ESDE Module-4 2019 Scheme Ful
ESDE Module-4 2019 Scheme Ful
Estimation
Module-4
Industrial Power and Lighting
Installations
Module 4
• Industrial installations –classifications
• Design of electrical distribution systems with main switch board, sub
switch boards and distribution boards with ACBs, MCCBs and MCBs as
the case may be, for feeding power (mainly motors) and lighting loads of
small and medium industries.
• Selection of armoured power cables (AYFY, A2XFY, YWY) – calculation
of ampacity, voltage drop, short circuit withstand capacity etc.
• Design of MSB & SSB including Motor Control Centre (MCC) for motor
controls – selection of bus bars and switchgears.
• Selection of 11kV indoor and outdoor transformer substations upto 630kVA
- selection of switchgears and protective devices –Preparation of schedule
of works and bill of quantities (cost estimation excluded).
• Short circuit calculations and earthing design for the HV and LV sides of
an 11 kV substation of capacity up to 630 kVA.
• Pre-commissioning tests of 11kV indoor/outdoor substation of an HT
consumer.
Industrial Installations
• Future expansion
• Spare capacity
• Statutory requirements
• Site condition
Standard rating of Distribution Transformers
(11/0.433kV)-
50,63,80,100,160,200,250,315,400,500,630,800,1000,1250,
1600 and 2000kVA
Cooling- Oil Natural Air Natural(ONAN), Oil Natural Air
Forced(ONAF),
Parallel operation of transformers- A pair of transformer
is said to be parallel if they are connected in parallel on at
least two sides for meeting higher loads
Condition for parallel operation
• Same vector group
• Turns ratios should be similar
• Same % impedance voltage
• Ratio of the rated capacities of the transformers shall not
be more than 3:1
Typical single line layout of Transformer Substation and Main
Switch Board(MSB)
Types of 11kV Substations
Consider distribution
1.Outdoor Substation
(i) Pole mounted outdoor substation
(ii) Floor mounted outdoor substation
• Copper conductor cable only will be used for submain/ circuit/ point
wiring.
• Minimum
• Lightsize of wiring:
Wiring (Lamp, Fan, 6A Socket) : 1.5 sq. mm.
• Power Wiring(16A or 20A Socket) : 2.5 or 4.0 sq. mm.
• Power circuit rated more than 1 KW : Size as per calculation based on Voltage drop
* (Refer Tutorial for more details)
The permitted voltage drop for any given equipment from the control switch is
3% for LT-AC system. The conductor size need to be increased if the voltage drop
exceeds this value. Voltage drop along a conductor mainly depends on current
flowing through it and the length and cross sectional area of the conductor
High Current Cables used for LT System
• PVC is water and chemical resistant, hence used for outer protection
• Black color used
Earth wire sizes - Standard Wire Gauge (SWG)
• Uninsulated Copper conductor is
used as the earth wire Each number
• Higher current will heat the represents a size of
cable and damage the insulation wire
and may result in short circuit
• Design 500KVA, 11kV/415V transformer substation used for
power supply to a medium industry
• Assume the Transformer as Indoor Oil Filled Type
1. TRF Current Ratings: 26.2A/666.5A (Ref. Table 31 of DB)
2. DO Fuse: 50A (Refer Table-34 of DB)
3. HT Cable: 3 Core, 150mm3, XLPE (From NEC)
4. HT CB: Load Break Switch (LBS) with Trip at 26A
5. LT Cable: 3 Runs of 3.5Core 400mm2 AYFY Cable(Refer Table-34, 54 of
DB)
6. LT ACB: 800A with Over Current Trip set at 666A (Refer Table-108 or
109 for MCB or 110 for ACB)
7. Busbar Sizing
• Permitted Current Density of Aluminium = 0.8A/mm2
• Busbar Area = 666A/(0.8A/mm2) = 833mm2
• Busbar Size: Single Bar of 76mm X 6mm Aluminium (Refer Table 38A of DB)
• Design 100KVA to 630KVA , 11kV/415V transformer substation
