Estimation of Simple Building

This document provides specifications and measurements for estimating the cost of building construction. It includes details like room heights, slab thicknesses, beam depths, and finishes. Foundation specifications include a 1’6” plinth level and 1.5” thick damp proof course. Dimensions are provided to calculate quantities of excavation, filling, concrete, and bricks for the foundation, plinth, and wall construction.

Uploaded by

Iqrar Ali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
30 views

Estimation of Simple Building

This document provides specifications and measurements for estimating the cost of building construction. It includes details like room heights, slab thicknesses, beam depths, and finishes. Foundation specifications include a 1’6” plinth level and 1.5” thick damp proof course. Dimensions are provided to calculate quantities of excavation, filling, concrete, and bricks for the foundation, plinth, and wall construction.

Uploaded by

Iqrar Ali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 38

ESTIMATION OF A SIMPLE

BUILDING
PLAN
FOUNDATIONS
SPECIFICATIONS
 Clear height of rooms: 12’
 Clear height of Verandah: 10’-0”
 Plinth level: 1’-6”
 Thickness of roof slab: 4”
 Thickness of RCC shade: 3”
 Depth of RCC Beams in Verandah: 1’-6” below verandah slab
 Parapet wall: 1’-0” (Clear height above roof tiles)
 Ventilators (4 No.): 2’-6” x 1’-6”
 RCC lintel: 6” in depth
 Damp proof coarse: 1 ½”thick PCC (1:2:4) + 2 coats of hot
bitumen + polythene sheet
 Full foundation up to plinth level along verandah periphery is
provided
 Internal finishes: Three coats of white wash/distemper paint
 External finishes: Three coats of Weather shield paint
Center to Center Lengths

 L1 = (10’-0”) + (12’-0”) + (0’-4 ½”) + (0’-4 ½”) +


(0’-4 ½”) = 23’-1 ½”

 S1& S2 = (12’-0”) + (0’-4 ½”) + (0’-4 ½”) = 12’-9”

 S3 = (8’-0”) + (0’-4 ½”) - (0’-4 ½”) = 8’-0”


BILL OF QUANTITIES
1- CIVIL WORKS
S. Description of item No Measurement Quantity Total Quantity Remarks
No
Length Breadth Depth

1 Earthwork for
excavation
in
foundation
trenches
L1 3 25’-7 ½ //
2’-6” 3’-6” 224.22 cft 672.66 cft L = 23’-1 ½”+2’-6” = 25’-7 ½”

S1 2 10’-3” 2’-6” 3’-6” 89.69 cft 179 .38 cft L = 12’-9”-(2’-6)” = 10’-3”

S2 1 10’-3” 2’-1 ½ ” 3’-6” 76.23 cft 76.23 cft L = 12’-9”-(2’-6)” = 10’-3”

S3 2 5’-6” 2’-6” 3’-6” 48.13 cft 96.25 cft L = 8’-0”-(2’-6)” = 5’-6”

Total = 1024.52 cft


2
Earth work in
filing under
floors
Room No.1 1 12’-0” 12’-0” 0’-6 ½ ” 78.00 cft 78.00 cft D = 1’-6”-(0’-11 ½”) = 6 1/2”

Room No.2 1 10’-0” 12’-0” 0’-6 ½ ” 65.00 cft 65.00 cft

Veranda 1 22’-4 ½ ” 7’-3” 0’-6 ½” 87.87 cft 87.87 cft L = 10’-0”+(0’-4½”)+(12’-0”)


= 22’-4 ½”
B = 8’-0”-(0’-9)”= 7’-3”

Total = 230.87 cft

3 Length & Breadth


P.C.C (1:4:8) in
foundation using same as for
crushed or Foundation trenches
broken stones (Item No. 1)

