Activity Planning and Schedule
Activity Planning and Schedule
TEAM MEMBERS
1: FINISH TO FINISH
2: FINISH TO START
3: START TO FINISH
4: START TO START
FINISH TO START: most common type,Task (B) can’t start until Task (A) finish.
I-e: ( Task (A) : new feature are to be added in app/site,
Task (B) : Testing of these new features,
Testing can only be done if features are added so B can’t start until A end )
VISUALIZATION:
TASK B
TASK A
VISUALIZATION:
TASK B
TASK A
Start time might be difference but end are same
START TO FINISH: Task (B) can’t finish until Task (A) start.less
common
I-e: ( Task (A) : start upgrading the system,
Task (B) : maintenance team do daily checkups.
Maintenance or task B only stops when system starts getting
upgradation)
VISUALIZATION:
TASK A
TASK B
TASK A
TASK B
A
Activity Predecessor
D
A -
B - B
C -
D A,B
C
E B
F D,C
E
Precedence Diagramming Method ( PDM )
A - 5
B A 3
C A 4
D B,C 2
E D 5
5 B8
ES AT EF 6 3 9
LSDR LF 0 A 5 9 D 11 11 E 16
0 5 5 9 2 11 11 5 16
5 C9
5 4 9
Schedule development :Adding the time dimension
Moving from Logical to Physical network model:
• we are now ready to start thinking about when each activity should be
undertaken (Physically).
CPM
project network analysis technique used to predict total project Duration and
concerned with two primary objectives:
• Planning the project in such a way that it is completed as quickly as possible; and
• Identifying those activities where a delay in their execution is likely to affect the
overall end date of the project or ‘later activities’ start dates.
A 6 0 6
B 4 0 4
C 3 6 9
D 4 4 8
E 3 4 7
F 10 0 10
G 3 10 13
Example Question
A - 5
B A 7
C A 4
D B 10
E C 3
F C 5
G D,E 6
H F,G 4
Early Finish (EF) = ES + Duration
LS = LF - DURATION
Critical Path 12 D 22 12 - 12 = 0
12 10 22
22 G 28
5-5=0 5 B 12
22 6 28
9 E 12
5 7 12
0 A 5
19 3 22
28 H 32
0 5 5
5 C 9
28 4 32
9 F 14
0-0=0
15 4 19 28- 28 = 0
23 5 28
ES - EF = 0
THANK YOU