0% found this document useful (0 votes)
17 views

Rotating Alignment

The document discusses the procedure for aligning rotating machinery. It outlines important considerations before starting alignment such as ensuring low runout and deciding which machine will move. The alignment procedure involves taking initial readings, checking for validity, measuring and correcting for sag, calculating shim requirements to correct radial and axial misalignment, moving the machinery as required, and taking a final reading. Both radial and axial alignment should be performed together for best results.

Uploaded by

abhishek jha
Copyright
© © All Rights Reserved
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
17 views

Rotating Alignment

The document discusses the procedure for aligning rotating machinery. It outlines important considerations before starting alignment such as ensuring low runout and deciding which machine will move. The alignment procedure involves taking initial readings, checking for validity, measuring and correcting for sag, calculating shim requirements to correct radial and axial misalignment, moving the machinery as required, and taking a final reading. Both radial and axial alignment should be performed together for best results.

Uploaded by

abhishek jha
Copyright
© © All Rights Reserved
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 16

ROTATING -ALIGNMENT

IMPORTANT CONSIDERATION BEFORE STARTING ALIGNMENT


IMPORTANT CONSIDERATION BEFORE ALIGNMENT

• Make sure that runout at the shaft as well as coupling is les than 0.05mm ON both
machines( Runout should not exceed 0.05mm).
• Decide which machine will be kept stationary and which one will be moved. Generally, for a motor
pump combination , pump is kept stationary, for turbine-pump combination , turbine is kept
stationary.
• Check for rusty or broken shims /too many shims under the supports legs. Number of shims should
not exceed four.
• Make provision for moving the machinery ( both sidewise and up-down motion)for sidewise
motion, using jack bolt is the preferred method. For up-down motion , wedging at the appropriate
place is done and then shims are kept below the legs.
ALIGNMENT PROCEDURE( TAKING ALIGNMENT READINGS )-
STEP NO. 1

• Dial pointer should preferably kept on the machine to be moved.


• The sum total of both side readings should be same as sum total of top bottom readings. In actual
practices, we can allow a difference of about 15 %. This rule is called validity Rule.
For examples, 0.00
sum total of side reading = 0.15+0.25 = 0.40
0.15 0.25 sum total of top bottom readings =0.00 +0.36=0.36
Difference =0.40-0.36 = 0.04
0.36 This difference should be less than 15% = 15% of 0.40 = 0.06
Thus difference is less than 15% hence alignment reading is valid.
ALIGNMENT PROCEDURE( TAKING ALIGNMENT
READINGS )- STEP NO. 1

• Alignment correction should be attempted only when sum total of


side readings and top bottom readings are matching within 15% as
shown in the above Examples.
WHAT CHECKS TO DO IF ALIGNMENT READINGS ARE FOUND
INVALID:

• Check the clamp for looseness. If found loose , tighten.


• Check the dial pointer is leaving contact contact during rotating. If so, do rough
alignment with straight edge first.
• check the coupling for eccentricity / ellipticity and shaft for runout, rectify , and rotate
both shafts together.
• if still alignment readings are found invalid, it means that there is sag in the dial clamp.
SAG MEASUREMENT AND CORRECTION

• This step is to be carried out only if the sum total of side readings is not
matching with the sum total of top- bottom readings.
• The movement of clamp causes change in dial readings. Due to this
change , sum total of top –bottom readings does not match with sum total
of side readings. The effect is called SAG.
ALIGNMENT PROCEDURE:- STEP NO. 2

• How to remove sag error from the alignment readings:


• Measure the value of SAG with the help of SAG measurement setup.
• This SAG value will be Negative.
• Add the SAG value to the Alignment Readings.
• As we can see, Sum total of top-bottom readings & side readings is not matching. All
three checks , given in step no. 1 have been done. Still difference is coming dial readings
from the SAG measurement setup. It means there is SAG of 0.08mm.
• Now Sum total of side readings and top bottom Readings is matching. Now , we can
proceed to step no. 3 of alignment procedure.
ALIGNMENT PROCEDURE –STEP NO. 3
(CALCULATION MACHINERY MOVEMENT)

• Important : for best results , radial and axial alignment correction should be done together. A table
for this purpose is shown as follow:-
• Amount of shims required
front leg Rear leg
For radial alignment A (mm) A(mm)
For axial alignment B( mm) C(mm)
Total alignment correction A+B (mm) A+C (mm)
ALIGNMENT PROCEDURE – STEP NO. 3A
(CALCULATING RADIAL MISALIGNMENT)

• Radial correction value is half of the total indicator reading.