L1 3 25’-7 ½ ” 2’-6” 0’-6” 32.00 cft 96.00 cft

S1 2 10’-3” 2’-6” 0’-6” 12.81 cft 25.63 cft

S2 1 10’-3 2’-1 ½” 0’-6” 10.89 cft 10.89 cft

S3 2 5’-6 2’-6” 0’-6” 6.87 cft 13.75 cft

Total= 146.27 cft


4
Burnt brick work
in foundation and
plinth using first
class bricks in
(1:6) cements
sand mortar.
(a) L1

1st step 3 24’-7 ½ ” 1’-6” 0’-6” 18.47 cft 55.40 cft L = 23’-1½”+(1’-6”) = 24’-7½”

2nd step 3 24’-3” 1’-1 ½ “ 0’-6” 13.64 cft 40.92 cft L = 23’-1½”+(1’-1½”) = 24’-3”

3rd step up to plinth 3 23’-10 ½” 0’-9” 3’-4 ½” 60.43 cft 181.30 L = 23’-1½”+(0’-9”) =
level cft 23’-10½”
D = 2’-0” +(1’-6”) –(0’-1 ½”)
= 3’-4 ½”

Total= 277.62
cft
(b) S1

1st step 2 11’-3” 1’-6” 0’-6” 8.44 cft 16.88 cft L = 12’-9”-(1’-6”) = 11’-3”

2nd step 2 11’-7 ½ ” 1’-1 ½ ” 0’-6” 6.54 cft 13.08 cft L = 12’-9”-( 1’-1½”) = 11’-7½”

3rd step up to plinth 2 12’-0” 0’-9” 3’-4 ½ ” 30.37 cft 60.75 cft L = 12’-9”-( 0’-9”) = 12’-0”
level

Total= 90.71 cft


(c) S2

1st step 1 11’-3” 1’-1 ½ ” 0’-6” 6.33 cft 6.33 cft L = 12’-9”-(1’-6 ”) = 11’-3”

2nd step 1 11’-7 ½ ” 0’-9 ” 0’-6” 4.36 cft 4.36 cft L = 12’-9”-( 1’-1½”)= 11’-7½”

3rd step up to plinth 1 12’-0” 0’-4 ½ ” 3’-4 ½ ” 15.19 cft 15.19 cft L = 12’-9”-( 0’-9”) = 12’-0”
level
Total= 25.88 cft

(d)S3

1st step 2 6’-6” 1’-6” 0’-6” 4.87 cft 9.75 cft L = 8’-0”-(1’6”) = 6’-6’

2nd step 2 6’-10 ½ ” 1’-1 ½” 0’-6” 3.86 cft 7.73 cft L = 8’-0”-(1’-1½”) = 6’-10½”

3rd step up to plinth 2 7’-3” 0’-9” 3’-4 ½ ” 18.35 cft 36.70 cft L = 8’-0”-(0’-9”) = 7’-3”
level
Total= 54.18 cft

(e) steps in front of


verandah

1st step 1 23’-10 ½” 2’-0” 0’-6” 23.88 cft 23.88 cft L = 23’-1½”+(0’-4½”) +
(0’-4½”) =23’-10½”

2nd step 1 23’-10 ½” 1’-0” 0’-6” 11.94 cft 11.94 cft

Total= 35.82 cft

G.Total= 484.21 cft


5 Length &
1-1/2” thick P.C.C
(1:2:4) in DPC Breadth same
including two as for plinth
wall
coats of hot
bitumen & 2
layers of
Polythene sheet
L1 2 23’-10 ½” 0’-9” - 17.9 sft 35.81 sft

S1 2 12’-0” 0’-9” - 9.00 sft 18.00 sft

S2 1 12’-0” 0’-4 ½” - 4.5 sft 4.50 sft

Verandah columns 3 0’-9” 0’-9” - 0.56 sft 1.69 sft

Total = 60.00 sft

Deduction of Door sills 1 4’-0” 0’-9” - 3.00 sft 3.00 sft

1 4’-0’ 0’-4 ½” - 1.50 sft 1.50sft

Total= 4.50 sft

Net Total = 55.50 sft


6 Length & Breadth
Brick work in
super structure same as for plinth
using first class wall
bricks in (1:4)
cement sand
mortar
L1 2 23’-10 ½” 0’-9” 13’-10 ½” 248.45 cft 496.90 cft H = 12’-0” (Room height) +
0’-4” ( Slab) + 0’-4’’ (Earth
filling) + 0’-1”(Mud plaster) +
0’-1½” (Tiles) + 1’-0” (P.
wall)
= 13’-10½”
S1 2 12’-0” 0’-9” 13’-10 ½” 124.87 cft 249.75 cft

