Rev 1
Rev 1
• Stability Test
Factory
• Quality Control
• Factory Acceptance Test
Commissioning
• Site Acceptance Test
• Start-up
Maintenance
• Reduce maintenance requirement
• Troubleshooting
• Warranty Claims
• After Warranty maintenance
GIS Testing Needs : What
Contact Resistance
Overall circuit low
resistance measurement.
Circuit Breaker
1- Timing
2- Coil current & voltage
3- Arcing contact condition\
lenth
4- Motor current
5- Travel
GIS Testing Needs : What
Switches
1- Motor current
2- Maneuver shaft travel
Instrument transformers
1- CT
2- VT
Insulation
1- SF6 condition
2- Partial discharge
Testing Challenges
GIS configuration
dependent Interlocks
Access to grounding
No access to primary links
terminal
Primary terminal not accessible for testing
Access to primary conductor through grounding links
Access to primary conductor through grounding links
Access to primary conductor through grounding links
Grounding links removed for testing
Grounding links removed for testing
Grounding links removed for testing
When possible
Alternative testing techniques
Dual ground
Contact Resistance Test
Testing Procedures
Measure Contact Resistance
Equipment Required
Injection Kit: MOM690
Contact Resistance Test
Testing Procedures
Measure Contact Resistance
Equipment Required
Injection Kit: MOM690
Testing Procedures
DualGround Contact Resistance
Equipment Required
Injection Kit: MJÖLNER 600 Micro-ohmmeter
DualGround Method
- No modifications to GIS.
- Run test.
- Measures ground path escape current.
- R= U \ (Igen – Ignd ).
- Follow connection loop done in factory to compare results
with factory test results.
Contact Resistance Test
DualGround Method
Testing Procedures
Measure Circuit Breaker Time
Equipment Required
Injection Kit: TM1600 + B10E
• Close Circuit 1
• +VE B10E \ TM1600 Input
• -VE B10E \ X0C 2
• TM1600 Close Coil Output \ X0C 1
Connection Circuit Ferruling
• Trip Circuit 1
• TM1600 Trip Coil Output \ X0C 4
• -VE B10E \ X0C 6
• Trip Circuit 2
• TM1600 Trip Coil Output \ X0C 7
• -VE B10E \ X0C 9
Circuit Breaker Timing
Testing Procedures
DualGround Timing Test
Equipment Required
Injection Kit: TM1800 Circuit Breaker Analyzer System
DualGround Method
- No modifications required.
- Dynamic capacitance measurement (DCM) technique.
- Accessories: DCM + Ferrites
- Ferrites block high frequency
.
Circuit Breaker Timing
Testing Procedures
Measure Earth Switch Time
Equipment Required
Injection Kit: TM1600 + B10E
Testing Procedures
Measure Earth Switch Time
Equipment Required
Injection Kit: TM1600 + B10E
Testing Procedures
Measure Bus Disconnect Time
Equipment Required
Injection Kit: TM1600 + B10E
Testing Procedures
Measure Leakage Current
Equipment Required
Injection Kit: DELTA4010
Instrument Transformers
VTs
CTs
CTs and VTs: Testing Challenges
• Interlocks.
• Protection scheme
Bus differential
Current Transformer Test
Current Transformer Test
Current Transformer Test
Testing Procedures
Insulation Resistance Test
Equipment Required
Injection Kit: MRCT
Current Transformer Test
Testing Procedures
- Secondary Winding Resistance
- Saturation (Excitation Current)
Current Transformer Test
Testing Procedures
- TTR and Polarity
Connecting to an MRCT
PowerDB Software
Connecting to an MRCT
PowerDB Software
Current Transformer Test
PowerDB Software
Current Transformer Test
•Connection on CT Analyzer will be
same as the shown figure.
Testing Procedures
Primary Injection Test
Equipment Required
Injection Kit: LET-2000-RD
Primary Injection Test
Testing Procedures
- Ratio and Polarity
Voltage Transformer Test
Testing Procedures
Insulation Resistance Test
Secondary to Ground
Equipment Required
Injection Kit: MRCT
Voltage Transformer Test
Testing Procedures
- Secondary Winding Resistance
Voltage Transformer Test
Testing Procedures
- Ratio and Polarity
PD in GIS
Simplified cross section of a GIS
PD in GIS
Simplified cross section of a GIS
• Homogenous electrical field by design
• Electrical field strength below critical field strength
PD in GIS
Simplified cross section of a GIS
• Inhomogeneous electrical field due to imperfection
• Electrical field strength above critical field strength
• Partial discharge inception
PD in GIS
Partial discharge emit energy as
• electromagnetic emissions, in the form of radio waves
• Acoustic emissions in the audible and ultrasonic ranges
• Chemical byproducts
Disconnector
Voltage Transformer
Current Transformer
Circuit Breaker
Current Transformer Testing
.Multimeter
Testing Procedures
CHECKING OF OPERATION AND INDICATIONS LCC
Circuit Breaker Timing
Testing Procedures
CHECKING OF OPERATION AND INDICATIONS LCC
Circuit Breaker Timing
Testing Procedures
CHECKING OF OPERATION AND INDICATIONS CR
Circuit Breaker Timing
Testing Procedures
CHECKING OF OPERATION AND INDICATIONS CR
Circuit Breaker Timing
Testing Procedures
CHECKING OF OPERATION AND INDICATIONS FMK
Circuit Breaker Timing
Testing Procedures
CHECKING OF OPERATION AND INDICATIONS FMK