procedures for Pre-commissioning, testing and commissioning for all the systems
onboard that are covered by the scope of classification shall be prepared by the
customer and accepted by the Society.
704 The tests shall give evidence as to satisfactory operation and performance in
accordance with the rules. When testing control and safety systems, failure modes
shall be simulated as realistically as possible.
705 The extent of participation by the Society should be clearly identified in the Quality
Survey Plan (QSP) submitted by the customer and accepted by the Society only to
ensure compliance with the requirement of Classification Rules and applicable
statutory requirements.
Drilling rig construction presents huge project management challenges,
particularly for a mobile offshore drilling unit (MODU).
Over the last ten years, Lloyd’s Register has been involved in the project
management and commissioning of approximately 150 new-build and major
upgrade drilling rig projects. We have accumulated a wealth of experience
and information, all captured in a knowledge database, which we can adapt
to any site or project that may arise.
STAVANGER, Norway - A joint report issued by Moduspec and the Athens Group at
ONS 2010 provides new insights on the causes and consequences of non-productive
time (NPT) on offshore oil and gas assets.
The report, “The State of NPT on High-Specification Offshore Assets,” found that
more attention to the commissioning stage and more resources allocated to training
are the primary opportunities to reduce NPT.
b.operating (“go live”) date delays cost survey operators between $48.4 million
and $2.4 billion;
NPT causes:
a.yards lack the experienced personnel to fulfill responsibilities under the turnkey
model (the report cited the five major offshore yards, which went unnamed). Some
79% do not believe the yards did a better job of commissioning topsides in 2009 than
in 2008; 21% think they got worse. Taking back control of commissioning was the
number one priority of drilling contractors and operators;
·PRE-INSTALLATION ACTIVITIES
- FACTORY ACCEPTANCE TESTING (FAT)
- STACK UP TESTS
·INSTALLATION ACTIVITIES
- SHALLOW WATER INSTALLATIONS
- DEEPWATER INSTALLATIONS
- Installing the Debris Cap
- Installing the Flowline Spools and Control Jumpers
This is a requirement to ensure product meets customer requirements. The Inspection and
Test Plan (ITP) provide client with various inspection points (hold, monitor, witness) to access
product integrity. External Expert Engineers sometimes participate in writting and witnessing
FAT's for several subsea products.
The well itself is 25 metres deep, and the principle sketch (right) illustrates the
construction.
JEP 110921 Ngee Ann
SIT (System Integration Testing)
On completion of manufacture, assembly and pressure testing a procedural set of system
checks is conducted prior to shipment and deployment
This is the most critical testing stage, where installation and operational conditions are
mimicked.
DECOMMISSIONING REQUIREMENTS AND ACTIVITIES
REGULATIONS / REQUIREMENTS
EXAMPLES :
PLATFORM REMOVAL
SUBSEA EQUIPMENT REMOVAL
Trees
Manifolds
CONCRETE PLATFORM -
CUTTING AND LIFTING SECTIONS REMOVAL OR REMAIN
JEP 110921 Ngee Ann IN PLACE?
STAFFA FIELD
START-UP 1992,
DECOMMISSIONED 1996
TEMPLATE REMOVAL
·Disconnect Flowline
·Cut Piles
·Lift Weight to Unstick
from Seabed = 2 times its
weight in water