S2 1 12’-0” 0’-4½ ” 12’-0” 54.00 cft 54.00 cft No Parapet Walls

Verandah columns 3 0’-9” 0’-9” 8’-6” 4.78 cft 14.34 cft H=10’-0”- (1’-6”)=8’-6”

Verandah parapet walls

(i) L1 1 23’-10 ½” 0’-9” 1’-6 ½” 27.60 cft 27.60 cft H = 0’-4” (Earth filling) + 0’-
1” (Mud plaster) +
0’-1½” (Tiles) + 1’-0” (P.
walls) = 1’-6½”
(ii) S3 2 7’-3” 0’-9” 1’-6 ½ ” 8.38 cft 16.76 cft

Total= 859.35 cft


Deduction
Doors 1 4’-0” 0’-9” 7’-0” 21.00 cft 21.00 cft
1 4’-0” 0’-4 ½ ” 7’-0” 10.5 cft 10.50 cft

Windows 3 4’-0” 0’-9” 4’-0” 12.00 cft 36.0 cft


Ventilators 4 2’-6” 0’-9” 1’--6” 2.81 cft 11.25 cft

Shelves 2 4’-0” 0’-6” 5’-0” 10.00 cft 20.00 cft


RCC lintels over
(i)doors 1 5’-0” 0’-9” 0’-6’ 1.87 cft 1.87 cft
1 5’-0” 0’-4 ½ ” 0’-6’ 0.93 cft 0.93 cft

