Chapter4 SPM Project Integration Management
Chapter4 SPM Project Integration Management
© South-Western/Cengage Learning.
All Rights Reserved. 2
Describe project management plan
development, understand the content of these
plans, and review approaches for creating them
Explain project execution, its relationship to
project planning, the factors related to
successful results, and tools and techniques to
assist in project execution
Describe the process of monitoring and
controlling project work
© South-Western/Cengage Learning.
All Rights Reserved. 3
Understand the integrated change control
process, planning for and managing changes on
information technology projects, and developing
and using a change control system
Explain the importance of developing and
following good procedures for closing projects
Describe how software can assist in project
integration management
© South-Western/Cengage Learning.
All Rights Reserved. 4
Project managers must coordinate all of the other
knowledge areas throughout a project’s life cycle
Many new project managers have trouble looking
© South-Western/Cengage Learning.
All Rights Reserved. 5
Develop the project charter: working with
stakeholders to create the document that formally
authorizes a project—the charter
Develop the project management plan:
coordinating all planning efforts to create a
consistent, coherent document—the project
management plan
Direct and manage project execution: carrying
out the project management plan by performing
the activities included in it
© South-Western/Cengage Learning.
All Rights Reserved. 6
Monitor and control the project work:
overseeing project work to meet the
performance objectives of the project
Perform integrated change control:
coordinating changes that affect the project’s
deliverables and organizational process assets
Close the project or phase: finalizing all project
activities to formally close the project or phase
© South-Western/Cengage Learning.
All Rights Reserved. 7
© South-Western/Cengage Learning.
All Rights Reserved. 8
The Airbus A380 megajet project was two years behind
schedule in Oct. 2006, causing Airbus’ parent company to
face an expected loss of $6.1 billion over the next four years
The project suffered from severe integration management
problems, or “integration disintegration...Early this year,
when pre-assembled bundles containing hundreds of miles
of cabin wiring were delivered from a German factory to the
assembly line in France, workers discovered that the
bundles, called harnesses, didn't fit properly into the plane.
Assembly slowed to a near-standstill, as workers tried to
pull the bundles apart and re-thread them through the
fuselage. Now Airbus will have to go back to the drawing
board and redesign the wiring system.”*
*Matlack, Carol. “First, Blame the Software,” BusinessWeek Online (October 5, 2006).
© South-Western/Cengage Learning.
All Rights Reserved. 9
Strategic planning involves determining long-term
objectives, predicting future trends, and projecting
the need for new products and services
Organizations often perform a SWOT analysis
© South-Western/Cengage Learning.
All Rights Reserved. 10
© South-Western/Cengage Learning.
All Rights Reserved. 11
© South-Western/Cengage Learning.
All Rights Reserved. 12
Only one in seven product concepts comes to fruition; why is it
that some companies like Proctor & Gamble, Johnson and
Johnson, Hewlett Packard, and Sony are consistently
successful in NPD?
Because they use a disciplined, systematic approach to NPD projects
based on best practices
Four important forces behind NPD success include the
following:
1. A product innovation and technology strategy for the business
2. Resource commitment and focusing on the right projects, or solid
portfolio management
3. An effective, flexible, and streamlined idea-to-launch process
4. The right climate and culture for innovation, true cross-functional
teams, and senior management commitment to NPD
© South-Western/Cengage Learning.
All Rights Reserved. 13
There are usually more projects than available
time and resources to implement them
Methods for selecting projects include:
◦ Focusing on broad organizational needs
◦ Categorizing information technology projects
◦ Performing net present value or other financial
analyses
◦ Using a weighted scoring model
◦ Implementing a balanced scorecard
© South-Western/Cengage Learning.
All Rights Reserved. 14
It is often difficult to provide strong justification for
many IT projects, but everyone agrees they have
a high value
“It is better to measure gold roughly than to count
pennies precisely”
Three important criteria for projects:
◦ There is a need for the project
◦ There are funds available
◦ There’s a strong will to make the project succeed
© South-Western/Cengage Learning.
All Rights Reserved. 15
One categorization is whether the project
addresses:
◦ A problem
◦ An opportunity, or
◦ A directive
Another categorization is how long it will take to
do and when it is needed
Another is the overall priority of the project
© South-Western/Cengage Learning.
All Rights Reserved. 16
Financial considerations are often an important
consideration in selecting projects
Three primary methods for determining the projected
© South-Western/Cengage Learning.