used for power supply to a medium industry
• Assume the Transformer as Indoor Oil Filled Type
1. TRF Current Ratings: (Ref. Table 31 of DB)
2. DO FuseRating: (Refer Table-34 of DB)
3. HT Cable: 3 Core, 150mm3, XLPE (From NEC)
4. HT CB: Load Break Switch (LBS) with Trip at ---A
5. LT Cable: 3 Runs of 3.5Core ----mm2 AYFY Cable(Refer Table-34, 54 of
DB)
6. LT MCCB or ACB: ----A with Over Current Trip set at ---A (Refer Table-
108 or 109 for MCB or 110 for ACB)
7. Busbar Sizing
• Permitted Current Density of Aluminium = 0.8A/mm2
• Busbar Area = ---A/(0.8A/mm2) = ---mm2
• Busbar Size: Single Bar of --mm X --mm Aluminium (Refer Table 38A of DB)
Installation of transformer substation
Outdoor type
Minimum clearance between suppliers and
consumers 11kV structure shall be 3m
Phase to phase clearance 915mm and phase to
earth 610mm
Minimum safety clearance of 2.6m between bare
conductor and live parts
Lightning arrestors –between AB(Air Break)
Switch and D.O(drop out) Fuse
AB switch operating handle- 1m to 1.25m from
ground level
11kV AB switches shall be three insulators types
Indoor Type
Recommended for rating above 630kVA
Only dry type
In case of oil indoor type
free access for fire engines to the transformer
stations
Minimum clearance of 1.5m from building
substation building shall be weatherproof and
fireproof, walls of 355mm thick brick or
230mm thick RCC
AB switch fuse unit/ VCB shall be provided on
the primary side
Minimum size of cable on 11kV side -150 sq.mm
XLPE
Fire separation walls shall be provided in between oil
filled transformers
Oil drainage facility/soak pits shall be insisted for oil
type
All round clearance shall be provided- minimum
1.25m if wall are provided at four sides
Adequate ventilation easy access
Doors and windows of transformer room –non
flammable material
Minimum 50cm headroom clearance
Minimum phase to phase 130mm and phase to ground
80mm clearance of busbars in 11kV panel
Selection of Switchgears
Basic Functions
• Electrical protection( Overload, short
circuits, insulation failure)
• Electrical isolation of a section of the
installation( a gap interposed insulating
barrier between the open contacts)
• Local or remote switching( functional,
emergency switching, emergency stopping,
switching off for maintenance)
Electrical Protection
Protection of circuit elements( against overloading,
provided by fuse or CB)
Protection of persons and livestock( due to insulation
failure, protection through fuses, CBs, ELCB or
RCCB)
Protection of equipment (against overheating , single
phasing, protection through thermal relay)
Electrical isolation- Separate a circuit or equipment
from other installation to carry out work. In the
isolation neutral pole must be opened, provided with
mechanical locking, comply with national standards,
visual indication complete opening of contacts
Switching control
Functional control-Includes all switching operations
during normal conditions for energizing and de-
energizing of a part of a system or installation or
equipment
Emergency control- It is a built in facility to de-energise
a live circuit which could be dangerous to person and
property. Provide large red mushroom headed emergency
stop button, single action guarantee complete switching
off.
Maintenance operation-To enable maintenance work,
stopping or disconnect a piece of equipment or circuit
Switching Devices
1. Isolators-Manually operated ON/OFF switch with
provision for locking and provides safe operation.
Cannot operated under loaded condition
2. Load break switch-Design for operation on loaded
circuit, under normal operating condition. Non-
automatic ON/OFF switching device
3. Contactors-It is a solenoid operated switch which is
held closed by a current through a solenoid coil.