(ii)Windows 3 5’-0” 0’-9” 0’-6’ 1.87 cft 5.62 cft


(iii)Ventilators 4 3’-6” 0’-9” 0’-6’ 1.31 cft 5.25 cft
(iv)Shelves 2 5’-0” 0’-9” 0’-6’ 1.87 cft 3.75 cft
Total = 116.18 cft
Net Total = 743.17 cft
7 Reinforced There is 4½”
cement bearing of both
concrete slabs on all walls
(1:2:4) as in
roof slab,
lintels,
columns,
beams etc.,
(reinforcement
will be
measured
separately)
Roof slab of 1 23’-1 ½” 12’-9” 0’-4” 98.28 cft 98.28 cft L = 10”-0” + 12’-0” +
rooms 0’-4½” + 0’-9” (2
bearings) = 23’-1½”
B = 12’-0” + 0-
4½”(bearing) + 0’-
4½”(bearing) = 12’-9”
Roof slab of 1 23’-10 ½ ” 8’-4 ½ ” 0’-4” 66.65 cft 66.65 cft B = 8’-0” + 0’-4½”
Verandah (bearing) = 8’-4½”
Verandah
beam
Long beam 1 23’-10½” 0’-9” 1’-6” 26.86 cft 26.86 cft
Short beam 2 7’-7 ½ ” 0’-9” 1’-6” 8.59 cft 17.18 cft L=8’-0”-(0’-9”) + (0’-
4½”) = 7’-7½”
Lintels
Doors 1 5’-0” 0’-9” 0’-6’ 1.87 cft 1.87 cft
1 5’-0” 0’-4½ ” 0’-6’ 0.93 cft 0.93 cft
Windows 3 5’-0” 0’-9” 0’-6’ 1.87 cft 5.62 cft
Ventilators 4 3’-6” 0’-9” 0’-6’ 1.31 cft 5.25 cft
Shelves 2 5’-0” 0’-9” 0’-6’ 1.87 cft 3.75 cft
Shades 2 5’-0” 1’-6” 0’-3” 1.87 cft 3.75 cft
Total= 226.39 cft
8 Mild steel round 6.75 lbs/cft
bars as steel of
reinforcement 226.39 cft
including cutting, concrete
bending, binding
and placing =1528.13
reinforcement in lbs
position
Total= 1529.00 lbs
9 Roof insulation
comprising of 2
coats of hot
bitumen, 4” thick
earth filling, 1”
thick mud plaster
and 1-1/2” thick
brick tiles jointed
and pointed in
cement sand mortar
(1:3)
Rooms (1 & 2) 1 22’-4 ½ ” 12’-0” - 268.50 268.5 sft L = 10’-0”+ (12”-
sft 0”) + (0’-4½”)
= 22’- 4-½”
Verandah 1 22’-4 ½ ” 7’-3” - 162.22 162.22 cft B = 8’- 0”- (0’-9”) =
cft 7’-3”
Total = 430.72 sft
10 Sand under floors
Room No.1 1 10’-0” 12’-0” 0’-6” 60.00 cft 60.00 cft
Room No.2 1 12’-0” 12’-0” 0’-6” 72.00 cft 72.00 cft
Verandah 1 22’-4½ ” 7’-3” 0’-6” 81.11 cft 81.11 cft
Total = 213.11 cft
11 Cement concrete
(1:4:8) as under
layer of floors
Room No.1 1 10’-0” 12’-0” 0’-4” 40.00 cft 40.00 cft
Room No.2 1 12’-0” 12’-0” 0’-4” 48.00 cft 48.00 cft
Verandah 1 22’-4 ½ ” 7’-3” 0’-4” 54.07 cft 54.07 cft
Total = 142.07 cft
12 1-1/2” thick
cement
concrete
(1:2:4) as top
layer of floor,
finished
smooth
Room No.1 1 10’-0” 12’-0” - 120.00 120.00 sft
sft
Room No.2 1 12’-0” 12’-0” - 144.00 144.00 sft
sft
Verandah 1 23’-10 ½” 8’-0” - 191.00 191.00 sft L = 10’-0” + (12’-0”) +
sft (0’-4 ½ ”) + (0’-9”) +
(0’-9”) = 23’-10 ½ ”
Door sill 1 1 4’-0’ 0’-9” - 3.00 sft 3.00 sft
Door sill 1 1 4’-0” 0’-4 ½ - 1.50sft 1.50sft

Total= 459.5 sft
Deduction
Columns 3 0’-9” 0’-9” - 0.56 sft 1.68sft
Net 457.80 sft
Total=
13
½” thick (1:3)
cement sand
plaster to walls
finished smooth
Inner side
Room No.1 (Long wall) 2 12’-0” - 12’-0” 144.00 sft 288.00 sft
Room No.1(Short wall) 2 10’-0” - 12’-0” 120.00 sft 240.00 sft
Room No.1 (Ceiling) 1 10’-0” - 12’-0” 120.00 sft 120.00 sft
Room No.2 (Long wall) 2 12’-0” - 12’-0” 144.00 sft 288.00 sft
Room No.2(Short wall) 2 12’-0” - 12’-0” 144.00 sft 288.00 sft
Room No.2 (Ceiling) 1 12’-0” - 12’-0” 144.00 sft 144.00 sft
Verandah wall 1 23’-10 ½” - 10’-0” 238.75 sft 238.75 sft L = (10’-0”) + (12’-0”) +
(0’-4½ “) +(0’-9”)+ (0’-9”)
= 23’-10 ½ “
Verandah ceiling 1 22’-4 ½” - 7’ –3” 162.26 sft 162.26 sft L = (10’-0”)+(12’-0”)

+(0’-4 ½ “) = 22’-½“

Columns 3 3’-0” - 8’-6” 25.50 sft 76.5 sft L = (0’-9”) + (0’-9”) +


(0’-9”) + (0’-9”) = 3’-0 ”
Long beam (internal 1 22’-4 ½” - 1’-6” 33.55 sft 33.55 sft
side)
Long beam (soffit) 2 10’-9 ¾” - 0’-9” 8.10 sft 16.21 sft L={(22’-4 ½”)-(0’-9”)}/2
=10’-9¾”
Short beam (internal 2 7’-3” - 1’-6” 10.87 sft 21.74 sft L={(8’-0”)-(0’-9”)}
sides) = 7’-3”

