Path Events
A 1247
B 12567
C 1347
D 13567
Table:
Paths through the Copyright@Robson
Oct 21, 2023
house-building network 11
The Project Network
The Critical Path
The critical path is the longest path through the network; the
minimum time the network can be completed. From
Figure :
Path A: 1 2 4 7 3 + 2 + 3 + 1 = 9 months
Path B: 1 2 5 6 7 3 + 2 + 1 + 1 + 1= 8 months
Path C: 1 3 4 7 3 + 1 + 3 + 1 = 8 months
Path D: 1 3 5 6 7 3 + 1 + 1 + 1 + 1 = 7 months
Oct 21, 2023 Copyright@Robson 12
The Project Network
Activity Start Times
Figure: Activity-on-node
Oct 21, 2023 Copyright@Robsonconfiguration 14
The Project Network
Activity Scheduling : Earliest Times
■ ES is the earliest time an activity can start:
ES Maximum{EF immediate predecessors}
Activity LS ES LF EF Slack, S
*1 0 0 3 3 0
*2 3 3 5 5 0
3 4 3 5 4 1
*4 5 5 8 8 0
5 6 5 7 6 1
*Critical path
6 7 6 8 7 1
*7 8 8 9 9 0
Activity Slack Times for House Building Project using QM for Windows
The Project Network
Activity Slack Time (2 of 2)
Beta Distribution
Probability
a m b Time
Optimistic Mean Pessimistic
Task 2 3 6 9
Task 3 1 3 5
Task 4 2 4 12 Task 1
Task 5 2 3 4 Task 2
Task 6 3 4 5 Task 3
Task 7 2 2 2 Task 3
Task 10 1 4 7 Task 4
Task
Oct 21,11 1
2023 10 13 Task 7 Task 8
Copyright@Robson Task 9 30
Probabilistic Activity Times
The Southern Textile Company
Normal
Oct 21, 2023 distribution of network duration
Copyright@Robson 38
Probability Analysis of a Project Network
The Southern Textile Company
Probability
Oct 21, 2023that the network will be completed in 30 weeks or less
Copyright@Robson 39
Probability Analysis of a Project Network
The Southern Textile Company
What is the probability that the new order
processing system will be ready by 30 weeks?
25weeks
2 6.9
6.9 2.63
x Z value of 1.90 corresponds to
Z probability of .4713 in Table A.1,
Appendix A. The probability of
30 25 completing project in 30 weeks or
Z 1.90 less:
2.63
(.5000 + .4713) = .9713.
Oct 21, 2023 Copyright@Robson 40
Probability Analysis of a Project Network
The Southern Textile Company
Probability
Oct 21, 2023 the network will be completed in 22 weeks or less
Copyright@Robson 41
Probability Analysis of a Project Network