Week 5
Week 5
Engineering
Department of Electrical Engineering
Lecture#2
1
Problem
A 100 MVA, 33kV, 3-phase generator has a subtransient reluctance of
15%. The generator is connected to 3 motors through a transmission line
and transformers as shown in the single line diagram. Selecting the
generator ratings as the base quantities, determine the base quantities and
p.u. values in other parts of the system. Also draw the reactance diagram of
the system.
Solution
Solution
Economic Operation
• Power generated at stations, transmitted, distributed and
utilized at user end
• DISCOs and GENCOs aim to minimize cost
• Major component of this cost is fuel cost
• Significant in thermal and nuclear power plants
• Thermal power plant
• Boiler, turbine, generator
Generator operating cost of
thermal power unit
• Unit consists of a set of boiler, turbine and generator
• Fuel cost curve
• Below MWmin, operation is technically not feasible or
not economical
• Each unit at power system has its own cost curve
Cost Curve
• Cost function 1
Ci ai PGi2 bi PGi d i
2
dCi
• Incremental cost ai PGi bi
dPGi
• If demand is PD and capacity of each unit is Pmax,i , then for
k
‘k’ units Pmax,i PD
i 1
• Constraint
PGi , min PGi PGi , max
P
i 1
Gi PD
Cost Curve
• Objective function k
min C Ci PGi
i 1
k
subject to P
i 1
Gi PD 0
• Optimization Problem (multi-variable optimization with
equality constraints)
• No. of variables?
• How to solve this optimization problem?
Lagrange Method
• Lagrange function
k
k
L( PGi ) Ci PGi PGi PD
i 1 i 1
P
i 1
Gi PD PL 0
Langrange function
k
k
L( PGi ) Ci PGi PGi PD PL
i 1 i 1
L dCi PL
0 (1 0 )0
PGi dPGi PGi
dCi PL
(1 )
dPGi PGi
Optimum load dispatch
considering transmission losses
dCi
dPGi
PL
1
PGi
dCi 1
Li Li
dPGi PL
1
PGi
where L is known as penalty factor at ‘i’th plant
1
• Can also be expressed as
Li where ITL is
1 ITLi
incremental transmission loss at ‘i’th plant
• Here λ is incremental cost of received power ($/MWh)
Dependence of PL on PG using
B-Loss coefficients method k k
PL PGm Bmn PGn
m 1 n 1
• Where PGm is generation at ‘mth’ plant and Bmn Bnmis loss
coefficient which is constant under certain assumptions.
• In matrix form, we have
PG1 B11 B12 B1k
P B B22 B2 k
T
PL P BPG
G , PG G 2 , B 21
P
Gt Bk 1 Bk 2 Bkk
PL B11 PG21 B22 PG22 B33 PG23 2 B12 PG1 PG 2 2 B13 PG1 PG 3 2 B23 PG 2 PG 3
• So, we have
PL k k
PGi
PGi m 1 n 1
PGm Bmn PGn
k k k k
PGm Bmn PGn PGi Bin PGn PGm Bmi PGi PGi Bii PGi
PGi m 1,m i n 1, n i n 1, n i m 1, m i
• Total number of terms = k 2
2
• Total number of terms independent of Gi =
P ( k 1)
dCi PL
• And (1 )
dPGi PGi
• Therefore, k
ai PGi bi 1 2 Bij PGj
j 1
Dependence of PL on PG using
B-Loss coefficients method
k
ai PGi bi 2 Bij PGj
j 1
k
ai PGi bi 2 Bii PGi 2 Bij PGj
j 1
j i
k
( ai 2Bii ) PGi bi 2 Bij PGj
j 1
j i
k
bi
1 2 Bij PGj
j 1
j i
PGi
ai
( 2 Bii )
Solving Economic Dispatch
considering transmission line losses
1. Assume suitable value of λ (should be greater than largest
value of bi)
2. Calculate PGj using simple incremental cost principle.
3. Solve the equation for PGi iteratively.
k
bi
1 2 Bij PGj
j 1
j i
PGi
ai
( 2 Bii )
k k
4. Calculate PL PGm Bmn PGn
m 1 n 1
5. If P
i 1
Gi PD PL , stop iteration
Solving Economic Dispatch
considering transmission line losses
k
• Else if PGi PD PL 0 , then increase λ
i 1
k
• Else if P i 1
Gi PD PL 0
, then decrease λ
6. Then go to step 2
Problem
• Determine the economic operating schedule of two plant
system to meet a load demand of 160MW.The incremental
fuel costs and loss coefficients of the two plants are given
below
dC1 dC2
0.01PG1 2 $ / MWh 0.01PG 2 1.5 $ / MWh
dPG1 dPG 2
When the load increases, the utility has to decide in advance the sequence in
which the generator units are to be brought in. Similarly, when the load
decreases, the operating engineer need to know in advance the sequence in
which the generating units are to be shut down.