All Rights Reserved. 17
Net present value (NPV) analysis is a method of
calculating the expected net monetary gain or loss
from a project by discounting all expected future
cash inflows and outflows to the present point in
time
Projects with a positive NPV should be considered if
© South-Western/Cengage Learning.
All Rights Reserved. 18
© South-Western/Cengage Learning.
All Rights Reserved. 19
Note: See the template called business_case_financials.xls
© South-Western/Cengage Learning.
All Rights Reserved. 20
Determine estimated costs and benefits for the life
of the project and the products it produces
Determine the discount rate (check with your
organization on what to use)
Calculate the NPV (see text for details)
Notes: Some organizations consider the investment
year as year 0, while others start in year 1; some
people enter costs as negative numbers, while
others do not
◦ Check with your organization for their preferences
© South-Western/Cengage Learning.
All Rights Reserved. 21
Return on investment (ROI) is calculated by
subtracting the project costs from the benefits and
then dividing by the costs
ROI = (total discounted benefits - total discounted costs) /
discounted costs
The higher the ROI, the better
Many organizations have a required rate of return
or minimum acceptable rate of return on investment
for projects
Internal rate of return (IRR) can by calculated by
finding the discount rate that makes the NPV equal
to zero
© South-Western/Cengage Learning.
All Rights Reserved. 22
Another important financial consideration is
payback analysis
The payback period is the amount of time it will
take to recoup, in the form of net cash inflows,
the total dollars invested in a project
Payback occurs when the net cumulative
discounted benefits equals the costs
Many organizations want IT projects to have a
fairly short payback period
© South-Western/Cengage Learning.
All Rights Reserved. 23
© South-Western/Cengage Learning.
All Rights Reserved. 24
A weighted scoring model is a tool that provides a
systematic process for selecting projects based on
many criteria
Identify criteria important to the project selection process
Assign weights (percentages) to each criterion so they add
up to 100%
Assign scores to each criterion for each project
Multiply the scores by the weights and get the total
weighted scores
The higher the weighted score, the better
© South-Western/Cengage Learning.
All Rights Reserved. 25
© South-Western/Cengage Learning.
All Rights Reserved. 26
Drs. Robert Kaplan and David Norton developed
this approach to help select and manage projects
that align with business strategy
A balanced scorecard:
◦ Is a methodology that converts an organization’s value
drivers, such as customer service, innovation, operational
efficiency, and financial performance, to a series of defined
metrics
See www.balancedscorecard.org for more
information
© South-Western/Cengage Learning.
All Rights Reserved. 27
© South-Western/Cengage Learning.
All Rights Reserved. 28
After deciding what project to work on, it is
important to let the rest of the organization know
A project charter is a document that formally
recognizes the existence of a project and
provides direction on the project’s objectives and
management
Key project stakeholders should sign a project
charter to acknowledge agreement on the need
and intent of the project; a signed charter is a key
output of project integration management
© South-Western/Cengage Learning.
All Rights Reserved. 29
© South-Western/Cengage Learning.
All Rights Reserved. 30
© South-Western/Cengage Learning.
All Rights Reserved. 31
A project management plan is a document used
to coordinate all project planning documents and
help guide a project’s execution and control
Plans created in the other knowledge areas are
© South-Western/Cengage Learning.
All Rights Reserved. 32
Introduction or overview of the project
Description of how the project is organized
Management and technical processes used on
the project
Work to be done, schedule, and budget
information
© South-Western/Cengage Learning.
All Rights Reserved. 33
© South-Western/Cengage Learning.
All Rights Reserved. 34
"The winners clearly spell out what needs to be done in a
project, by whom, when, and how. For this they use an
integrated toolbox, including PM tools, methods, and
techniques…If a scheduling template is developed and used
over and over, it becomes a repeatable action that leads to
higher productivity and lower uncertainty. Sure, using
scheduling templates is neither a breakthrough nor a feat.
But laggards exhibited almost no use of the templates.
Rather, in constructing schedules their project managers
started with a clean sheet, a clear waste of time.”*
*Milosevic, Dragan and And Ozbay. “Delivering Projects: What the Winners Do.”
Proceedings of the Project Management Institute Annual Seminars & Symposium
(November 2001).
© South-Western/Cengage Learning.
All Rights Reserved. 35
Project execution involves managing and
performing the work described in the project
management plan
The majority of time and money is usually spent
on execution
The application area of the project directly affects
© South-Western/Cengage Learning.
All Rights Reserved. 36
Project planning and execution are intertwined
and inseparable activities
Those who will do the work should help to plan the
work
Project managers must solicit input from the team
© South-Western/Cengage Learning.