• For example : 0.00
+0.20
• Dial is clamped on pump coupling and pointer is on motor coupling.
• Dial is set to zero at upper position.
• Dial is reading +0.20 mm at lower position.
• This means that motor shaft is down( +sign means dial pointer has got Compressed).
• Thus motor shaft will have to be lifted up by +0.20/2=+0.10 mm . That is, shimming of 0.10mm is
required at all the four legs.
ALIGNMENT PROCEDURE – STEP NO. 3A

• Important :-
For Radial misalignment correction , the value of shimming
required will be same for all the four legs , as we saw in the above
examples.
ALIGNMENT PROCEDURE :- STEP NO. 3B

• D=diameter on which the dial is moving.(approx. equal to coupling diameter).


• L1= Distance at front leg from motor coupling.
• L2=Distance at back leg from the motor coupling.
• Shimming required at front / back leg= L1& L2*dial reading /D
• For example:- 0.00

+0.30 mm
• D =100 mm
• L1= 200 mm ; L2 =400 mm .
• This means that top gap between coupling is more than bottom Gap(+ sign means dial pointer has got
compressed).
ALIGNMENT PROCEDURE :- STEP NO. 3B
( CORRECTING AXIAL MISALIGNMENT)

• Thus motor shaft will have to be lifted up.


• Shimming required at front leg = L1*dial reading /D
= 200 *0.30/ 100 = 0.60 mm
• Shimming required at back leg =L2 *Dial reading/D
= 400* 0.30/100 =1.20 mm
• For axial misalignment correction , the amount of shims required to be added or removed is
different for the front legs and back leg
ALIGNMENT PROCEDURE :- STEP NO. 3C
(CORRECTING TOTAL MISALIGNMENT )

• As per our example, the top bottom readings are :- 0.00 0.00
R A
0.20 0.30
• Shimming required for radial & axial misalignments respectively have been calculated on the previous slides. The total
shimming required is calculated as follow:-
• Amount of shims required in
Front leg Rear leg
To correct radial alignment +0.10 mm +0.10 mm
To correct axial alignment +0.60 mm +1.20 mm
To alignment correction 0.10 + 0.60= 0.70 mm 0.10 + 1.20= 1.3mm
Thus in order to do total(radial + axial) alignment, put shim of 0.70mm in front leg and 1.3mm in back leg of motor in out
example
ALIGNMENT PROCEDURE:- STEP NO. 4
( MOVING THE MACHINERY)

• For top to bottom movement shims are added or removed from below the feet of the
machine to be moved. For this purpose, the machine is lifted up by wedging , and then shims
are added or removed.
• For side wise movement, using jack bolts is the preferred method. A light hammer can also
be used on small machines. The movement should be closely monitored by two dial gauges.
• After making the required movement, one final alignment reading should be taken.
CONCLUSION

• We have to see that it is very convenient to do radial and axial alignment correction together.
• Hence , we can say that ultimately there are only two types of misalignments- top-bottom(radial +
axial) misalignment and side wise (radial+ axial) misalignment.
• For best results top-bottom alignment should be done first , followed by side wise alignment. The
reason is that if you do side wise alignment first, then while doing top-bottom alignment, side wise
alignment will again get disturbed.
• How ever, if during step no. 1:- (taking alignment readings) it is found that side wise misalignment
is very large as compare to top-bottom misalignment, then rough alignment (of side wise) should be
done first. After that final top-bottom alignment and then final side wise alignment should be done.
CONCLUSION

• Remove coupling guards and coupling spool piece if necessary . Measure the shaft and coupling
hub run out on both units. Inspect coupling for any damaged or worn parts. Keep track of the
coupling parts and label then if necessary . If equipment's is going to be removed for servicing,
make punch marks on casing and baseplate as a reference during reinstallation.
• Check for soft foot, casing or frame warpage, excessive static piping or conduit forces, damaged
or rusty shims, loose foundation bolt. etc. correct any of the potential problem areas.
• Take and record a set of alignment reading.
• Calculate and perform the necessary axial , vertical and horizontals move, recheck alignment ,
calculate and move until equipment is within acceptable alignment tolerance foundation bolts to
required value. Record final alignments reading.

You might also like