the items abstracted from the dimension sheets in bill order. This may not seem
too difficult a task to anyone who has not tried it, but when tender documents are
being prepared in a rush against a tight deadline (which must be 99% of the
time!) the worker-up may be handed the dimension sheets in small lots but must
lay out his abstract to accommodate items he has not yet seen.
A typical abstract is set out in Figure 7. The figures on the left-hand side are
the column numbers of the dimension sh
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0 ratings0% found this document useful (0 votes)
57 views24 pages
Contract Changes Management Nov.2016
the items abstracted from the dimension sheets in bill order. This may not seem
too difficult a task to anyone who has not tried it, but when tender documents are
being prepared in a rush against a tight deadline (which must be 99% of the
time!) the worker-up may be handed the dimension sheets in small lots but must
lay out his abstract to accommodate items he has not yet seen.
A typical abstract is set out in Figure 7. The figures on the left-hand side are
the column numbers of the dimension sh
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 24
Contract Changes Management
The two most important issues considered in contract
change management are Uncertainties and Changes.
Uncertainties are issues that can either be difficult to
reasonably predict or unknown during the planning phase of Procurement and Contract Management.
For instance, when uncertainty is understood as the
difference between the amount of information required to perform the task and the amount of information already available by the planning team .
Changes are issues requiring alterations during the
implementation of Procurement and Contract Management. Uncertainty is higher in the early phase and reduces through time by getting more and better information. Uncertainty is not only related to the future but also the knowledge of the past as well, that is; information records and those based on experiences are also uncertain. This indicated that Uncertainty is always with us and can never be eliminated. Therefore, all projects were, are and will be planned under a certain level of uncertainty. This can be therefore one of the major reasons why changes occur during implementations.
Uncertainties can be mitigated using the following
four interventions used in project contracts: Absorbing: Understanding projects are planned under uncertainty and changes are expected during implementations imply alternative provisions for implementation phases such as Contingencies, Alterations, etc which are made and used to absorb changes caused by uncertainties. Dividing or Splitting: When a project uncertainty is high or there is less past experience, dividing projects into packages or different phases in order to make them smaller in sizes and their complexities, etc is to divide or split to reduce risks due to uncertainties. Postponing: When Contracts could not clearly state specifications, quantities and estimates; they often place Provisional Quantity or Provisional Sum to postpone uncertainties. Transferring: Lump Sum Contracts, DB and BOT delivery systems are some form of contractual approaches to transfer uncertainties from Owners to Providers. Requirement Changes Management Systems All projects are planned under the context of uncertainties, what makes them different among each other is that the type and degree of uncertainties does differ.
so that Project Owners can prerogatively make
changes during implementations. For instance, Clauses 51 and 52 of the General Conditions of FIDIC Red Book provided provisions for Alterations (Additions and Omissions) to enable Project Owners use the Engineer (the Consultant) to make requirement Changes. They can cause review of designs and / or create additional or changes in designs and / or just work orders to instruct contractors to carryout the requirement changes. While project owners retain the right to requirement changes, the contractor is obliged to accept as per the conditions of the contract. However, the contractor is entitled to request and agree upon new or existing rates for such changes.
