WEEK 3 Presentation
WEEK 3 Presentation
WEEK 3
ABDUL SHAIKH
Ph.D., PMP®
[email protected]
These slides have been created from Effective Project Management, PMBOK® and pmi.org
Project Scope Management
Project Scope Management Knowledge Area
Project Scope Management Knowledge Area includes the processes required to ensure that the
project includes all the work required and only the work required to complete the project
successfully. It is primarily concerned with defining and controlling what is included and what is
not included in the project.
Project Scope
The Project Scope is the work the project team will do to deliver the project’s product. Project scope refers to
everything that must be done to deliver the product.
The project scope encompasses the product scope. The scope must be clearly defined and formally approved
before work starts.
For example, On a project to build a new train terminal, the project scope will be “ a new train terminal that meets
this technical specification, plus all the work needed to deliver the train terminal.”
In other words, the project scope includes the planning, coordination, and management activities (such as
meetings and reports) that ensure product scope is achieved.
These efforts become part of the scope baseline and scope management plan, which are parts of a project
management plan.
Product Scope
Product scope is another way to say “requirements that relate to the product, service, or result of the project.”
It can also be defined as the product deliverables with associated features and functions.
Product scope – not project scope – is defined as the project deliverables.
Let’s look at the train terminal example; the product scope is “a new train terminal that meets these technical
specifications.”
To determine if the project successfully achieved the product scope, the resulting product (the new train terminal) is
compared to the product requirements, which were recorded in the requirements documentation and the project
scope statement.
Note: Product scope refers more narrowly to the features and functions (requirements) of what is being produced. At
the same time, the project scope refers to all the work needed to deliver those features and functions
(requirements).
The product scope is measured against the product requirements.
Project Scope Statement and Statement of Work
Scope Baseline:
The scope baseline is the approved version of a scope statement, Work Breakdown Structure, and its
associated WBS dictionary.
Once approved, it becomes a controlled document, and the scope baseline can be changed only through
formal change control procedures and is used as a basis for comparison.
It is a component of the project management plan.
Stakeholders have input, but the Project team creates the actual Scope Baseline.
Scope Creep and Gold Platting
Scope Creep: The PMBOK Guide describes scope creep as “adding features and functionality (project scope)
without addressing the effects on time, costs, and resources, or without customer approval.” Scope creep refers to
uncontrolled changes in scope due to either interference of the customer/stakeholders or a misunderstanding of the
scope by the project team or the project manager.
Gold Platting: Gold plating refers to intentionally adding extra features or functions to the product which were not
included in the product’s scope.
Following are a few causes of gold plating:
A team member may add extra functions to prove his abilities to the project manager, or the Project manager may add
extra functions to earn credit from the client or the top management. Sometimes, it is performed to divert the client’s
attention from the defects in the product.
Although gold plating sounds good to everyone, there is no gold in gold plating, which is bad for the project team and
the project manager in the long run. Gold plating increases the input cost (though, in many cases, it does not appear to
be high), increases the risk, and increases the customer’s expectation.
If you do another project for the same customer, the customer will again expect you to deliver a product with extra
features. If you do not, the customer will be dissatisfied.
Opportunity Cost
Opportunity Cost:
Opportunity cost is the loss of potential future return from the best alternative project when a choice is required for
several projects.
Opportunity cost in project management is the cost of forgoing one project or activity in favor of another. It is the cost of
not pursuing one option and instead taking another. In other words, it is the cost of the best alternative not chosen.
Opportunity cost can be used to compare the cost of the project to the cost of not doing it or the cost of doing something
else with the same resources.
Since there are limited resources such as humans, time, money, etc., we cannot work on an infinite number of projects
simultaneously. Opportunity cost is a concept to help you judge which project(s) to take and which project(s) NOT to
take based on the relative potential returns of the project(s).
For example, Project A has a potential ROI of $25,000 - Project B has a potential ROI of $20,000 - Project C has a
potential ROI of $10,000
The opportunity cost for selecting Project A for completion over Project B and C will be $20,000 (the “potential loss” of
not completing the second-best project).
Project Scope Management Processes
Define Scope
Collect
5.3
Requirements
Plan Scope
Management 5.2
Create WBS
5.1
5.4
Project Scope Statement (Scope of Work): The project Scope Statement focuses on the project's specific tasks and how they
connect to its overall goal. The scope of work explains the services the winning vendor will provide on a particular project and
the work performed under a contractual agreement.
The project scope statement documents and addresses the characteristics and boundaries of the project and its associated
products and services, as well as product acceptance criteria and scope control.
Project Scope Statement vs. Statement of Work: The statement of work is prepared by the customer while the project
management team develops the scope statement. The statement of work focuses on physical or technical matters, while the
project scope statement focuses on a functional view.
Plan Scope Management
The following are 9 requirements documents that a business may want to use while pushing a project through its stages of
completion;
The scope is the foundation of the cost estimate and project schedule.
The project scope establishes the boundaries of Tasks that are and are not included for the client.
The defined scope process is primarily concerned with what is included and what is not included in the project and its
deliverables (product).
Define Scope is the process of developing a detailed description of the project and product.