Short beam (soffit) 2 7’-3” - 0’-9” 5.43 sft 10.87 sft


Door jambs 2 0’-9” - 7’-0” 5.25 sft 10.50 sft

2 0’-4½” - 7’-0” 2.63 sft 5.25 sft

1 0’-9” - 4’-0” 3.0 sft 1.50 sft


1 0’-4½” - 4’-0” 1.50 sft 3.00 sft

Window jambs 6 0’-9” - 4’-0” 3.00 sft 18.00 sft

6 0’-9” - 4’-0” 3.00 sft 18.00 sft


Ventilator jambs 8 0’-9” - 2’-6” 1.88 sft 15.00 sft

8 0’-9” - 1’-6” 1.19 sft 9.00 sft

Shelves 4 0’-6” - 5’-0” 2.5 sft 10.00 sft


4 0’-6” - 4’-0” 2.0 sft 8.00 sft
Outer side
Rear wall 1 23’-10 ½” - 15’- 379.00 379.00 sft H = (0’-6”) + (1’-6”) +
10½” sft (12’-0”) + (0’-4”) + (0’-
(From 6” below 4’’) + (0’-1”) + (0’-1½”)
G.L. to Parapet + (1’-0”)
walls) = 15’-10½”
Left & Right side 2 13’-6” - 15’- 214.32 428.64 sft L= (12’-0”) + (0’-9”) +
wall 10½” sft (0’-9”)
= 13’-6”
Front side (above 1 23’-10 ½” - 3’-0” 71.63 sft 71.63 sft H = (12’-0”) + 0’-10½”)
verandah roof) + (1’-0”) - (10’-10 ½” )
= 3’-0”
Left & Right side 2 8’-0” - 2’-0” 16.00 sft 32.00 sft H = (1’ – 6’’) + (0’ – 6’’)
plinth of verandah = 2’ – 0’’
Parapet wall
Inner side of rooms 2 22’-4 ½” - 1’-0” 22.37 sft 44.70 sft L = (10’-0”)+(12’-0”)
+(0’-4 ½ “)
= 22’-4 ½ “
2 12’-0” - 1’-0” 12.00 sft 24.00 sft
Inner side of 1 22’-4 ½” - 1’-0” 22.37 sft 22.37 sft
Verandah
2 7’-3 “ - 1’-0” 7.25 sft 14.50 sft
Outer side of 1 23’-10 ½” - 3’- 67.66sft 67.66 sft H = (1’-6”)+(0’-4”)
Verandah 4 ½” +(0’-6 ½”) + (1’-0 “)
= 3’-4 1/2//

