Chapter 5 - Risk Analysis
Chapter 5 - Risk Analysis
RISK ANALYSIS
INTRODUCTION
Risk analysis provide knowledge of the relative severity of risks on a project. Its purpose is
to develop agreed priorities for the identified risks.
To convert the consequence and likelihood ratings to an initial priority for the risk.
The output is a prioritized list of risks and a detailed understanding of the impact
upon the success of the project should they occur.
Qualitative analysis is based on nominal or descriptive scales for describing the
likelihoods and consequences of risks.
Quantitative analysis uses numerical ratio scales for likelihoods and consequences,
rather than descriptive scales.
QUALITATIVE RISK ANALYSIS
In performing qualitative analysis consequences are rated in terms of the potential impact
on scope, cost, quality and/or time, often on five-point descriptive scales ( e.g.
insignificant, minor, moderate, major and catastrophic).
Likelihoods are rated in terms of those consequences occurring using a descriptive scale
(e.g. rare, unlikely, possible, likely, almost certain).
Moderate Large impact, but can be managed with effort using standard
procedures
Catastrophic Extreme event, potential for large financial costs or delays, or damage
to the organization’s reputation.
Likelihood Ratings
Likelihood Expected / actual frequency experienced
Rare May only occur in exceptional circumstances; no previous incidence of non-
compliance
Unlikely Could occur at some time; less than 25% chance of occurring.
Almost Can be expected to occur in most circumstances; more than 75% chance of
certain occurring.
Probability/impact matrix/ Risk Assessment Matrix
Consequence
Likelihood
Cost Insignificant cost <10% cost 10%-20% cost 20-40% cost >40% cost
increase increase increase increase increase
Time Insignificant time < 5% time 5-10% time 10-15% time > 15% time
increase increase increase increase increase
Scope Scope decrease Minor areas of Major areas of Scope reduction Project end item is
barley noticeable scope affected scope affected unacceptable to effectively useless
sponsor
Quality Quality Only very Quality reduction Quality reduction Project end item is
degradation barley demanding requires sponsor unacceptable to effectively useless
noticeable applications are approval sponsor
affected
Likelihood ratings
Level Frequency
Very high (5) ≥1 in 2
High ( 4) 1 in 2
Medium (3) 1 in 5
Low (2) 1 in 10
Very Low (1) 1 in 100
OR
Risk factor= L + C – (L*C)
Interval descriptors for risk severity: Cut-off levels are set to provide an initial indication of
priorities based on a set of predetermined risk severity/risk factor categories. .
Due to exposure time is a complicating issue, it is usually ignored in much of risk analysis
except for discounted cash-flow models for investment projects and some quantitative long-
term health project studies.
Qualitative Risk Analysis: Output
The probability impact matrix is used to generate initial priorities (Ranks )for the risks.
Identify and establish a periodic review of the top ten project risk items (Tracking).
Prepare a watch list that includes a list of risks that are low priority, but are still identified as
potential risks.
The aim of quantitative risk analysis is to analyze numerically the probability of each risk occurring and its
consequence on project objectives
Expected Monetary Value (EMV) considers an event’s probability of occurrence and the loss or gain
that will result. It is calculated by multiplying each possible outcome by its probability of occurring and
then adding the result.
Example:
Project Risks 1 – Weather: There is a 25 percent chance of excessive rain fall that’ll delay the
construction for two weeks which will, in turn, cost the project Birr 80,000.
Project Risks 2 – Cost of Construction Material: There is a 10 percent probability of the price of
construction material dropping, which will save the project Birr100,000.
Project Risks 3 – Labor Turmoil: There is a 5 percent probability of construction coming to a halt if
the workers go on strike. The impact would lead to a loss of Birr 150,000. Compute the expected
value.
Risk Probability consequence PXI
(EMV)
Example: The following decision tree illustrates the decision to lease or own your
business with probabilities in which there is uncertainty involved .To determine
whether to lease or to have your own business the decision maker must compute the
expected value at each probability (or circle).
EMV lease= .8x12,0000+0.2x0= $ 96, 000
EMV own business = .05x100,000+ 0.5x80,000 = $90,000
Decision : Lease
Class Activity: Suppose a manager of manufacturing company wants to make a
decision whether to build a new plant or upgrade the existing plant with investments of
$ 120 million and $ 50 million respectively. If he builds a new plant with a 65% of
probability that future demand for product is strong he expects a revenue of $200
million but $90 million if demand is weak. On the other hand, second option of
upgrading the existing plant with a 65% strong demand is assumed to generate
revenue of $120 million, but $60 million if demand is weak.
Draw a Decision Tree showing these choices and advice the manager what she
should do.
Exercise 2 : suppose a farmer must decide what to do with his land for the next
growing season. He can choose to plant corn or soybeans or to not plant anything at
all. If he plants nothing at all, the government farm subsidy will pay him $30 per
acre. If the farmer decides to plant corn or soybeans on his land, there is some risk
involved. The yield per acre depends on the amount of rainfall. Too much rain or too
little rain will give poorer results than the right amount of rainfall. There is a 40
percent probability that the rainfall will be low; there is a 40 percent probability that
the rainfall will be medium; and there is a 20 percent chance that the rainfall will be
high.
If the farmer decides to plant corn, the yield per acre will be $0, $90, and $50,
respectively, if the rainfall is low, medium, or high. If the farmer decides to plant
soybeans, the yield per acre will be $40, $70, and $20, respectively, for low,
medium, and high amounts of rainfall.
Draw a Decision Tree showing these choices and advice the farmer what to do with
his land.