4. Discontactors-A contactor equipped with a thermal
relay for protection against over current is defined as
a discontactors. It is not a CB
5.Changeover switches-Wide application in
situations when the reliability of electrical supply
from utility is low and are used in lighting/industrial
applications wherever continuity of supply is
necessary. ON load as well as OFF load available
6.Automatic transfer switch (ATS)-Automatic
transfer of power. By using Automatic Main
Failure(AMF) system. It is self acting equipment
containing the transfer switching devices and other
accessories for monitoring the supply sources and
for transferring load circuit from one supply to
another.
Material Load Current Fault Current
Density Permitted Density
(A) Permitted (A)
SOLUTION
• MCB or MCCB
• Use 100A MCCB with 100A setting
• Cable: 3.5 Core 35mm2 AYFY Cable
• Starter: Soft Starter with VFD operation
type as the motor is 40HP
• Safety earthing from two points on motor
body using 6 SWG Copper strip.
• An industrial electrical installation has a demand of
50 kW at a power factor of 0.75 lagging. Determine
the rating of the capacitor bank required to improve
the power factor to 0.95 lagging
• Basic idea (1 Mark) Expression (1 Mark) Reactive
power rating of the capacitor bank calculation =
27.66kVAR (3 Marks)
Selective Coordination: Page 194 – 195
MSB: 100A, 63A, 40A, 26A, 16A
(Fault)
• MV Switch Boards Page: 214
• Diesel Generator Set, Change over Switch: Page 185-186
• Automatic Transfer Switch
(ATS)
Cable Voltage Drop Calculation
• Single Phase Loads
• Max V Drop: 3% from DB to Load
• PF=0.8 assumed
• VD = (i*r*l) Volts
• % VD = (V*100)/ VD %
• During measurement of insulation resistance, the transformer must not be connected with any
external lines or lightning arrestor etc.
• Line terminal of the megger is to be connected to one of the HV Bushings of Power transformer
and Earth terminal of megger is to be connected to Power transformer Body Earth Point.
Insulation Resistance Test (contd…)
• IR Values are to be read on the megger by meggering the Power transformer
• i) The above Value is to be noted as HV to Body
• ii) Then IR Value between LV terminal and body of Power transformer is to be measured & noted.
• iv) The temperature of transformer oil at which the IR Values are measured is also to be noted.
• The maximum value shall be 60MΩ at 60°C temperature for transformer which are in
service.
• For new transformer the value obtained shall be tallied with manufactures test
results.
• When insulation resistance falls below specified value, it can often be brought back to
the required value by cleaning and drying.
2. Dielectric Absorption and polarization index Test:
• Oil should be admitted into the transformer from its bottom valve and suction side to be connected to
the top valve to evacuate nitrogen/dry air inside the transformer as the oil fills from the bottom
• Oil sample from the top and the bottom of the tank, selector switch and diverter switch ,tank of the
tap changer and radiator tank etc should be tested.
• The dielectric strength of the transformer oil should be more than 50 KV.
• The polarization index (PI) is defined as the ratio of IR values measured at the intervals of 600 and
60 seconds respectively.
• Whereas, the dielectric absorption is the ratio of IR values measured after 60 sec and 15 sec.
• The Dielectric strength of transformer oil is also known as the breakdown voltage of the transformer
oil. “Breakdown Voltage” (BDV) is measured by observing the voltage that is required to jump a
spark between two electrodes immersed in the oil separated by a specific gap or
• Also known as the sparking strength, the higher the voltage required to jump the spark, the higher the
BDV will be in the oil. The lower the voltage required to jump the spark, the BDV will be lower
indicating the presence of moisture content and other conducting substances in the oil distance.
• A rating of 30 kV is the minimum breakdown voltage at which transformer oil can be safely used in a
power transformer.
• Dielectric strength of oils is also determined by the dielectric loss tangent or “Tan Delta.”
• Oil samples from top oil & bottom oil of Power transformer main tank as well as OLTC tank are to be
collected and tested. Across 2.5 mm gap test Kit, The oil shall stand for KV For/ minute.