2 8’-0” - 2’-10” 22.67 sft 45.33 sft


Top of parapet wall 2 23’-10 ½” - 0’-9” 17.9 sft 35.80 sft
(Rooms)
2 12’-0” - 0’-9” 9.00 sft 18.00 sft
Top of parapet wall 1 23’-10 ½” - 0’-9” 17.90 sft 17.90 sft
(Verandah)
2 7’-3” - 0’-9” 5.43 sft 10.87 sft
Steps
Tread 2 23’-10 ½” - 1’-0” 23.87 sft 47.74 sft
Riser 3 23’-10 ½” - 0’-6” 11.93 sft 35.80 sft
Sides 2 2’ – 00’’ 0’-6” 1.00 sft 2.00 sft
2 1’ – 00’’ 0’-6” 0.5 sft 1.00 sft
Total= 3316.07 sft
Deduction
Doors 2 4’-0’ - 7’-0” 28.00 sft 56.00 sft
Windows 3 4’-0’ - 4’-0” 16.00 sft 48.00 sft
Ventilators 4 2’-6” - 1’-6” 3.75 sft 15.00 sft
Total= 119.00 sft
Net Total= 3197.07 sft
14 Wood work as
in
(i) 1 ½” thick 2 4’-0’ - 7’-0” 28.00 sft 56.00 sft
wooden doors
with chowkat,.
Total = 56.00 sft
(ii) Glazed and 3 4’-0’ - 4’-0” 16.00 sft 48.00 sft
gauzed windows
and ventilators.
4 2’-6’ - 1’-6” 3.75 sft 15.00 sft
Total = 63.00 sft
G.Total 119.00 sft
=
15 Three coats of - - - - - .(2 x Qty of item
painting to No.14)
doors , = 238.0 sft
windows and
ventilators
Total 238.00 sft
16 Three coats of
distempering/
white washing to
walls (Internal
Side)
Room No.1 2 12’-0” - 12’-0” 144.00 sft 288.00 sft
(Long wall)
Room No.1 2 10’-0” - 12’-0” 120.00 sft 240.00 sft
(Short wall)
Room No.1 (Ceiling) 1 10’-0” - 12’-0” 120.00 sft 120.00 sft
Room No.2 2 12’-0” - 12’-0” 144.00 sft 288.00 sft
(Long wall)
Room No.2 2 12’-0” - 12’-0” 144.00 sft 288.00 sft
(Short wall)
Room No.2 (Ceiling) 1 12’-0” - 12’-0” 144.00 sft 144.00 sft
Verandah wall 1 23’-10 ½” - 10’-0” 238.75 sft 238.75 sft
Verandah Ceiling 1 22’-4 ½” - 7’ –3” 162.26 sft 162.26 sft
Columns 3 3’-0” - 8’-6” 25.50 sft 76.50 sft
Long beam (sides) 1 22’-4 ½” - 1’-6” 33.55 sft 33.55 sft
Long beam (soffit) 2 10’-9 ¾” - 0’-9” 8.10 sft 16.21 sft L= {(22’-4 ½”)-(0’-9”)}/2
= 10’-9¾”
Short beam (sides) 2 7’-3” - 1’-6” 10.87 sft 21.74 sft
Short beam (soffit) 2 7’-3” - 0’-9” 5.43 sft 10.87 sft
Door jambs 2 0’-9” - 7’-0” 5.25 sft 10.50 sft
2 0’-4½” - 7’-0” 2.63 sft 5.25 sft
1 0’-9” - 4’-0” 3.0 sft 1.50 sft
1 0’-4½” - 4’-0” 1.50 sft 3.00 sft
Window jambs 6 0’-9” - 4’-0” 3.00 sft 18.00 sft
6 0’-9” - 4’-0” 3.00 sft 18.00 sft
Ventilator jambs 8 0’-9” - 2’-6” 1.88 sft 15.00 sft
8 0’-9” - 1’-6” 1.19 sft 9.00 sft
Shelves 4 0’-6” - 5’-0” 2.5 sft 10.00 sft
4 0’-6” - 4’-0” 2.0 sft 10.00 sft
Total = 2017.16 sft
Deduction
Doors 4 4’-0’ - 7’-0” 28.00 sft 112.00 sft
Windows 4 4’-0’ - 4’-0” 16.00 sft 64.00 sft
Ventilators 6 2’-6” - 1’-6” 3.75 sft 22.50 sft
Total= 142.5 sft
Net 1874.66 sft
Total =
17 Three coats of
Weather shield
paint to walls.
(External side)
Rear wall 1 23’-10 ½” - 15’-4½” 367.07 sft 367.07 sft H = ={(15’-10 ½”)-
(0’-6”) = 15’-4 1/2”
Left & Right side wall 2 13’-6” - 15’-4½” 207.5 sft 415.13 sft
Front side (above 1 23’-10½” - 3’-0” 71.63 sft 71.63 sft
verandah roof)
Left & Right side wall 2 8’-0” - 2’-0” 16.00 sft 32.00 sft
of verandah
Parapet wall
Inner side of rooms 2 22’-4 ½” - 1’-0” 22.37 sft 44.70 sft
2 12’-0” - 1’-0” 12.00 sft 24.00 sft
Inner side of 1 22’-4 ½” - 1’-0” 22.37 sft 22.37 sft
Verandah
2 7’-3” - 1’-0” 7.25 sft 14.50 sft
Outer side of 1 23’-10½” - 2’-10½ ” 67.66 sft 67.66 sft
Verandah
2 8’-0” - 2’-10½ ” 22.67 sft 45.32 sft
Top of parapet wall 2 23’-10 ½” - 0’-9” 17.9 sft 35.80 sft
(Rooms)
2 12’-0” - 0’-9” 9.00 sft 18.00 sft
Top of parapet wall 1 23’-10 ½” - 0’-9” 17.90 sft 17.90 sft
(Rooms)
2 7’-3” - 0’-9” 5.43 sft 10.87 sft
Total= 1186.95 sft
Deduction