This process uses information from the project charter, the scope management plan, the requirements management plan, the
assumption log, and the risk register to define the project and product scope.
Defining scope helps to ensure that the project is properly planned and executed and helps to ensure that it is completed on
time and within budget.
The key benefit of this process is that it describes the product, service, or result boundaries by defining which of the
requirements collected will be included in and excluded from the project scope.
The result and main objective of the Define Scope process is creating the project scope statement.
During the Planning Process Group, a project manager works on defining the project scope
Project Requirements and Project
Scope
Project Requirements:
Project requirements are the specific needs or expectations that must be met for a project to be successful. They are based on
the project objectives and provide the basis for project planning.
For example, a project to design and build a new website might require a database to store customer data, a payment system
to process orders, and a content management system to update the site.
Project Scope:
Project scope defines the boundaries of the project. It is the activities required to meet the project objectives and deliverables.
For example, the scope of the website project could include designing the website, coding the database and payment system,
and testing the website before launch. The scope also includes any limitations or constraints that must be considered, such as
budget, timeline, and resources.
Level 1: The first and the top one of the WBS Levels is the project title.
Level 2: The second one of the WBS Levels is Control Accounts. Control accounts are a project's major parts, systems,
phases, or deliverables. PMI numbering system is also allotted from here.
Level 3: The third one of the WBS Levels is Work Packages. Work packages come together to constitute Control Accounts.
It is a point where it can be reliably scheduled, cost-estimated, monitored & controlled.
Level 4: The last one of the WBS levels is activities. Activities are the tasks assigned to project team member (s) to complete
the work package.
Note: When we are done with breaking down the scope into tasks, at that time, a project manager should identify Staff working
on the project tasks, their roles and responsibilities, and the tasks’ due dates.
WBS Sample
PMI Numbering: PMI numbering starts from Control Accounts, our level 2 of WBS, and then comes to down level (at Level 1, we have
a project title, it doesn't contain any number).
Project Title
1 2
Wedding Function
1 2 3 4
Preparation Ceremony Reception Clean-Up
1.1 1.2 2.1 2.2 2.3 3.1 3.2 4.1 4.2 4.3
1.1.1 1.1.2
Availability
Near Both
On the
Families
Dates
WBS Dictionary
A Work Breakdown Structure Dictionary is a document that describes each element (Task) within a project’s Work
Breakdown Structure (WBS). A WBS dictionary is where the details of the tasks, activities, and deliverables of the work
breakdown structure are located. The content includes resources, cost, and quantity of each task. It also lists the acceptance
criteria for each deliverable/product. It is an output of Create WBS process.
Project
Control Accounts
Activity/Task
Create WBS
Note: Variance analysis is the technique used to find the cause and variance between the agreed baseline
and the actual performance.
PRACTICE QUESTIONS
Practice Question
As part of tracking a project, a project manager is validating the completion of the project scope.
He or she would measure this against:
As part of tracking a project, a project manager is validating the completion of the project scope.
He or she would measure this against:
Completion of project scope is measured against the scope baseline which is a part of the project management plan.
In contrast, the product scope is measured against the product requirements.
Practice Question
While managing a project, you have included the product acceptance criteria in the Quality Management Plan.
While reviewing your plan, a senior manager asks you to reconsider this. You then realize that what you did is
incorrect. Where should you place the product acceptance criteria?
A. Project Charter
B. Change control process
C. Project Scope Statement
D. Scope Verification Plan
Practice Question
While managing a project, you have included the product acceptance criteria in the Quality Management Plan.
While reviewing your plan, a senior manager asks you to reconsider this. You then realize that what you did is
incorrect. Where should you place the product acceptance criteria?
A. Project Charter
B. Change control process
C. Project Scope Statement
D. Scope Verification Plan
The project scope statement documents and addresses the characteristics and boundaries of the project
and its associated products and services, as well as product acceptance criteria and scope control.
Practice Question
Project Scope Management includes the processes required to ensure that the project includes all the work
required and only the work required to complete the project successfully. It is primarily concerned with defining
and controlling what is included and what is not included in the project.
Practice Question
A project manager approaches you to better understand the Work Breakdown Structure (WBS). You tell her that:
A. A WBS is a detailed project plan and includes the effort and resource dates on which the tasks for the project
are complete.
B. A WBS is a task-oriented decomposition of work that identifies tasks and the resources required to
accomplish the task.
C. The WBS is a deliverable-oriented hierarchical decomposition of the project team must accomplish to meet
project objectives.
D. The WBS is a Gantt chart that contains details about the p deliverables the project team must do.
Practice Question
A project manager approaches you to better understand the Work Breakdown Structure (WBS). You tell her that:
A. A WBS is a detailed project plan and includes the effort and resource dates on which the tasks for the project
are complete.
B. A WBS is a task-oriented decomposition of work that identifies tasks and the resources required to
accomplish the task.
C. The WBS is a deliverable-oriented hierarchical decomposition of the project team must accomplish to meet
project objectives.
D. The WBS is a Gantt chart that contains details about the p deliverables the project team must do.
Validate Scope is the process of formalizing acceptance of the completed project deliverables by the customer
or sponsor of the project.
THANK YOU