Change Orders are written instructions, agreed by
the Project Owner or His Representative, directing the Project Doer to make changes with or without the Consent of Regulatory Bodies. Often they are entertained using standard formats There are three kinds of Change Orders: Unilateral Change Order: is that provides the right to any of the parties to make changes without causing any effect on the other parties or disrespecting any laws, regulations and rules binding the contract and itself but requires notification to the other parties for knowledge. Bilateral Change Order: is a type of change order that require the agreement and / or consent of the two contracting parties (the Project Owners and The Project Provider) to make changes but requires the respects for laws, rules and regulations binding the contract and itself and requires notification to the other parties for knowledge. Multilateral Change Order: is a type of change order that require the agreement and / or consent of the three or more contracting parties (the Project Owners, The Project Providers, The Project Financiers and / or the Regulators) to make changes but requires the respects for laws, rules and regulations binding the contract and itself and requires notification to the other parties for knowledge Requirement changes based on the different types of change orders modifies contracts in either of or the combinations of the following three ways: Time changes only, Time changes accompanied by Cost Compensations, and Cost Changes only. Contract Time can either be Competitively or Directly Time Changes Management System
assigned. In both cases, Time planning can be made
using different approaches such as using CPM, PERT, MCS, SP or TOC. Bar Charts, Gantt Charts, Network Diagrams and Tables can be used to show Time Plans and Accomplishments. Contractual Agreement finally defines the Contract Time of a project. The Completion Time of projects include: Dates between Contract Agreement and Handing Over of Site, Mobilization Period(s), Contract Time, and Justified and Agreed Supplementary or Extension of Time. Dhos = Dcont + Thos; Dstart = Dhos + Tmob; Dcomp = Dstart + Tcont + Tjust + Tsupp If Dact < Dcomp; Bonus, if any If Dact > Dcomp; Time Overrun and Liquidated Damage Where, Dhos = Date for Handing Over of Site; DCont = Date for Contract Agreement; Thos = Time between Contract agreement and handing over of site; Dstart = Date for Start of Construction Works; Tmob = Time for Mobilization; DComp = Date for Completion Time; Tjust = Time for Justified Delay; and Tsupp = Time for Supplementary Works or Agreements. Unfortunately, in most instances projects exhibit a principal dimension measured by such comparison called Time Delays and Overruns. Time Delays and Overruns Time delays can occur in components of a project or trades of works, but when their cumulative effect makes the actual completion time beyond the contract completion time, it is called time overrun Contractors in some instances accelerate projects in order to avoid liquidated damages. Time delays can be classified into the following three categories:- Classic delay ;-occurs "when a period of idleness or useless- ness is imposed upon contractual work“ source of delay can be contractor ,owner or by an outside force which neither party can control.
Serial delay :- is a "linkage" or series of delays one after the
other, created by one original delay. Concurrent delay :- occurs when both the contractor and owner cause separate delays during the same period of time. The one that causes longer delay is considered for time delay computations.
Justifiable and Non - Justifiable Delays
Justifiable delays ;- are delays that occurred due to causes which are beyond the control of project doer. It is caused by project owners, the contractor or the consultant or the supplier is directly justified for the ef- fects on delay of the project. Force Majeur will also be one of the causes for justifiable delay. Non - Justifiable or Non - Execusable Delays:- are delays that occurred due to negligence to fulfill contractual obligation and are within the control of the contracting parties.
While Justifiable delays can be either compensable or
non compensable; Non -justifiable delays will cause remedial rights Compensable and Non – Compensable Delays Delay damages can involve additional costs incurred by the contractor as a result of the extended duration of its performance:- Examples of the type of additional costs associated with delays include: - Extended or Increased management / supervisory costs - Additional payment / performance bond premiums - Additional liability insurance premiums - Extended equipment / trailer rental costs - Materials escalation costs - Unanticipated weather protection - Idle labor / equipment charges - Overhead Cost (Specifically for that project)
N.B;- One of the first factors for determining whether
you can assert a valid claim for delay damages is your contract. For example, contract clauses can be in line with: - No Damage for Delay, :-prohibits recovering of additional costs incurred as a result of delay, regardless of the cause in creating the delay. Conditional Recovery,;- This view limits ability to recover or make a claim for delay or impact damages, so that the recovery is very much dependent on causes of delay and their CPM Network. Additional Time and Compensation for Delays;- This view does not inhibit or limit rights to recover due to delay damages. In Evaluating delay claims, five aspects must be taken into account: The effective duration of delay The effect of delay on work intended to be done The costs attributable to the delay The nature of costs / expenses The resources and acceleration / expediting measures Typical Contractors Delay Damage Components Include: (1) Direct cost increased (material escalation) material that occur during the delay (2) indirect costs that occurred during the extended performance period, e.g. project supervision costs, site overhead cost, insurance, and job site power and water. (3) home office overhead that was incurred during the extended performance period, (4) lost productivity caused by the delay and (5) other damages directly related to and attributable to the delay. E.g- interest on the claim, - lost profits on other jobs if it Generally provisional sum is an amount allocated for a specialized work by a specialized firm, for which the details are not available at the time of tender. The provisional sum amount will be a best guess at the time of tender by the employer or contractor depending upon the type of provisional sum. Hence claim made by the contractor need not necessarily be the exact amount mentioned in the contract.