0% found this document useful (0 votes)
30 views

Production and Cost Key Concepts 1

This document discusses the critical path method (CPM) for project management. It defines key terms like activities, events, paths and networks. It explains that CPM and PERT techniques are used to analytically schedule project activities based on precedence relationships. The objectives are to complete projects on time using minimal resources. Examples are provided to demonstrate how to draw network diagrams representing activities and how to calculate things like earliest start time, latest finish time, and float. The critical path is identified as the longest path through the network diagram determining the minimum project duration.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
30 views

Production and Cost Key Concepts 1

This document discusses the critical path method (CPM) for project management. It defines key terms like activities, events, paths and networks. It explains that CPM and PERT techniques are used to analytically schedule project activities based on precedence relationships. The objectives are to complete projects on time using minimal resources. Examples are provided to demonstrate how to draw network diagrams representing activities and how to calculate things like earliest start time, latest finish time, and float. The critical path is identified as the longest path through the network diagram determining the minimum project duration.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 10

MINDANAO STATE UNIVERSITY

MGT 203 – QUANTITATIVE ANALYSIS FOR


MANAGEMENT

TITLE: CRITICAL PATH METHOD (CPM)

PREPARED BY: AL-KHAIR U. SANGCOPAN, R.A

OUTLINE OF THE TOPIC

• PROJECT MANAGEMENT
• NETWORK ANALYSIS
• NETWORK TERMINOLOGIES
• OBJECTIVES OF PERT AND CPM
• HOW TO DRAW NETWORK DIAGRAM
• FIND THE CRITICAL PATH, EST, LFT, LST, EFT, FLOAT
PROJECT MANAGEMENT

NETWORK ANALYSIS

Critical Path Method Project Evaluation and


(CPM) Review Technique (PERT)

Project: it is a combinaton of interrelated activities which must be


executed in a certain order before the entire task is completed

Basic requirments of a project:

1. It should be completed without any delay


2. It should use available man-power and other resources as small as
possible
3. It should involve as small investment as possible.
Network Terminologies

1. Activity: it is a physically identifiable part of a project which requires


time and resources for its execution. An activity is represented by
arrow.

2. Event: the beginning and end points of an activity are called events or
nodes. Event does not consume any resource. It is represented by a
circle.
Dij
i j 3. Path: an unbroken chain of activity arrows connecting the intial event
Actiity – (X) to some other event is called path.
Event – (i) Event – (j)
4. Network: it is grapichal representation of ligecally and sequentially
connected arrows and nodes representing activities and events of a
project. Networks are also called as arrow diagram.
Objectives of CPM and PERT is to provide analytic means for scheduling the activities

Steps of technique:

Step – 1: define the activities oof the problem, their precedence


relationship and their time required.

Step – 2: precedence relationship among the activities are represented by


network.

Step – 3: involes specific computations to develop the time schedule for


the project.

Step – 4: the schedule must be revised to reflect the realities on the ground.
How to draw a Network Diagram

Rules for Network Construction: Activity Precedence


1. No two activities should have the same starting and ending event.
2. The activities are put in a logical sequence based on precedence A --
relationship.
3. If needed, use dummy activity to show the logical relationship. B --
4. Each activity is represented once and only once in the network C A
diagram.
5. There is only one starting and ending event in the network diagram.
D A,B
Example – 1: Draw the network diagram for the following activities:

Activ
v ity (A) ity (C
)
A cti 2
:
1 : (DM) 4
:
Activ
ity (B 3 y (D)
) vit
Acti
Example – 2: Draw the network diagram for the following activities:

E
4
A 2 I
C

1 G
D 5
3
B 6 7 8 9
F H J K

Activity Precedence Activity Precedence


A -- G C,D
B -- H G,F
C A I E
D B J H,I
E A K J
F B
Example – 3: Construct a network diagram for a project in which activities have the following precedence:
-A,C,D can start immediately and E>B,C ; F,G>D ; H,I>E,F ; J>I,G ; K>H; B>A

Activity Precedence Activity Precedence


A -- G D
B A H E,F
C -- I E,F
D -- J I,G
E B,C K H
F D

A 2
6
B

H
C E K
1 4 5
I
D
3 F
7 8
G J
Example – 3: Construct a network diagram, find the critical path, EST, LFT, LST, EFT, FLOAT

Activity Duration
1-2 13
13 15
2
1-3 12
2
1 5 2-4 2
4
3-4 8
12 3 2
8 2-5 15
PATH 1: CRITICAL PATH 28 W
4-5 2
1- 2 – 5 = 13 +15 = 28 W
PATH 2:
1 – 2 – 4 – 5 = 13 + 2 + 2 = 17 W
PATH 3:
1 – 3 – 4 – 5 = 12 + 8 + 2 = 22 W
;KKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKK
Example – 3: Construct a network diagram, find the critical path, EST, LFT, LST, EFT, FLOAT
KKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKK
KKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKK
KKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKK
Activity Duration
KKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKK
1-2 13
KK 13 15
2
KKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKK 1-3 12
13 13 2
1 5 2-4 2
4
0 0 28 28 3-4 8
12 3 20 26 2
EST LFT 8 2-5 15
12 18
4-5 2

1. Forward pass  MAX


2. Backward pass  MIN
;KKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKK
Example – 3: Construct a network diagram, find the critical path, EST, LFT, LST, EFT, FLOAT
KKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKK
KKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKK
FF = EST - EST - D
KKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKK
KKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKK
KK 13 1 5
LFT – EFT (OR) LST - EST IF EST – LFT - D
2
KKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKKK
13 13 2
1 5
4
0 0 28 28
12 3 20 26 2
EST LFT 8
12 18

ACTIVITY DURATION EST EFT LST LFT TOTAL FREE INDEPEND


(EST+D) (LFT-D) FLOAT FLOAT ENT FLOAT

1-2 13 0 13 0 13 0 0 0

1-3 12 0 12 6 18 6 0 0

2-4 2 13 15 24 26 11 5 5

3-4 8 12 20 18 26 6 0 0

2-5 15 13 28 13 28 0 0 0

4-5 2 20 22 26 28 6 6 0

You might also like