Windows 2 4’-0’ - 4’-0” 16.00 sft 32.00 sft


Ventilators 2 2’-6” - 1’-6” 3.75 sft 7.50 sft
Total= 39.50 sft
Net 1147.45 sft
Total=
ABSTRACT OF QUANTITIES
1- CALCULATIONS

1. Excavation in Medium soil

Quantity from BOQ item No. 1 = 1024.52 cft

Output of one labourer working 8 hrs = 75 cft

04 labourers are required for 3 ½ days to


excavate 1050 cft earth.
2. PCC (1:4:8)
Quantity of BOQ item No.3 (Foundations) = 146.27 cft
Quantity of BOQ item No.11 (Floors) = 142.07 cft
Total = 288.34 cft
Dry material for 100 cft of cement concrete = 154 cft

Note:
Materials
(i) Cement=154x1x288.34/(100x13) = 34.15cft
(ii) Sand=154x4x288.34/(100x13) = 136.62 cft
(iii) Coarse aggregate
=154x8x288.34/(100x13) = 273.25 cft
3. Ist Class Burnt brick work in foundation
in cement sand mortar (1:6)
Quantity of BOQ item No.4 = 484.21 cft

Note: Bricks for 100 cft of brick work = 1350 Nos.


Dry mortar for 100 cft of brik work = 30 cft

Material
(i) Bricks=1350x484.21/100 = 6537 Nos.
(ii) Cement=30x1x484.21/(7x100) = 20.75 cft
(iii) Sand=30x6x484.21/(7x100) = 124.51cft
4. 1 ½” thick PCC (1:2:4) in DPC including
two coats of hot bitumen & 2 sheets of
Polythene.
Quantity of BOQ item No.5=55.50x0.125 = 6.93 cft

Note: (i) Dry material for 100 cft of cement concrete = 154 cft
(ii) Bitumen for 100 sft of DPC (first coat) = 15 Kg
(iii) Bitumen for 100 sft of DPC (second coat) = 10 Kg

Material
(i) Cement=154x1x6.93/(100x7) = 1.52 cft
(ii) Sand=154x2x6.93/(100x7) = 3.04 cft
(iii) Coarse aggregate=154x4x6.93/(100x7) = 6.09 cft
(iv) Bitumen =25x55.50/100 = 13.87 Kg
(v) Polythene Sheet (2 x 55.5) = 111.0 sft
5. Ist Class Burnt brick work in Super
structure in cement sand mortar (1:4)

Quantity of BOQ item No.6 = 743.17 cft

Note: (i) Bricks for 100 cft of brick work = 1350 Nos.

(ii) Dry mortar for 100 cft of brik work = 30 cft

Material

(i) Bricks=1350x743.17/100 = 10033 Nos.

