Internship PPT

The document summarizes an internship presentation on a multi-storied residential project. It details the objectives, company profile, project details including area, cost and flats. It also describes the structural details, construction safety measures, materials used and works executed like shuttering, reinforcement, concreting, curing and deshuttering.

Uploaded by

AK
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
96 views19 pages

Internship PPT

The document summarizes an internship presentation on a multi-storied residential project. It details the objectives, company profile, project details including area, cost and flats. It also describes the structural details, construction safety measures, materials used and works executed like shuttering, reinforcement, concreting, curing and deshuttering.

Uploaded by

AK
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 19

BANGALORE INSTITUTE OF TECHNOLOGY

K R Road, V V Puram, Bangalore 560 004


DEPARTMENT OF CIVIL ENGINEERING

Internship presentation on

MULTISTORIED RESIDENTIAL QUARTERS

PRESENTED BY: Under the guidance


AKSHITH KARTHIK GOWDA DEEPIKA.K.C
(1BI20CV009) Assistant professor
Dept of civil Engineering
CONTENTS
1. INTRODUCTION
2. OBJECTIVES OF THE INTERNSHIP PROGRAM
3. COMPANY PROFILE
4. ABOUT THE PROJECT
5. CONSTRUCTION SAFETY
6. MATERIALS USED
7. WORK EXECUTED IN CONSTRUCTION
8. CONCLUSION
INTRODUCTION
• Practical knowledge in Civil Engineering helps students and engineers apply
theoretical concepts in real-world scenarios, developing critical skills like
problem-solving and communication.

• Exposure to construction sites and laboratories allows engineers to


understand material properties and industry regulations, aiding in material
selection and adherence to standards.

• Internships provide hands-on experience in various phases of construction


projects, promoting lifelong learning and technical proficiency.

• Internship experiences in disciplined and quality-focused companies bridge


the gap between theoretical knowledge and practical application, preparing
individuals for professional life.
OBJECTIVES OF INTERNSHIP PROGRAM
1. To familiarize with proper planning, design and field operations.

2. To understand the construction methods adopted for different construction


activities.

3. To get exposure with the management and communication functions


performed with in the construction site.

4. To know how the construction projects are executed based on the design and
its specifications.
COMPANY PROFILE

NSL CONSTRUCTIONS.PVT.LTD.
Company name: NSL CONSTRUCTIONS .PVT.LTD.
Address: No-93, 4th Floor, Sai complex, 1st Phase, Sector A, Yelahanka new
town, Bangalore-560062
Mobile:+91 80 28462613
ABOUT THE PROJECT
Project Name: Proposed Group ‘A’ Officers Quarters.
Area Details:
• Total area of the land- 2675sqmts
• Built up area- 1985sqmts
• Total open area-690 sqmts
Cost Details:
• Construction Cost: Rs 76,45,10,469/-
Flat Details:
• Total Number of Flats- 72
• 48 Flats with 172 sqmts area.
• 24 Flats with 221 sqmts area.
Floor Details : G+12 Floors.
• With a multipurpose hall.
Height Details:
• Ground Floor/ Mechanical Parking- 5.1M
• Floor to Floor Height: 3.05M
• Total Height of The Building- 41.7M
Project Location:

5th Cross, Vasant Nagar,


Bengaluru 560051.
STRUCTURAL DETAILS
• RCC framed structure with columns beams and slabs, having regard to safety &
durability.
• Grade of Concrete:
For Columns: M30
For Beams & Slabs: M25
• Grade of Steel : Fe 550
• The design life of the structure -100 Years.
• A total 289 Piles of 750mm Dia are used.
• A Raft foundation of 1.2m is placed.
• Safe bearing capacity soil for the raft is 63.75 kN/sqmtr
• The safe load carrying capacity of the pile is 1863.26 kN/sqmtr
CONSTRUCTION SAFETY
SAFETY EQUIPEMENT’S USED
• Helmet, Jacket

• Shoes

• Hand glows, shoulder glows

• Safety nets.
MATERIALS USED
SHUTTERING AND SCAFFOLDING WORKS

Column Shuttering Jacks or Props Runners

Tie-rods C-Clamps Acrow Span


CONTINUED..
COUMNNS BEAMS & SLABS

Ready Mix Concrete TMT Bars-Fe 550 Cover Blocks


CONTINUED..
MASONRY WORKS

Solid concrete blocks AAC Blocks Ramco cement-53 Grade


(400x200x200) (600x200x200),(400X200x100)

AAC Block Adhesive M-Sand GI-Mesh


WORKS INVOLVED DURING INTERNSHIP
TRAINING PERIOD

1. SHUTTERING WORK
• Shuttering work includes both formwork and false work. Formwork is a mould or
open box, like container into which fresh concrete is poured and compacted.
• When the concrete is set, the formwork is removed, and a solid mass is produced
in the shape of the inner face of the formwork.
• False work is the necessary support system that holds the formwork in the correct
position.
• The top of the formwork is normally left open.
• Generally shuttering involves three major stages, i.e. column shuttering, beam
shuttering and slab shuttering.
• In column shuttering, plywood is used as the moulding material and in beam
shuttering plywood and supporting jacks are used.
Shuttering for Column Shuttering for Beam & Slab Shuttering for Staircase
2. REINFORCEMENT & CONCRETING
• It involves arranging steel bars within the column, Beam & Slab formwork
according to structural drawings and specifications.
• This ensures proper reinforcement to withstand the anticipated loads and provide
structural integrity to the Building.
• Concrete of M25 Grade is used in Slabs & Beams and M30 Grade is used in
columns

Reinforcement of staircase, beam & slab Casting of Column


3. CURING
Curing involves maintaining adequate moisture and temperature conditions to
facilitate hydration and strengthen the concrete over time
• Curing of slabs and beams shall be achieved by ponding only, for a period of 7
days.
• Curing of footing tops, RCC walls, columns and external beam faces shall be
done by covering them with gunny bags or hessian and keeping wet constantly
for complete curing period of 7 days.

Curing for column, beam & slab


4. DESHUTTERING

• De-shuttering refers to the removal of formwork from around the cured concrete slab
after it has achieved sufficient strength

Deshuttering