SPECIFICATIONS
Clear height of rooms: 12’
Clear height of Verandah: 10’-0”
Plinth level: 1’-6”
Thickness of roof slab: 4”
Thickness of RCC shade: 3”
Depth of RCC Beams in Verandah: 1’-6” below verandah slab
Parapet wall: 1’-0” (Clear height above roof tiles)
Ventilators (4 No.): 2’-6” x 1’-6”
RCC lintel: 6” in depth
Damp proof coarse: 1 ½”thick PCC (1:2:4) + 2 coats of hot
bitumen + polythene sheet
Full foundation up to plinth level along verandah periphery is
provided
Internal finishes: Three coats of white wash/distemper paint
External finishes: Three coats of Weather shield paint
Center to Center Lengths
1 Earthwork for
excavation
in
foundation
trenches
L1 3 25’-7 ½ //
2’-6” 3’-6” 224.22 cft 672.66 cft L = 23’-1 ½”+2’-6” = 25’-7 ½”
S1 2 10’-3” 2’-6” 3’-6” 89.69 cft 179 .38 cft L = 12’-9”-(2’-6)” = 10’-3”
1st step 3 24’-7 ½ ” 1’-6” 0’-6” 18.47 cft 55.40 cft L = 23’-1½”+(1’-6”) = 24’-7½”
2nd step 3 24’-3” 1’-1 ½ “ 0’-6” 13.64 cft 40.92 cft L = 23’-1½”+(1’-1½”) = 24’-3”
3rd step up to plinth 3 23’-10 ½” 0’-9” 3’-4 ½” 60.43 cft 181.30 L = 23’-1½”+(0’-9”) =
level cft 23’-10½”
D = 2’-0” +(1’-6”) –(0’-1 ½”)
= 3’-4 ½”
Total= 277.62
cft
(b) S1
1st step 2 11’-3” 1’-6” 0’-6” 8.44 cft 16.88 cft L = 12’-9”-(1’-6”) = 11’-3”
2nd step 2 11’-7 ½ ” 1’-1 ½ ” 0’-6” 6.54 cft 13.08 cft L = 12’-9”-( 1’-1½”) = 11’-7½”
3rd step up to plinth 2 12’-0” 0’-9” 3’-4 ½ ” 30.37 cft 60.75 cft L = 12’-9”-( 0’-9”) = 12’-0”
level
1st step 1 11’-3” 1’-1 ½ ” 0’-6” 6.33 cft 6.33 cft L = 12’-9”-(1’-6 ”) = 11’-3”
2nd step 1 11’-7 ½ ” 0’-9 ” 0’-6” 4.36 cft 4.36 cft L = 12’-9”-( 1’-1½”)= 11’-7½”
3rd step up to plinth 1 12’-0” 0’-4 ½ ” 3’-4 ½ ” 15.19 cft 15.19 cft L = 12’-9”-( 0’-9”) = 12’-0”
level
Total= 25.88 cft
(d)S3
1st step 2 6’-6” 1’-6” 0’-6” 4.87 cft 9.75 cft L = 8’-0”-(1’6”) = 6’-6’
2nd step 2 6’-10 ½ ” 1’-1 ½” 0’-6” 3.86 cft 7.73 cft L = 8’-0”-(1’-1½”) = 6’-10½”
3rd step up to plinth 2 7’-3” 0’-9” 3’-4 ½ ” 18.35 cft 36.70 cft L = 8’-0”-(0’-9”) = 7’-3”
level
Total= 54.18 cft
1st step 1 23’-10 ½” 2’-0” 0’-6” 23.88 cft 23.88 cft L = 23’-1½”+(0’-4½”) +
(0’-4½”) =23’-10½”
Verandah columns 3 0’-9” 0’-9” 8’-6” 4.78 cft 14.34 cft H=10’-0”- (1’-6”)=8’-6”
(i) L1 1 23’-10 ½” 0’-9” 1’-6 ½” 27.60 cft 27.60 cft H = 0’-4” (Earth filling) + 0’-
1” (Mud plaster) +
0’-1½” (Tiles) + 1’-0” (P.
