Thesis Presentation
Thesis Presentation
on
IMPROVEMENT OF PROJECT
PERFORMANCE THROUGH THEORY OF
CONSTRAINT; A CASE STUDY OF RURAL
ROAD CONSTRUCTION
May,2018 1
Presentation Outline
1. Introduction
2. Statement of the problem
3. Research Questions and Research objectives
4. Significance of the study
5. Scope and Limitation of the study
6. Literature Review
7. Methodology
8. Results and Discussion
9. Conclusions and Recommendations
2
Introduction
Constraint
3
Introduction
Constraint Contd..
4
Introduction
Theory of Constraint
• The Theory of Constraints is a methodology for identifying the most
important limiting factor (i.e. Constraint) that stands in the way of
achieving a goal and then systematically improving the constraint
until it is no longer the limiting factor (Lau & Kong 2006).
5
Introduction
•Theory of Constraint
6
Statement of the Problem
7
Statement of the Problem
8
Research Questions
9
Research Objectives
General Objective
• The overall objective of this study is to identify the constraints in
the specified road construction project working environment and
apply the theory of constraints.
Specific objectives
• To identify the constraint i.e. weakest processes in the project
scheduling.
.
11
Scope and Limitation of the study
Scope
• To deal with the different critical constraints and identification of the
critical chain in the proposed scheduling in rural road construction
• Two rural road construction projects were selected which are under
construction by SNRTP, DTO/DoLIDAR.
12
Limitations
• Only Two sample projects are chosen for the application of
TOC and CCPM approach to reschedule the project.
13
Literature Review
Project Management
• Project management is the application of knowledge, skills, tools, and
techniques to project activities to meet project requirements.
Source:
https://www.learnproduction.com/theory-of-c
18
onstraint
Literature Review
Theory of Constraints Applications
• Manufacturing
• Project Management: This is sometimes called Critical Chain
Project Management (CCPM), which is a method of planning and
managing projects that puts more emphasis on the resources used
to execute project tasks. The solution will tend to keep resources
levelly loaded, but will require them to be flexible in their
scheduling.
• Distribution
• Marketing and sales
• Finance
19
Literature Review
Critical Chain Project Management (CCPM)
20
Literature Review
Critical Chain Project Management (CCPM)
21
METHODOLOGY
22
Research Flowchart
23
Study Area
Bhimdhunga-Lamidanda Road
24
Study Area
25
Data Collection
27
Constraints of Selected Project
Sankosh-Tipling Road
28
Constraints of Selected Project
Sankosh-Tipling Road
29
Constraints of Selected Project
Sankosh-Tipling Road
30
Constraints of Selected Project
Sankosh-Tipling Road
31
Constraints of Selected Project
Sankosh-Tipling Road
100.00%
90.00%
80.00%
Proposed Work Schedule
70.00%
%completion
60.00%
50.00%
40.00% Actual Progress
30.00%
20.00%
10.00%
0.00%
123456789111111111122222222223333333333444444
0 1 2 3 4 5 6 7 8 9 0 1 2 3Weeks
4567890123456789012345
32
Constraints of Selected Project
Bhimdhunga-Lamidanda Road
33
Constraints of Selected Project
Bhimdhunga-Lamidanda Road
34
Constraints of Selected Project
Bhimdhunga-Lamidanda Road
35
Constraints of Selected Project
Bhimdhunga-Lamidanda Road
S-Curve (Bhimdhunga-Lamidanda Road)
Actual Start Dec 15, 2017
100.00%
90.00%
80.00%
70.00%
60.00%
50.00%
40.00%
30.00%
20.00%
10.00%
0.00%
1 4 7 10 13 16 19 22 25 28 31 34 37
36
Application of Theory of Constraint (TOC)
Sankosh – Tipling Road
Inserting Buffers to protect project deadline
37
Application of Theory of Constraint (TOC)
Sankosh – Tipling Road
Application of Critical Chain Project Managment
38
Application of Theory of Constraint (TOC)
Sankosh – Tipling Road
Buffer Penetration Management
40
Application of Theory of Constraint (TOC)
Bhimdhunga-Lamidanda Road
Exploitation of Constraint
•Removal of minor constraints (like economic,
environmental, socio-political issues) which can disturb
to major process implementation
•Provision of full staffing at the constraint processes
with surplus/backups.
•Mobilization of sufficient skilled workers with support
•Setting of Management plan for stock piling of
materials (river bed materials, crusher run materials,
sand, cement, reinforcement bars, bitumen), provision
for labor camp, facilities, health and safety.
•24/7 operation at the constraints (day/night shift).
41
Application of Theory of Constraint (TOC)
Bhimdhunga-Lamidanda Road
Exploitation of Constraint
•Ensuring availability of gravel materials, bituminous
materials and equipments
42
Application of Theory of Constraint (TOC)
Bhimdhunga-Lamidanda Road
Subordination to above exploitation
•Transferring the resources to constraint processes which are
being used by non-constraint processes like earthworks, Stone
masonry works, gabion masonry works and those activities
have available float to complete, so that sufficiency of
resources to sub-grade, sub-base, base and bituminous works
are maintained.
•Backup system of material, manpower and equipment are
generated.
•Immediate problem solving team is formed and set under
alarm condition.
43
Application of Theory of Constraint (TOC)
Bhimdhunga-Lamidanda Road
Subordination to above exploitation
•User committee members are motivated to solve social,
political and other environmental issues.
•Installing management hotlines and plant alarm at the
constraint.
•Monitoring the work progress to track it at day/night shift.
•Expediting as required to ensure uninterrupted supply to
constraint.
•Educating staff: Constraint first (tooling, maintenance and
material movement).
•Ensuring raw material availability at all times
•Ensuring the uninterrupted supply of resources to constraint at
all times. 44
Application of Theory of Constraint (TOC)
Bhimdhunga-Lamidanda Road
Elevating the system Constraint
47
Conclusions
At first, Study was carried out to identify the major constraints
in the road project.
49
Conclusions
-After identifying the constraints,
•In study of Sankosh-Tipling Road project, the Theory of
Constraint (TOC) was applied considering the human behavior
factors like Pakrinson’s Law and Student syndrome to manipulate
the activity time estimate to aggressive time estimate by creating
the time buffers in Critical Chain Project Management (CCPM).
•With application of Critical Chain Project Management (CCPM),
the project was supposed to be finished 30 weeks prior to
originally estimated date of completion if it has ideal condition.
However, several delay factors consume the time buffer like
feeding buffer as well as project buffer can make project delay
rather than ideal condition. But, CCPM ensures by early warning
of time consumption, timely completion of project as intended
date of completion.
50
Conclusions
•In study of Bhimdhunga-Lamidanda Road Project, the
generalized form of Theory of Constraint (TOC) was applied to
overcome the constraints identified.
•Exploitation of constraint was applied for improvement of
internal capacity to accelerate the output of the processes.
•Similarly, Subordination was proposed for assuring the
availability of resources within internal project environment.
•If performance of work process is not improved by managing
and effective utilization of the internal resources, extra resources
were proposed for its addition to constraint i.e. elevating system
constraint. Thus, with application of Theory of Constraint (TOC),
the project was supposed to be finished within intended date of
completion.
51
Recommendations
52
Recommendations for further study
53
References
54
References
56
References
57
THANK YOU!!!
58