The problem of finding the order in which the units are to be brought in and the
order in which the units are to be shut down over a period of time, say one day,
so the total operating cost involved on that day is minimum, is known as Unit
Commitment (UC) problem. Thus UC problem is economic dispatch over a day.
The period considered may a week, month or a year.
But why is this problem in the operation of electric power system? Why not
just simply commit enough units to cover the maximum system load and leave
them running? Note that to “commit” means a generating unit is to be “turned
on”; that is, bring the unit up to speed, synchronize it to the system and make
it to deliver power to the network. “Commit enough units and leave them on
line” is one solution. However, it is quite expensive to run too many
generating units when the load is not large enough. As seen in previous
example, a great deal of money can be saved by turning units off
(decommiting them) when they are not needed.
Example 7
The following are data pertaining to three units in a plant. Unit 1: Min. =
150 MW; Max. = 600 MW
C1 = 5610 + 79.2 P1 + 0.01562 P 2 Rs / h
1
Note that the least expensive way of meeting the load is not with all the three
units running, or any combination involving two units. Rather it is economical
to run unit one alone.
Example 8
Daily load curve to be met by a plant having three units is shown below.
1200
MW
500
MW
12 noon 4 pm 8 pm 2 am 6 am 12 noon
Data pertaining to the three units are the same in previous example.
Starting from the load of 1200 MW, taking steps of 50 MW find the shut-
down rule.
Solution
For each load starting from 1200 MW to 500 MW in steps of 50 MW, we simply
use a brute-force technique wherein all combinations of units will be tried as
in previous example. The results obtained are shown below.
Optimum combination
Load
Unit 1 Unit 2 Unit 3
1200 On On On
1150 On On On
1100 On On On
1050 On On On
1000 On On Off
950 On On Off
900 On On Off
850 On On Off
800 On On Off
750 On On Off
700 On On Off
650 On On Off
600 On Off Off
550 On Off Off
500 On Off Off
Optimum combination
Load
Unit 1 Unit 2 Unit 3
1200 On On On
1150 On On On
1100 On On On
1050 On On On
1000 On On Off
950 On On Off
900 On On Off
850 On On Off
800 On On Off
750 On On Off
700 On On Off
650 On On Off
600 On Off Off
550 On Off Off
500 On Off Off
Example 9
A strict priority order for these units, based on the average production cost,
would order them as follows:
Combination Load PD
2+1+3 1000 MW ≤ PD < 1200
MW
2+1
2 400 MW ≤ PD < 1000
MW PD < 400 MW
Note that such a scheme would not give the same shut – down sequence
described in Example 7 wherein unit 2 was shut down at 600 MW leaving
unit 1. With the priority – list scheme both units would be held on until load
reached 400 MW, then unit 1 would be dropped.
Unit Commitment
• Process of deciding when and which generating units at each power station to
start-up and shut-down
• Economic dispatch is the process of deciding what the individual power
outputs should be of the scheduled generating units at each time-point.
• Unit commitment table
• Dependent on total demand at every time instant
• Generally prepared by dynamic programming
• Corresponding to each demand
• Optimal combination of units
• Optimal loading on selected combination of units
• Suppose at any time instant, PD 8MW. How many units to operate? Which
units to operate? (Unit commitment)
Unit Commitment Table
• If only one unit, then
1
F1 (8) f1 (8) ai PGi2 bi PGi d i 232 ($ / h)
2
• So cost is 232 $/h if demand (8MW) is met by unit ‘1’ alone
F3 (8) min f 3 ( y ) F2 (8 y )
f 3 (1) F 2(7) , f 3 ( 2) F 2(6) , f 3 (3) F 2(5) , f 3 ( 4) F 2(4) ,
min
f 3 (5) F 2 (3) , f 3 ( 6) F 2 ( 2) , f 3 ( 7 ) F 2 (1)
Example of Unit Commitment
Table
Quiz
???
53