walls) = 1’-6½”
(ii) S3 2 7’-3” 0’-9” 1’-6 ½ ” 8.38 cft 16.76 cft
+(0’-4 ½ “) = 22’-½“
Note:
Materials
(i) Cement=154x1x288.34/(100x13) = 34.15cft
(ii) Sand=154x4x288.34/(100x13) = 136.62 cft
(iii) Coarse aggregate
=154x8x288.34/(100x13) = 273.25 cft
3. Ist Class Burnt brick work in foundation
in cement sand mortar (1:6)
Quantity of BOQ item No.4 = 484.21 cft
Material
(i) Bricks=1350x484.21/100 = 6537 Nos.
(ii) Cement=30x1x484.21/(7x100) = 20.75 cft
(iii) Sand=30x6x484.21/(7x100) = 124.51cft
4. 1 ½” thick PCC (1:2:4) in DPC including
two coats of hot bitumen & 2 sheets of
Polythene.
Quantity of BOQ item No.5=55.50x0.125 = 6.93 cft
Note: (i) Dry material for 100 cft of cement concrete = 154 cft
(ii) Bitumen for 100 sft of DPC (first coat) = 15 Kg
(iii) Bitumen for 100 sft of DPC (second coat) = 10 Kg
Material
(i) Cement=154x1x6.93/(100x7) = 1.52 cft
(ii) Sand=154x2x6.93/(100x7) = 3.04 cft
(iii) Coarse aggregate=154x4x6.93/(100x7) = 6.09 cft
(iv) Bitumen =25x55.50/100 = 13.87 Kg
(v) Polythene Sheet (2 x 55.5) = 111.0 sft
5. Ist Class Burnt brick work in Super
structure in cement sand mortar (1:4)
Note: (i) Bricks for 100 cft of brick work = 1350 Nos.
Material
Materials
(i) Cement=154x1x226.39/(100x7) = 49.80 cft
(ii) Sand=154x2x226.39/(100x7) = 99.61 cft
(iii) Coarse aggregate
=154x4x226.39/(100x7) = 199.22 cft
(iv) Mild steel round bars = 1529 lbs
= 693.55 Kg
(Note: 1 Kg = 0.454 lbs)
7. Roof insulation
Quantity of BOQ item No.9 = 430.72 sft
Note: (i) Brick tiles for 100 sft roof insulation = 360 Nos.
(ii) Dry mortar for 100 sft = 9.00 cft
(iii) Bitumen for 100 sft of DPC (first coat) = 15 Kg
(iv) Bitumen for 100 sft of DPC
(second coat) = 10 Kg
Material
(i) 1 ½” thick brick tiles = 1551 Nos.
(ii) Cement=9x1x430.72/(4x100) = 9.69 cft
(iii) Sand=9x4x430.72/(4x100) = 29.07 cft
(iv) Bitumen =430.72/100 = 107.68 Kg
(v) Mud /Earth filling=430.72x0.42 = 180.90 cft
(Vi) Polythene sheet (2 x 430.72) = 862 sft
8. Sand under floors
Quantity of BOQ item No.10 = 213.11 cft
Material
Sand = 213.11 cft
9. 1 ½” thick cement concrete (1:2:4) in
floors
Quantity of BOQ item No.12=457.80x0.125 = 57.23 cft
Note: Dry mortar for 100 sft of ½” thick cement plaster = 6 cft
Material
(i) Cement=6x1x 3197.07/(4x100) = 47.96 cft
(ii) Sand=6x3x 3197.07/(4x100) = 143.87 cft
Material
(i) Timber for doors =13x56/100 = 7.28 cft
(ii) Timber for windows and Ventilators = 5.04 cft
=8x63/100
Total = 13.32 cft
12. White wash / Distemper
Quantity of BOQ item No.16 = 1872.9 sft
Note: Lime for 100 sft of white wash (one coat) = 1.00 Kg
Material
Lime for three coats=1x3x1872.9/100 = 56.24 Kg
Material
Earth for filling = 230.87 cft
2- SUMMARY
S.No. Description of material Quantity