Estimation of Flexible Pavement
Estimation of Flexible Pavement
7 Soiling Coat
i. Stone boulders 15cm 1 1000 4.00 0.15 600 m3 30cm wider
ii. Laying and
consolidation of
boulders including 1 1000 4.00 0.15 600 m3
blinding with local
sandy soil
8 Inter Coat
i. Stone ballast 50mm 1 1000 3.70 0.12 444 m3
ii. Laying and 12mm thick
consolidation of loose layer
boulders including 1 1000 3.70 0.12 444 m3 compacted to
blinding with local 8cm
sandy soil
Height
Sl. Particulars of Length Breadth
No of Depth Quantity Remarks
No Items of Works (m) (m)
(m)
9 Top Coat
i. Stone ballast 1 1000 3.70 0.12 444 m3
40mm
ii. Laying and 12mm thick
consolidation of loose layer
stone ballast compacted to
including 1 1000 3.70 0.12 444 m3 8cm
blinding with
local sandy soil
PAINTING
10 Painting 1st coat with Road Tar No.3
i. Stone grit 20mm
gauge @1.35 1 1000 3.70 1.35 / 100 50 m3
cu.m % sq.m.
Height of
Sl. Particulars of Length Breadth
No Depth Quantity Remarks
No Items of Works (m) (m)
(m)
ii. Paint or
binding road 220 kg / 8140 kg
1 1000 3.70
Tar No.3 @ 100 sqm (8.14 tonne)
220 kg % sq.m
iii. Laying 1 1000 3.70 - 3700 m2
11 Painting 2nd coat with Asphalt
i. Stone grit
12mm gauge
1 1000 3.70 .75 / 100 27.75 m3
@ 0.75 cu.m %
sq.m.
ii. Paint or
binding 120 kg/ 4440 kg
1 1000 3.70
Asphalt @ 120 100 sqm (4.44 tonne)
kg % sq.m
iii. Laying 1 1000 3.70 - 3700 m2
Height
Sl. Particulars of Length Breadth of
No Quantity Remarks
No Items of Works (m) (m) Depth
(m)
Brick edging on
both sides
12 1 1000 - - 1000 m
including bricks
and labour
Miscellaneous
Items
13 1 1000 - - 1000 m
(Km, half Km and
boundary stones
Road directions
posts, caution
14 signs, Traffic 1 1000 - - 1000 m
diversions, service
road etc.,