This document summarizes the methods of load estimation according to the Egyptian Electrical Code. It discusses using the build-up area method to estimate the electrical load of a university building. The total connected load was calculated to be 1604 KVA by multiplying the area of each floor by the standard load value. The total demand load was determined to be 1000 KVA by applying diversity factors to account for simultaneous loading.

Uploaded by

antonsaad300
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
87 views

Load Estimation

This document summarizes the methods of load estimation according to the Egyptian Electrical Code. It discusses using the build-up area method to estimate the electrical load of a university building. The total connected load was calculated to be 1604 KVA by multiplying the area of each floor by the standard load value. The total demand load was determined to be 1000 KVA by applying diversity factors to account for simultaneous loading.

Uploaded by

antonsaad300
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 6

Load Estimation according to EGY.

Code.
1

Content.
• 1- Methods of load estimation.

• 2- According to EGY. Code.

• 3- Excel sheet.
2

The Methods of Load estimation.


• 1- Build up area  Calculate the gross interior area of the building,
Determine the load density according to type of the building (from tables /
Codes or standards), and Multiply gross interior area by its load density to
get the estimated electrical load for this building.

• 2- Space by space  Divide the building into different spaces based on its function
(for example, office, storage, mechanical, and corridor).

• 3- Load types  Divide the whole building loads into different types (for example,
Lights, Power, mechanical, ……..).
3

Our Project ( Using Build up Area )


4

The Load estimation for Our Building.


University
Floor Type Area(m)2 Standard (VA/m2) KVA Total Connected Load (KVA)= 1604
Lower Ground 2732 100 273.2
Ground 2769 100 276.9
First 2974 100 297.4
Second 2382 100 238.2
Total Connected Load 1086
Total Demand Load (KVA) = 1604*0.8
= 1284
Electromechanical Loads Total Demand Load (KVA) = 1284*0.8
Type Qty. Load power/unit T.D.L = 998.4  1000 KVA
lifts 3 9 27
Pump 4 5 20
For Transformer Dry Type (KVA) =1000
HVAC - - 471.72
Total (KVA) 518.72