PM 7
PM 7
A none 2 2
B none 4 3
C A 3 2
D A 5 4
E A 1 3
F C 2 3
G D 5 3
H B, E 7 3
I H 2 2
J F, G, I 3 1
Resource Smoothing - Homework
0 2 2 5 5 7
1 A 2 6 C 3 6 F 2
1 3 8 11 11 13
0 0
0 St 0 2 7 7 12
0 0 1 D 5 1 G 5 13 16 16 16
3 8 8 13 0 J 3 0 En 0
13 16 16 16
2 3
1 E 1
3 4
0 4 4 11 11 13
0 B 4 0 H 7 0 I 2
0 4 4 11 11 13
Resource Smoothing - Homework
Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Activity
A 2 2
B 3 3 3 3
C 2 2 2
D 4 4 4 4 4
E 3
F 3 3
G 3 3 3 3 3
H 3 3 3 3 3 3 3
I 2 2
J 1 1 1
Suma 5 5 12 9 9 10 10 6 6 6 6 5 2 1 1 1
Resource Smoothing - Homework
Non-critical activity C has been delayed and the following activities too:
Time 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Activity
A 2 2
B 3 3 3 3
C 2 2 2
D 4 4 4 4 4
E 3
F 3 3
G 3 3 3 3 3
H 3 3 3 3 3 3 3
I 2 2
J 1 1 1
Suma 5 5 10 9 9 9 10 9 6 6 6 5 2 1 1 1
Resource Smoothing - Homework
Activity
A 2 2
B 3 3 3 3
C 2 2 2
D 4 4 4 4 4
E 3
F 3 3
G 3 3 3 3 3
H 3 3 3 3 3 3 3
I 2 2
J 1 1 1
Suma 5 5 6 7 7 7 7 7 8 8 8 8 8 1 1 1
Resource Smoothing - Homework
Activity A B D E G
CPM Application:
2 4 4 7
CPM Application:
The scenario created by our decision to crash C:
1 B 2 1 F 3 A 2 1700
3 5 5 8 B 2 1760 N/A
C 2 3000 yes
D 2 1820 N/A
0 2 2 4 4 8 8 10 E 4 3300
0 A 2 0 C 2 0 E 4 0 H 2 F 3 1200
0 2 2 4 4 8 8 10 G 4 1600
H 2 1900 N/A
Total 10 16280
2 4 4 8
0 D 2 0 G 4
2 4 4 8
Scenario “crash C”:
CP: A-C-E-H & A-D-G-H
Time: 10, Cost: 16280
Improving our plan
CPM Application:
The scenario created by our decision to crash C and then A:
2 4 4 7 B 2 1760 N/A
C 2 3000 yes
D 2 1820 N/A
0 1 1 3 3 7 7 9 E 4 3300
0 A 1 0 C 2 0 E 4 0 H 2 F 3 1200
0 1 1 3 3 7 7 9 G 4 1600
H 2 1900 N/A
Total 9 16480
1 3 3 7
0 D 2 0 G 4
1 3 3 7
Scenario “crash C&A”:
CP: A-C-E-H & A-D-G-H
Time: 9, Cost: 16480
Improving our plan
CPM Application:
The scenario created by our decision to crash A, C, E, and G:
0 B 2 0 F 3 A 1 1900 yes
1 3 3 6 B 2 1760 N/A
C 2 3000 yes
D 2 1820 N/A
0 1 1 3 3 6 6 8 E 3 4500 yes
0 A 1 0 C 2 0 E 3 0 H 2 F 3 1200
0 1 1 3 3 6 6 8 G 2 2000 yes
H 2 1900 N/A
Total 8 18080
1 3 3 5
1 D 2 1 G 2
2 4 4 6
Scenario “crash C,A+E&G”:
CP: A-B-F-H & A-C-E-H
Time: 8, Cost: 18080
Improving our plan
There is only one possibility for crashing remaining (F) but it will
shorten just one of two critical paths and total time will stay the same
(8 days, but the cost will rise by another 400 )
There is no further improvement possible
Important notes:
There are limits as to how much speed can be gained by adding staff.
Doubling the size of the workforce will not necessarily reduce
completion time by half – issues of training, communication within
larger team, problem of co-ordination etc.
These problems could be solved by scheduling overtime (no
additional costs of coordination and communication) but it has many
disadvantages too.
It is not true that over an extended period of time, a person
productivity remains constant. There are natural limits to what is
possible and extended overtime may actually lead to an overall
decline in productivity.
Homework