3. Measurement of winding resistance at all taps
• To check for any abnormalities due to loose connections, broken strands and high contact resistance in tap
changers.
• LV side ry = yb = br = rn = yn= bn =
• Winding resistance is always defined as the DC‐resistance (active or actual resistance) of a winding in Ohms
(Ω).
• To determine the turns ratio of transformers to identify any abnormality in tap changers/ shorted or
open turns etc.
• Measurement of turn ratio is based on, applying a phase voltage to one of the windings using a
bridge (equipment) and measuring the ratio of the induced voltage at the bridge.
• The measurements are repeated in all phases and at all tap positions, sequentially.
• The ratio test between the HV and LV at all tap positions should also be performed.
• For three winding transformers ratio between other pair of windings should also be taken.
• Where TR is turn ratio. The % deviation of the turn ratios should be ≤ 0.5 %.
• With turns Ratio meter, turns Ratio between HV & LV windings at various
taps to be measured & recorded. At normal tap for 33/11 KV Delta/Star
transformer the turns ratio is 5.196. At other taps values will be as per the
percentage raise or lower at the respective tap positions.
• When “Turns Ratio meter” is not available, Voltage Ratio Test is done at
Various tap position by applying 3 phase LT(415V) supply on 33 KV side of
Power transformer. At Various taps applied voltage and Resultant voltages
LV side between various Phases and phases& neutral measured with
precision voltmeter & noted.
• The tap changer should be undergone the following tests
• Manual operation
• Parallel operation
• The operation should be checked from one end of the range to the other to
check for the limit switch operation also.
• This test is used to determine the phase relationship and polarity of transformers.
• . Polarity test
Polarity test
Vector Group Test
• Magnetic balance test is conducted only on three-phase transformers to check the imbalance in the magnetic circuit.
• 415V, Two phase supply is to be applied to any two phases terminals on HV side of Power transformer and voltages in
other two phase combination are to be measured.
• Sum of the Resultant two values shall be equal to the voltage applied.
• In this test, no winding terminal should be grounded. Otherwise results would be erratic and confusing.
• This test should be done before DC measurements of winding resistance to reduce the effect of residual
magnetism.
• Therefore, transformer under test may be demagnetized before commencement of magnetizing current test.
• The magnetizing current can be measured with milli ammeter by feeding 415 V, three phase 50 Hz supply
from HV side keeping the LV side open circuited and the value in different phases could be compared.
PRE COMMISSIONING CHECKS ON POWER TRANSFORMERS
Check that
1) Top & Bottom valves of radiators are in open position
2) All drain valves are in closed position with dummy plates in position duly fitted with bolts & nuts
3) All filler valves in closed position with dummy plates in position duly fitted with bolts & nuts
4) No oil leakages from radiators, valves, dummies, top cover, inspection covers, oil level gauges etc.
5) Silica gel breather is in position with silica gel filled & oil in oil cup
6) The air path of silica gel breather is free with out any seals to holes of the oil cup
7) Equalizing valve of the interconnecting pipe of vent pipe to conservator tank is in open position
8) Top oil filling point of conservator tank is in closed position with cover duly bolted.
9) The valves on either side of Bucholtz relay are in open position.
10)Thermometer pockets on main tank top cover are having oil inside & Thermometer sensing bulbs are in position duly nuts fixed properly.
11)The double earthing of neutral of Power transformer is done as per standards.
12) The double earthing of body of Power transformer is done as per standards.
13)The oil levels in conservator tank, OLTC Conservator tank.
14)The operation of main Bucholtz relay & OLTC Bucholtz relay ( Trips &alarms to be checked)
15)Operation of Transformer alarms.
16) The operation of PRV to trip the breakers or operation of alarms
17) The vent pipe diaphragm is intact.
18) The lock pieces are provided, duly welded to base channels, for the support wheels of transformers (If wheels are provided)
19)Tightness of all bolts, nuts, clamps, jumpers etc.