(ii) Cement=30x1x743.17/(5x100) = 44.59 cft

(iii) Sand=30x4x747.13/(5x100) = 178.36 cft


6. Reinforced cement concrete (1:2:4)
Quantity of BOQ item No.7 = 226.39 cft

Note: Dry material for 100 cft of cement = 154 cft


concrete

Materials
(i) Cement=154x1x226.39/(100x7) = 49.80 cft
(ii) Sand=154x2x226.39/(100x7) = 99.61 cft
(iii) Coarse aggregate
=154x4x226.39/(100x7) = 199.22 cft
(iv) Mild steel round bars = 1529 lbs
= 693.55 Kg
(Note: 1 Kg = 0.454 lbs)
7. Roof insulation
Quantity of BOQ item No.9 = 430.72 sft

Note: (i) Brick tiles for 100 sft roof insulation = 360 Nos.
(ii) Dry mortar for 100 sft = 9.00 cft
(iii) Bitumen for 100 sft of DPC (first coat) = 15 Kg
(iv) Bitumen for 100 sft of DPC
(second coat) = 10 Kg
Material
(i) 1 ½” thick brick tiles = 1551 Nos.
(ii) Cement=9x1x430.72/(4x100) = 9.69 cft
(iii) Sand=9x4x430.72/(4x100) = 29.07 cft
(iv) Bitumen =430.72/100 = 107.68 Kg
(v) Mud /Earth filling=430.72x0.42 = 180.90 cft
(Vi) Polythene sheet (2 x 430.72) = 862 sft
8. Sand under floors
Quantity of BOQ item No.10 = 213.11 cft
Material
Sand = 213.11 cft
9. 1 ½” thick cement concrete (1:2:4) in
floors
Quantity of BOQ item No.12=457.80x0.125 = 57.23 cft

Note: (i) 1 ½” = 0.125 ft = 154 cft


(ii) Dry material for 100 cft of cement
concrete
Materials
(i) Cement=154x1x57.23/(100x7) = 12.59 cft
(ii) Sand=154x2x57.23/(100x7) = 25.18 cft
(iii) Coarse aggregate
=154x4x57.23/(100x7) = 50.36 cft
10. 1/2” thick cement plaster in cement sand
mortar (1:3)
Quantity of BOQ item No.13 = 3197.07 sft

Note: Dry mortar for 100 sft of ½” thick cement plaster = 6 cft

Material
(i) Cement=6x1x 3197.07/(4x100) = 47.96 cft
(ii) Sand=6x3x 3197.07/(4x100) = 143.87 cft

11. Wood work in door, windows ventilators


Quantity of BOQ item No.14 (i) Doors = 56.00 sft
Quantity of BOQ item No.14 (ii) Windows = 63.00 sft

Note: (i) Timber for 100 sft of Panelled Doors = 13 cft


(ii) Timber for 100 sft of Glazed windows and
Ventilators = 8 cft

Material
(i) Timber for doors =13x56/100 = 7.28 cft
(ii) Timber for windows and Ventilators = 5.04 cft
=8x63/100
Total = 13.32 cft
12. White wash / Distemper
Quantity of BOQ item No.16 = 1872.9 sft
Note: Lime for 100 sft of white wash (one coat) = 1.00 Kg

Material
Lime for three coats=1x3x1872.9/100 = 56.24 Kg

13. Weather Shield


Quantity of BOQ item No.17 = 1143.45 sft

14. Earth filling under floors


Quantity of BOQ item No.2 = 230.87 cft

Material
Earth for filling = 230.87 cft
2- SUMMARY
S.No. Description of material Quantity

1. Cement 220.68 cft or


(From 2,3,4,5,6,7,9,10) 177 Bags
2. Sand 740.26 cft
(From 2,3,4,5,6,7,9,10)
3. Coarse aggregate 528.92 cft
(From 2,4,6,9)
4. Mild steel round bars (item No: 6) 693.55 Kg
5 Burnt bricks 1st class 16570 Nos.
(From 3,5)
6 1/2” thick Brick tiles (item No: 7) 1551 Nos.
7 Bitumen 121.55 Kg
(From 4,7)
8 Polythene sheet 973 sft
(From 4,7)
9. Timber 13.32 cft
(item No: 11)
10. Lime 56.24 Kg
(item No: 12)

11. Mud/Earth filling 411.77 cft


(From 7,13)