0% found this document useful (0 votes)
17 views

09 Project Management in Engineering Design

This document discusses project management techniques for engineering design projects. It describes the Critical Path Method (CPM), a network diagram approach used to plan projects, identify relationships between activities, and determine bottlenecks. Key elements of a CPM diagram include activities, events, and precedence relationships. The document outlines rules for constructing a CPM diagram and determining the critical path, which is the longest sequence of activities such that delaying any activity delays project completion. It also introduces the Program Evaluation and Review Technique (PERT), which assigns probabilistic time estimates to activities to determine project completion probability. Both CPM and PERT are useful for managing engineering design project schedules and accounting for uncertainty.

Uploaded by

Antony Njoroge
Copyright
© © All Rights Reserved
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
17 views

09 Project Management in Engineering Design

This document discusses project management techniques for engineering design projects. It describes the Critical Path Method (CPM), a network diagram approach used to plan projects, identify relationships between activities, and determine bottlenecks. Key elements of a CPM diagram include activities, events, and precedence relationships. The document outlines rules for constructing a CPM diagram and determining the critical path, which is the longest sequence of activities such that delaying any activity delays project completion. It also introduces the Program Evaluation and Review Technique (PERT), which assigns probabilistic time estimates to activities to determine project completion probability. Both CPM and PERT are useful for managing engineering design project schedules and accounting for uncertainty.

Uploaded by

Antony Njoroge
Copyright
© © All Rights Reserved
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 21

PROJECT

MANAGEMENT IN
ENGINEERING DESIGN
CRITICAL PATH METHOD
 Is a graphical network diagram approach to project
planning
 Shows logical precedence relationships
 Attempts to identify major bottlenecks in a project
schedule
Elements of the CPM Diagram
 Activity: Ongoing effort on a project activity for a
specific duration.
 Activities are labelled with name/letter and duration.
 Event: Represents a discrete state (event), or
decision point, etc... and it is assumed the event
consumes ‘no time’. Events are usually not labelled.
Table of Activities, Duration and Precedence
Relations:
GENERAL RULES for CPM diagram
construction:

 Must start at a single “Start” event and end at a single


“Finish/End” event.
 Consecutive activities must be separated by events.
 Any pair of events cannot be connected by more than
one activity, without an intervening event.
 f a single activity (R) must precede several unrelated
activities(S, T, etc...), the relation is depicted as Fig. A:
 If several unrelated activities (S, T, etc...) must precede
an activity (R), the relation is depicted as Fig. B:
Dummy Activities (if necessary):
Approach to using the CPM method:

 (1) Generate the table of “Activities, Duration and


Precedence Relations”.
 This can be done as a team, especially for establishing/
estimating Duration and Precedence of activities.
 (2) Find all activities that have no ‘precedence
requirement’, and draw them using arrows
emanating from “start” event.
 Terminate these arrows with an “event” circle. Scratch
these activities from your table.
Approach to using the CPM method: Cont’d

 (3) Find all activities preceded by the activities


drawn in the previous step.
 Place them as appropriate on the network diagram.
Terminate them with an “event” circle, and scratch
them from the table list.
 (4) Repeat step (3) and ‘iterate and backtrack’ if
necessary.
 (5) All activities must eventually terminate at single
“End” event.
Determining the critical path
 The critical path is defined as:

“The sequence of activities from project start to


project end, such that a delay in any one of those
activities, will delay the completion of the entire
project”
Determining the critical path (Cont’d)

 Determining the ‘critical path’ can be done ‘ad-hoc’ by


tracing the various paths from start to finish.

 Hence, the critical path here is: A-B-F-G-H-K, which is


19 units in duration.
Determining the critical path (Cont’d)

 For more ‘complex CPM diagrams’, there is a systematic


approach to determining the critical path.
 Determine for each activity:
 Earliest Start (ES): The earliest possible time the activity can
begin.
 Project Duration: Least possible time to complete the project.
 Latest Start (LS): The latest possible time activity can begin
without delaying the project.
Defined as:
 Proj.Dur. - (longest possible reverse path to activity)
 Total Float (TF): Defined as (LS - ES)
Determining the critical path: Example
In Summary....
 The project duration is equal to the sum of the
duration of all activities along the critical path.
 The TF for each activity in the Table, is the amount
of time by which that activity can be delayed,
without causing a delay in the project duration.
 The critical path is defined as the sequence of
activities in the Table, for which TF = 0.
 Any delay in an activity that is on the critical path,
will cause a delay in the project duration.
In Summary....
 The CPM has application to very practical problems,
likely to occur during your professional careers.
 Consider the results of Table 7.4. Immediately, you
can see:
 The project has a duration of 19 time-units.
 The critical path is: A-B-F-G-H-K, therefore, you
must “pay special attention to these activities” as a
project manager. If any of these is delayed, the whole
project is delayed!
PERT: Program Evaluation and Review
Technique

 Using PERT, each activity is assigned ‘three time


estimates’ as attributes, which are:
 to (optimistic estimate
 tm (mode (most likely) estimate)
 tp (pessimistic estimate)
 Note: The values to and tp represent the left and
right terminus respectively, of a Beta probability
density function.
PERT Example (Previous Ex.)
Determine Critical Path in PERT
 Similar to CPM, however, the activity duration is
known as “expected time, te”.
 Calculate te for each activity, based on the
weighted average of tm, and the midpoint of (to +
tp)/2. This is done with the formula:
Determine Critical Path in PERT
 The te values are thus;
In Summary PERT....
 The main advantage of the PERT technique, is the
ability to determine the ‘probability’ that a project
will be completed within a specified time, Ts.
 It is thus more realistic
Summary PERT and CPM
 Like CPM, the PERT has application to very
practical and realistic problems, likely to occur
during your professional careers.

 PERT has all the benefits of CPM, plus, you can


make realistic estimations of activity durations that
account for uncertainty in the estimates.

You might also like