• Buchholz Relay Test
• Buchholz relay operation for alarm and trip should also be checked by injecting air to the test pocket provided
in the relay.
• The low oil level alarm of the magnetic oil gauge should be checked.
• The contacts of the Oil Temperature Indicator and Winding Temperature Indicator for alarm trip and control
should be checked and set at required temperature.
• The IR values and setting for operation of oil pumps and fans motor should be checked.
• Alarm trip contact settings of differential pressure gauge, oil and water flow indicators, where provided should
be checked.
• Marshalling Box
• The Marshalling box is the master control panel for protection devices. This panel comes
with a see-through glass door to allow easy visibility of the instruments and their readings.
The panel is situated next to the transformer.
• The wiring from various accessories to the Marshalling kiosk should be checked
• Whenever possible, while commissioning, the voltage should be build up slowly and brought to
the full level in about 4 to 6 hours.
• If the circuit breaker is tripped on differential, Buchholz or any other devices, the cause must be
investigated before re-energizing the transformer. Sometimes tripping occurs maybe because of
magnetic inrush current which depends upon the switching at a particular moment in the cycle.
• A) I) Status of Breaker “Open” Measure IR values between “IN” & “Out” terminals Each limb of breaker shall be more than 3000 MΩ
• II) Status of Breaker “Close” Measure resistant of each limb by connecting “IN” & “Out” terminals to a precision Micro ohm meter. The values shall tally with manufacturer’s test
report.
• III) Status of Breaker “Close” Measure IR values between phase & Body ground terminal of breaker for all limbs the values shall be more than 3000 MΩ
• B) Opening time & closing time tests to be done on all limbs. The values shall tally with test results of the Manufacturer.
• C) As follows:
• c) Primary injection test on current transformer is to be done to check operation of relays functioning of meters.
• d) Check the entire earthing system in the Sub Station is as per standards.
A Few more tests are mentioned below:
• Operational Checks on protection System: Checks whether the protection devices are working good. It checks
on the cooler bank (pumps & Fans), Breathers (silica gel or drycol), MOG, temperature gauges (WTI/OTI),
gas actuated relays (Buchholz, PRD, SPR etc.) and simulation test of the protection system.
capacitance of an insulator indicate abnormal conditions such as the presence of moisture layer, short ‐ circuits
• Vibration measurement: The measurement of vibration is an important control procedure that must be
performed periodically, which can be the result of the movement of the core-spiral assembly and the shielding
structure caused by the variable magnetic forces in time that results in the vibration of the tank and auxiliary
equipment. These vibrations have detrimental effects, such as excessive tension in the core-coil assembly.
• Frequency Response Analysis (FRA) measurement: To evaluate the mechanical integrity of the transformer. Transformers while experiencing the
severity of the short-circuit current lose their mechanical properties by means of deformation of the winding or core. During the precommission, this
test is required to determine that the active part of the Transformer has not suffered any severe impact / shake during transport.
• Floating Neutral point measurement: This test is conducted to ascertain the possibility of the short circuit in a winding.
• Measurement of Short Circuit Impedance: This test is used to detect the winding movement that usually occurs due to a heavy fault current or
mechanical damage during transportation or installation from shipment from the factory.
• Magnetising current measurement: To locate the defect in magnetic core structure, shifting of windings, failures, in turn, to turn insulation or
problems in tap changers. These conditions change the effective reluctance of the magnetic circuit thus affecting the current required to establish the
• Operational check on OLTCs: To ensure smooth & trouble free operation of OLTC during operation.
• Stability of Differential, REF of Transformer/ Reactor: This test is performed to verify the proper functioning of the differential protection and REF
of the transformer and the reactor simulating the actual conditions. Any problem in the CT connection, incorrect wiring, retransmission adjustment
• Tests/ Checks on Bushing Current Transformers (BCTs): To ascertain the healthiness of bushing current transformer at the time of erection
Thank You