Rotating Alignment
Rotating Alignment
• Make sure that runout at the shaft as well as coupling is les than 0.05mm ON both
machines( Runout should not exceed 0.05mm).
• Decide which machine will be kept stationary and which one will be moved. Generally, for a motor
pump combination , pump is kept stationary, for turbine-pump combination , turbine is kept
stationary.
• Check for rusty or broken shims /too many shims under the supports legs. Number of shims should
not exceed four.
• Make provision for moving the machinery ( both sidewise and up-down motion)for sidewise
motion, using jack bolt is the preferred method. For up-down motion , wedging at the appropriate
place is done and then shims are kept below the legs.
ALIGNMENT PROCEDURE( TAKING ALIGNMENT READINGS )-
STEP NO. 1
• This step is to be carried out only if the sum total of side readings is not
matching with the sum total of top- bottom readings.
• The movement of clamp causes change in dial readings. Due to this
change , sum total of top –bottom readings does not match with sum total
of side readings. The effect is called SAG.
ALIGNMENT PROCEDURE:- STEP NO. 2
• Important : for best results , radial and axial alignment correction should be done together. A table
for this purpose is shown as follow:-
• Amount of shims required
front leg Rear leg
For radial alignment A (mm) A(mm)
For axial alignment B( mm) C(mm)
Total alignment correction A+B (mm) A+C (mm)
ALIGNMENT PROCEDURE – STEP NO. 3A
(CALCULATING RADIAL MISALIGNMENT)
• Important :-
For Radial misalignment correction , the value of shimming
required will be same for all the four legs , as we saw in the above
examples.
ALIGNMENT PROCEDURE :- STEP NO. 3B
+0.30 mm
• D =100 mm
• L1= 200 mm ; L2 =400 mm .
• This means that top gap between coupling is more than bottom Gap(+ sign means dial pointer has got
compressed).
ALIGNMENT PROCEDURE :- STEP NO. 3B
( CORRECTING AXIAL MISALIGNMENT)
• As per our example, the top bottom readings are :- 0.00 0.00
R A
0.20 0.30
• Shimming required for radial & axial misalignments respectively have been calculated on the previous slides. The total
shimming required is calculated as follow:-
• Amount of shims required in
Front leg Rear leg
To correct radial alignment +0.10 mm +0.10 mm
To correct axial alignment +0.60 mm +1.20 mm
To alignment correction 0.10 + 0.60= 0.70 mm 0.10 + 1.20= 1.3mm
Thus in order to do total(radial + axial) alignment, put shim of 0.70mm in front leg and 1.3mm in back leg of motor in out
example
ALIGNMENT PROCEDURE:- STEP NO. 4
( MOVING THE MACHINERY)
• For top to bottom movement shims are added or removed from below the feet of the
machine to be moved. For this purpose, the machine is lifted up by wedging , and then shims
are added or removed.
• For side wise movement, using jack bolts is the preferred method. A light hammer can also
be used on small machines. The movement should be closely monitored by two dial gauges.
• After making the required movement, one final alignment reading should be taken.
CONCLUSION
• We have to see that it is very convenient to do radial and axial alignment correction together.
• Hence , we can say that ultimately there are only two types of misalignments- top-bottom(radial +
axial) misalignment and side wise (radial+ axial) misalignment.
• For best results top-bottom alignment should be done first , followed by side wise alignment. The
reason is that if you do side wise alignment first, then while doing top-bottom alignment, side wise
alignment will again get disturbed.
• How ever, if during step no. 1:- (taking alignment readings) it is found that side wise misalignment
is very large as compare to top-bottom misalignment, then rough alignment (of side wise) should be
done first. After that final top-bottom alignment and then final side wise alignment should be done.
CONCLUSION
• Remove coupling guards and coupling spool piece if necessary . Measure the shaft and coupling
hub run out on both units. Inspect coupling for any damaged or worn parts. Keep track of the
coupling parts and label then if necessary . If equipment's is going to be removed for servicing,
make punch marks on casing and baseplate as a reference during reinstallation.
• Check for soft foot, casing or frame warpage, excessive static piping or conduit forces, damaged
or rusty shims, loose foundation bolt. etc. correct any of the potential problem areas.
• Take and record a set of alignment reading.
• Calculate and perform the necessary axial , vertical and horizontals move, recheck alignment ,
calculate and move until equipment is within acceptable alignment tolerance foundation bolts to
required value. Record final alignments reading.