Lesson 6 Close The Project - Phase
Lesson 6 Close The Project - Phase
CLOSE THE
PROJECT/PHASE
• Project/Phase Closure
• Benefits Realization
• Knowledge Transfer
Version 3.1 | 2023 Release Copyright 2023© Project Management Institute, Inc. All rights reserved.
This material is being provided as part of a PMI® course.
Learning Objectives
• Define the reasons and activities related to the closure of a phase or a project.
• Explain the benefits gained from a project or phase, and how they are managed,
sustained, etc.
• Examine the reasons for knowledge transfers and how they relate to the closure of
a phase or project.
3
Why Projects
or Phases Stakeholders accept deliverables based on acceptance
criteria established at the beginning of the project in
Close the project management plan
Fulfillment Acceptance criteria may be modified during a project life
cycle
Use the requirements traceability matrix to ensure
completion and approval of all requirements
These activities are part of the Close Project or Phase process and are typically
included in the project management plan and in the WBS, under the project
management function. Copyright 2023© Project Management Institute, Inc. All rights reserved.
This material is being provided as part of a PMI® course.
6
Transition
s
(Handovers) Deliverables are handed to the customer or owner.
Transition/handover specifications for deliverables are in the
project management plan.
• Some
organizations
use a rollout or
transition
plan. A tailored solution that delivers value — most likely in an
• This is not a incremental way — to the organization.
project
management
plan
component.
Every iteration output is handed to the product owner.
13
Benefits Realization
TOPIC B
14
Early and
Long-Term
Benefits Benefits accrue at various stages depending on:
• Project life cycle used
Realization • Nature of the project work
• Intended outcomes
Provides planned performance Compares actual performance to planned Uses metrics chosen with team to measure
data performance, including KPIs performance
• Using the chosen metrics, the product owner reports on progress for each
tangible benefit
• For intangible benefits, a subjective (qualitative) determination may be
more useful
• Reporting should include:
• For tangible benefits—progress toward being met
21
Knowledge Transfer
TOPIC C
22
Knowledge Management
During Closing
• Conduct retrospectives or final
lessons learned meetings
• Archive all project information
• Finalize lessons learned register
• Add the lessons learned to the
knowledge management/lessons
learned repository
• Transition knowledge from project team
to the customer
Learned
Include the following topics from the project’s
lessons learned register in the final report:
• Scope changes
• Schedule impacts
• Risks and issues
• Stakeholder relationships
• Vendor relationships
• Artifacts
• Recommendations
Scope
objectives Document scope evaluation criteria and give evidence of met completion criteria
Quality Describe evaluation criteria for project and product quality. Verify objectives are met,
objectives give actual milestone delivery dates and reasons for any variances
Cost objectives Restate acceptable cost range, give actual costs and reasons for any variances
Validation Include required approvals for final product, service or result—e.g., user satisfaction
information survey results
Schedule Verify project objectives were completed on time; report on any variance and effects of
objectives the variance
Benefits State how the final product, service or result achieved the business needs and
realization expected benefits; if partial, give details of variance and fulfillment schedule
Risks or issues
encountered List risks and issues and state how they were addressed
28
End of Lesson 6
29