All Rights Reserved. 37
Project managers must lead by example to
demonstrate the importance of creating and then
following good project plans
Organizational culture can help project execution
by:
◦ Providing guidelines and templates
◦ Tracking performance based on plans
Project managers may still need to break the rules
to meet project goals, and senior managers must
support those actions
© South-Western/Cengage Learning.
All Rights Reserved. 38
General management skills like leadership,
communication, and political skills
Product, business, and application area skills and
knowledge
Use of specialized tools and techniques
© South-Western/Cengage Learning.
All Rights Reserved. 39
Expert judgment: experts can help project managers
and their teams make many decisions related to project
execution
Project management information systems: there are
hundreds of project management software products
available on the market today, and many organizations
are moving toward powerful enterprise project
management systems that are accessible via the
Internet
See the What Went Right? example of Kuala Lumpur’s
Integrated Transport Information System on p. 159
© South-Western/Cengage Learning.
All Rights Reserved. 40
Changes are inevitable on most projects, so it’s
important to develop and follow a process to
monitor and control changes
Monitoring project work includes collecting,
© South-Western/Cengage Learning.
All Rights Reserved. 41
The 2002 Olympic Winter Games and Paralympics took
five years to plan and cost more than $1.9 billion. PMI awarded
the Salt Lake Organizing Committee (SLOC) the Project of the
Year award for delivering world-class games.
Four years before the Games began, the SLOC used a
Primavera software-based system with a cascading color-coded
WBS to integrate planning…The SLOC also used an Executive
Roadmap, a one-page list of the top 100 Games-wide activities,
to keep executives apprised of progress. Activities were tied to
detailed project information within each department’s schedule.
A 90-day highlighter showed which managers were accountable
for each integrated activity.
Fraser Bullock, SLOC Chief Operating Officer and Chief,
said, “We knew when we were on and off schedule and where
we had to apply additional resources. The interrelation of the
functions meant they could not run in isolation—it was a
smoothly running machine.”*
*Foti, Ross, “The Best Winter Olympics, Period,” PM Network (January 2004) 23.
© South-Western/Cengage Learning.
All Rights Reserved. 42
Three main objectives are:
◦ Influencing the factors that create changes to
ensure that changes are beneficial
◦ Determining that a change has occurred
◦ Managing actual changes as they occur
© South-Western/Cengage Learning.
All Rights Reserved. 43
Former view: the project team should strive to do
exactly what was planned on time and within
budget
Problem: stakeholders rarely agreed up-front on
© South-Western/Cengage Learning.
All Rights Reserved. 44
A formal, documented process that describes
when and how official project documents and work
may be changed
Describes who is authorized to make changes and
© South-Western/Cengage Learning.
All Rights Reserved. 45
A formal group of people responsible for
approving or rejecting changes on a project
CCBs provide guidelines for preparing change
© South-Western/Cengage Learning.
All Rights Reserved. 46
Some CCBs only meet occasionally, so it may
take too long for changes to occur
Some organizations have policies in place for
time-sensitive changes
◦ “48-hour policy” allows project team members to make
decisions; then they have 48 hours to reverse the
decision pending senior management approval
◦ Delegate changes to the lowest level possible, but keep
everyone informed of changes
© South-Western/Cengage Learning.
All Rights Reserved. 47
Ensures that the descriptions of the project’s
products are correct and complete
Involves identifying and controlling the functional
and physical design characteristics of products
and their support documentation
Configuration management specialists identify
and document configuration requirements, control
changes, record and report changes, and audit
the products to verify conformance to
requirements
See www.icmhq.com for more information
© South-Western/Cengage Learning.
All Rights Reserved. 48
© South-Western/Cengage Learning.
All Rights Reserved. 49
To close a project or phase, you must finalize all
activities and transfer the completed or cancelled
work to the appropriate people
Main outputs include:
© South-Western/Cengage Learning.
All Rights Reserved. 50
Several types of software can be used to assist in
project integration management
◦ Documents can be created with word processing software
◦ Presentations are created with presentation software
◦ Tracking can be done with spreadsheets or databases
◦ Communication software like e-mail and Web authoring
tools facilitate communications
◦ Project management software can pull everything together
and show detailed and summarized information
◦ Business Service Management (BSM) tools track the
execution of business process flows
© South-Western/Cengage Learning.
All Rights Reserved. 51
Project integration management involves
coordinating all of the other knowledge areas
throughout a project’s life cycle
Main processes include:
© South-Western/Cengage Learning.
All Rights Reserved. 52