Earthworks
Earthworks
- The movement of soil or rock from one location to another for construction purposes is called earthworks.
- A volume of earth that is excavated, that is, removed from its natural location, is called cut.
- Excavated materials that is placed and compacted in a different location is called embankment or fill.
The volume of earthworks can be determined by either of the following methods:
a) Volume using End Area Method
b) Volume using Prismoidal Formula
c) Volume using End Area with Prismoidal Correction
a) Volume using End Area Method - It is assumed that the volume between the successive cross sections is the
average of their areas multiplied by the distance between them
( 𝐴 1+ 𝐴 2 ) ( 𝐿)
A2 VE =
2
A1
L A1 = Area of the 1st section
A2 = Area of the 2nd section
A2
Am
L/2
A1
L/2
(𝐿) ( 𝐴 1+ 𝐴𝑚+ 𝐴 2 )
VE =
A1 = Area of the 1st section 6
A2 = Area of the 2nd section
Am = Area of the midsection
c) Volume using End Area with Prismoidal Correction - only for 3 level section
D1 D2
C1 C2
A1 A2
V = VE – VCP
𝑟𝑖𝑠𝑒
Gradient = =m
𝑟𝑢𝑛
or%
m rise
run
CL
CROSS-SECTION NOTES:
(6.45,
2.3)
x 6.45 0 4.5 (0, 1.5)
(x,y)
y +2.3 1.5 +1.0
(4.5, 1.0)
CL
LEFT SECTION RIGHT SECTION B/2 B/2
B
Given the following cross-section notes of an earthwork on a terrain.
The width of the road is 12m and the side slope is 2.5:1
CL CL
(31, 10) (41, 14)
(0, 5) (0, 7)
10 m A2 (13.5, 3) 14 m A2 (17.25, 4.5)
A1 5m A3 A1 7m A3
A4
3m A4
4.5 m
25 m 6m 6m 7.5 m 35 m 6m 6m 11.25 m
31 m 13.5 m 41 m 17.25 m
12 m 12 m
The following is set of notes of an earthworks of a road construction which is undertaken by the DPWH.
9 4.5 0 4.5 6
1 + 020
+3 +5 2 1.5 1.0
7.54.5 04.59
1 + 040
+ 2+ 5+4+2+3
“If not mentioned, side slopes (S:1) for left and right are equal”
(0, 2.64)
(9.8, 2.4)
(7.4, 1.2)
2.4 1
S 1
S 1.2
9.8 - B/2 B/2 B/2 7.4 - B/2
Given the cross section notes of an earthwork between station 10+100 to 10+200. Assume
both stations have the same side slope and width of the base.
CL (6.0, 2.0)
CL
(6.45, 2.3)
Cut and Fill is the process of removing or cutting earth from areas of higher elevation and using it to fill
in areas of low elevation to level a parcel of land so it can be used for some purpose.
This technique where commonly used to prepare building sites, roadways, railways, waterways, and
anywhere else that the natural topography must be leveled to make the area useful in those capacities.
The process requires the use of various heavy earthmoving and excavation equipment such as,
backhoes, loaders, dump truck, bulldozers, and compactors.
Given the following section of an earthworks for a proposed road construction on a hilly
portion of the route. The width of the road base for cut is 6 meters for allowance of drainage
canals and 5 meters for fill. Sides slopes for cut is 1:1 and for fill is 1.5:1
3.7 0 𝑥
−0.8 0 +1.8
2.7 1.8
1
1.2 2.5 1
1.5
1 3 1.8
0.8
4.8
(3.7, -0.8)
Given the following cross sections:
Finished Roadway
2.8
-g% +5%
3
1.2
1.4
0.2 0.2
60 meters
Ground Line
Finished Roadway
+ 5% 2.8
-g%
3
1.2
1.4
0.2 0.2
60 meters
+ 5% 2.8
-g%
1.4
x 60-x
Sta 0+260
Sta 0+250
1.4
30 10
x 60-x
Sta 0+250
CL
1 C = 2.1 1
2 2
5 5